Title: Dan Dolan
1Who Will Build the Resources for the Future?
- Dan Dolan Vice President
- Electric Power Supply Association
- September 2008
www.epsa.org
2What is EPSA?
- The national trade association of competitive
power sector - Nearly 40 of installed generating capacity
- Competitive sector built almost all new
generation since early 1990s - New generation was largely at suppliers risk,
not at ratepayer expense - Nearly all wind generation is being built by
competitive suppliers
3(No Transcript)
4Wind Projects Completed in 2008
Rate-Base Construction 13
Competitive Suppliers 87
Total Capacity (MW)
Percentage of Total Capacity
American Wind Energy Association, 2nd Quarter
2008 Market Report, August 5, 2008
5Wind Projects Under Construction
Rate-Base Construction 6
Competitive Suppliers 94
Total Capacity (MW)
Percentage of Total Capacity
American Wind Energy Association, 2nd Quarter
2008 Market Report, August 5, 2008
6Build versus BuyWho Bears the Risk?
- Utility cost-over runs
- Competitive suppliers risk management
- New technologies
- Large investments
7Joint Federal/State Report
- The FERC and NARUC on July 20 jointly released a
report of "best practices" to ensure a fair and
objective system of encouraging robust
competition for utility resource needs. - The report is titled Competitive Procurement of
Retail Electricity Supply Recent Trends in State
Policies and Utility Practices and was prepared
by the Analysis Group. Available at
www.naruc.org.
8FERC/NARUC Report Quotes
- "...because the large capital investments
necessary for development of these types of
resources pose potentially valuable opportunities
for utilities to enter new resources into rate
base, commissions should be aware that utilities
may attempt to shield such projects from
competition even in situations where market
processes are applicable. Despite these
challenges, the potential economic gains from
imposing the market discipline of competitive
procurements on development of capital-intensive
and advanced technologies may be great." (p. 19,
emphasis added)
9FERC/NARUC Report Quotes
- "Because the utility's (and/or its parent's)
financial interests may not be aligned with those
of its customers when the utility selects from
among the options, extra care is needed to
prevent improper self-dealing by the utility.
Best practices under these circumstances require
a higher degree of regulatory supervision and
scrutiny..." (p. 12, emphasis added) - "...as many states have determined, the benefits
of independent monitors of competitive
procurements seem to outweigh these costs in
most instances, and are a necessary element
of a credible process where the utility itself
has a financial stake in the outcome of the
competitive procurement itself." (p. 22, emphasis
added)
10Change the Way We Think of New Electricity
Supplies
11Credible Solicitations
- Collaborative Process
- Local utility submits recommended approach
- Multi-day, commission-facilitated collaborative
meetings - State Commission resolves outstanding issues
- Independent, Third-party Evaluator
- Performs independent evaluation of the bids
- Monitors communication between the utility,
affiliate - Benefit Extra pair of eyes
12Credible Solicitations (cont.)
- Fair Process Must
- Be free from actual, apparent conflicts of
interest - Provide all bidders similar access to information
- Require full public review of the utility
decision-making process - If the utility or affiliated entity participates,
additional protections are required - Use of an independent evaluator - reports to
commission - Separation of utility personnel - utilitys
proposal vs. evaluating bids - Utility winner must honor its bid prices
13- Dan Dolan
- Vice President,
- Policy Research Analysis
- Electric Power Supply Association
- 1401 New York Ave., NW
- 11th Floor
- Washington, DC 20005
- Telephone (202) 628-8200
- Fax (202) 628-8260
- E-mail ddolan_at_epsa.org
- Website www.epsa.org