Title: Engineering Management
1Engineering Management
- Assistant Prof. Dr. Korb Srinavin
2Outline
- ????????????????????????
- ??????????????????????????????
- ????????????
- ??????????????????????
- ??????????????
- ?????????????????????
- ????????????????????????????
3- ?????????????????? ???????????????
- ???????????????????????????
- ??????????????????????
- ????????????????????????
- ?????????????????
- ????????????????
4- ?????????????????????????????
- ??????????????????????????????????????????????????
???? - ????????????????????
5?????????????????????(Budgeting and Estimates)
6
- BUDGET FOR CONSTRUCTION PROJECTS
- In all organizations, a construction project is a
capital investment project. Budgeting for the
project will, therefore, be different from annual
budgets for the organization. - Budgeting in organization
- The usual approach in most organizations is to
base next year's budget on this year's budget and
expenses. A percentage is then added based on
anticipated cost increases, thus - Next year's budget This year's budget X,
- The value X may be based on
- 1. Get feelings,
- 2. Inflation forecasts,
- 3. Additional plans made.
6Major approaches
- 1. Top-down budgeting
- Management has been said to be better at
judging overall project costs than the cost of
individual parts. Top down budgeting may vary
from an assessment of probable cost by
individuals, costs generated through consensus of
experts' is then broken down to individual parts.
The broken down may use factors generated from
experience. This approach leaves the setting of
overall budget to the top management while lower
level managers have to distribute budget
allocated to them to parts under them. Using this
approach, overall budgets may be accurate while
errors are infighting between lower level
managers.
7- 2. Bottom-up budgeting
- In this approach, costs are calculated for
individual parts and then summed up for the whole
project. There is thus the need to ensure that
all parts are included. A major failing is that
individuals may tend to "overstate" budgetary
requirements in the knowledge that top management
will reduce the budget. However, the approach
lead to participative management making the lower
levels not to feel that budgets are imposed. - 3. Mixed approaches
- Top management may call for budget requests and
then use suggestions to make a budget that is
distributed down the organization.
8Budgeting for construction projects
24 June 2005
- Construction project budgets are, ideally based
on estimates of costs of construction resources.
However, most budgets are set before design is
finalized. It thus means that there will be much
reliance on historical costs. In practice,
typical approaches that may be used are - 1. Setting a fixed amount to which design should
conform. - 2. Using updated historical unit cost records to
generate overall costs which is then distributed
to parts. The overall cost will have professional
fees added together with other expenses. - 3. If the development of the design permits it,
resource costs may be calculated and even project
plans may be used for this purpose to make the
budget time-related.
9- Important notes
- 1.A budget depends on estimates. Budgets are good
to the extent that estimates are good. - 2.Estimates are made by people with preferences.
- 3.Budgets made early can be used to control the
design process.
10TENDERING BIDDING AND CONTRACTS
- Contract strategies
- 1. Choice of contractor,
- 2. Method of selecting contractor,
- 3. Organization structure to control design,
construction and interfacing of the both, - 4. Selection of the content and sequencing of
work package, - 5. Tender documents, including contract
condition, risk allocation.
11- The tendering procedure
- 1. Open tendering
- 2. Selective tendering
- 3. Serial tendering
- 4. Negotiation tendering
12- 1. Open tendering
- The project is advertised for all qualified
contractors to submit a bid. The job can be
advertised in several ways such as trade
magazine, public advertisement or local
newspapers, designers, agency bid lists,
organization - plan service centers and national
publications. - Advantage Disadvantages
- More choice Too many bidders,
- Definitely competitive Higher possibility of
low bids
13- 2. Selective tendering
- The project owner may decide to limit the number
of contractors (reasonably, 6-8 contractors)
allowed to submit bids for the project. This may
be done by having approved lists of contractors,
then use selectively approaching contractors
known to the owner.
14- 3. Serial tendering
- This method of tendering is for continuing work
(which the work is done in stages).
15- 4. Negotiation tendering
- This method of tendering is that a good
contractor may be asked to tender alone for the
job and the price negotiated with the firm. In
other words, the owner prior accepted the
contractor performance (and intent the contractor
to perform the job) but still need to negotiate
the cost of project with the contractor prior
proceeding.
16Approved lists of the contractors
- The owner may have an approved list of
contractors for project. The propose is to limit
the number of bids received for any project and
monitor the quality of services received from
contractors. The process of getting into the
approved list is known as "pre-qualification" or
"pre-selection".
17- Criteria for pre-qualification
- 1. References, reputations and past performances,
- 2. Financial stability,
- 3. Technical expertise.
- Criteria for pre-selection
- 1. References, reputations and past performances,
- 2. Financial stability,
- 3. Technical expertise,
- then add some additional criteria such as
- 4. Status of current work program,
- 5. Project-specific criteria.
-
- In many instances, the two procedures are
referred to as "pre-qualification".
18- Disadvantages of pre-qualification
- 1. The need to continuously update information in
changing market situation, - 2. Indiscriminate distribution of company
secrets,
19- Decision to tender
- A good contractor does not need to tender for
every job available in the market. The decision
to tender is based on two (2) major
considerations as follows
201. Information supplied
- 1.1 The name of the job,
- 1.2 The name of client and designers,
- 1.3 The name of any consultants with supervisory
duties, - 1.4 Location of site,
- 1.5 A general description of the work,
- 1.6 The approximate cost range of the project,
- 1.7 Details of any nominated sub-contractors/supp
lier, - 1.8 The form of contract to be used,
- 1.9 The procedure to be adopted in examining
bids, - 1.10 Whether contract is to be under seal or
under hand, - 1.11 Anticipated date of possession of site,
- 1.12 The period of completion of the works,
- 1.13 The duration of the tender period,
- 1.14 The period for which the tender is to
remain open, - 1.15 The anticipated value of liquidated damage
(if any), - 1.16 Details of bond requirements (if any),
- 1.17 Any particular conditions relating to the
contract.
212. Company consideration
- 2.1 The company's current workload, turnover and
recovery of overheads, - 2.2 The company's financial resources,
- 2.3 The availability of resources to undertake
the job, - 2.4 Type of work,
- 2.5 Location of the contract,
- 2.6 The identity of the client or promoter and
his/her representatives, - 2.7 A detailed examination of the contract
documents. - If the company decides to tender, an of
cost is prepared and a tender submitted in
accordance with owner's requirements. Normally,
estimate preparation will only be done after
through "site investigation".
22Estimating process
- The following steps describe the process of
producing a cost estimate by the contractor as a
basis for tender submittal - 1. Decision to tender,
- 2. Programming the estimate,
- 3. Collection and calculation of cost information
- 3.1 Labour,
- 3.2 Plant,
- 3.3 Materials,
- 3.4 Sub-contractors,
23- 4. Project study
- 4.1 Drawings,
- 4.2 Site visit,
- 4.2.1 Description of site,
- 4.2.2 Position of existing services,
- 4.2.3 Description of ground conditions,
- 4.2.4 Any problem related to the security of
the site, - 4.2.5 A description of the access to the site,
- 4.2.6 Topographic details of the site,
- 4.2.7 A description of the facilities available
for the disposal of soil, - 4.2.8 A description of any demolition works of
temporary works to adjoining building, - 4.3 Method statement
24- 5. Preparing the estimate
- 5.1 Operational estimating,
- 5.2 Unit rate estimating,
- 5.3 Combined method, operational and unit rate
estimating, - 6. Site overheads
- 6.1 Site staff,
- 6.2 Cleaning site and clearing rubbish,
- 6.3 Site transport facilities,
- 6.4 Mechanical plant which is not included in
item rates, - 6.5 Scaffolding and gantries,
- 6.6 Site accommodation,
- 6.7 Small plant,
- 6.8 Temporary services,
- 6.9 Welfare, first aid and safety provisions,
- 6.10 Final clearance and handover,
- 6.11 Defects liability,
- 6.12 Transport of workers to site,
- 6.13 Abnormal overtime,
- 6.14 Risk
25- 7. Estimator's report
- 7.1 A brief description of the project,
- 7.2 A description of the method of construction,
- 7.3 Unusual risks which is not covered in
contract documents, - 7.4 Unresolved or contractual problems,
- 7.5 Design assessment and financial
consequences, - 7.6 Assumptions in estimated,
- 7.7 Assessment of the profitability of the
project, - 7.8 Other market and industrial information,
26- The cost of work to be included in the estimates
are reported to senior management in cost reports
containing the following details - 1. Main contractor's labour,
- 2. Main contractor's plant allocated to rates and
in preliminaries, - 3. Main contractor's materials,
- 4. Main contractor's own sub-contractors,
- 5. Sums of nominated sub-contractors,
- 6. Sums of nominated suppliers,
- 7. Provisional sums and dayworks,
- 8. Contingencies,
- 9. Amounts included for attendance on
sub-contractors, - 10. Amounts included for materials and
sub-contract cash discounts.
27???????????????????????????? (Introduction to
Engineering Economics)
7
- See ???????????1, 2 3 .ppt
- ???????????1.ppt
- ???????????2.ppt
- ???????????3.ppt
28?????????????????? ???????????????(Engineering
Contracts and Insurance)
8
- PROJECT DELIVERY SYSTEMS FOR CONSTRUCTION
PROJECTS - Project delivery system is an organization which
assigns specific responsibilities and authorities
to people and organizations, and which defines
relationships of the various elements in the
construction of a project. There are four (4)
basic project delivery systems
291. The engineering-contractor (E-C) system
- in which responsibility for engineering,
materials acquisition and construction are
assigned to one responsible organization.
Sometimes E-C is referred to as "turn key
system". Owner will usually that there is no
overall project manager that can speak for both
engineering and construction. - Advantages
- 1) One responsible contract for the owner with
materials acquisition and construction closely
coordinated with engineering, - 2) Moderate owner participation,
- 3) Improved construction completion date over
the EC system, - 4) Improved costs and quality by liaison
utilization without contractual problems and
delay of project completion. - Disadvantages
- 1) Inability to establish form project cost in
the early stages of construction, - 2) More problems in labour relations for a large
national operator as opposed to a local
contractor, - 3) Only fair "checks and balances" on the E-C
apply in contrast with separate contracts for
engineering and construction, - 4) The problem of controlling project cost,
particularly in monitoring accumulated cost as
construction progresses and projecting final cost
from monitoring effort.
302. The engineering-plus-contractor (EC) system
- in which engineering is assigned to one
organization and after all engineering is
completed, material acquisition and construction
are assigned to another organization, during the
period when engineering is in progress, there is
a direct relationship between the owner and the
engineer, at that time, no contractor is
involved, when engineering is completed and a
construction contract is in effect, there will be
direct and responsible relationships between the
owner and the contractor and between the engineer
and the contractor, the relationship between the
owner and the engineer will still be maintained. - Advantages
- 1) An accepted historically supports system with
legal and contract precedents well established, - 2) Provision of good checks and balances between
the owner, engineer and contractor, - 3) Determination of project cost before
construction contracts are let. - Disadvantages
- 1) Construction expertise does not benefit design
(minimal E-C liaison), - 2) The longest project completion time,
- 3) Maximum owner participation,
- 4) Greater coordinating and administrative costs
on the part of the owner in most cases.
313. The professional construction manager (CM)
system
- in which a competent construction manager
with no vested interests in design or
construction brings the practical construction
viewpoint to bear during the design phase and
using phased construction, provide overall
management for all construction elements,
professional construction manager as a focal
point for the relationships of the three (3)
basic elements, these relationships persist
during the entire life of the project, the
professional construction manager has had an
important role in the development and
presentation of the engineering design on the
basis of his contribution to construction
practicability, suitability and cost, and will
also have strong voice in the interpretation of
engineering design as well as provide an
excellent control in times of rapidly changing
costs and economic uncertainty, - Advantages
- 1) Application of special construction skills
with no conflict of interest (excellent E-C
liaison), - 2) Moderate owner participation,
- 3) Independent evaluation of costs, schedules and
construction performance, - 4) Good coordination of engineering and
construction, - 5) Minimal time for project completion,
- 6) Best system to construct a project during a
period of rapidly changing costs and economic
uncertainty, - 7) Application to any project delivery system if
function is clearly defined. - Disadvantages
- 1) Usually no firm project cost establishment in
the early stages of construction, - 2) Another layer of responsibility and
administrative cost, - 3) Forcing of the owner or his agent into the
position of referee in settling differences
between construction elements, - 4) Lack of fiscal responsibility on part of
professional construction manager.
324. The professional specification (PS) system
- in which a lump-sum contract is placed with
one organization which provides a complete
"turnkey project", including engineering,
materials and construction on the basis of a
performance-type specification, in this system,
the engineer is chosen by the contractor on the
basis of his special knowledge and experience
relating to the project and to the construction
methods to be used, thus, there is a direct
relationship to the construction and engineering
but "none" between the owner and engineer. - Advantages
- 1) Lowest possible cost and excellent time of
completion, - 2) Determination of project cost before
construction contract is let, - 3) Minimum owner participation,
- 4) One responsible contract for the entire
project, - 5) Provides economical variation in details of
construction without affecting performance of
finished project. - Disadvantages
- 1) Details of construction sometimes causing
personal dissatisfaction, - 2) Unsatisfactory or barely satisfactory
completed project performance may be occurred, - 3) Limited chance for owner to select most
acceptable details of construction or equipment, - 4) Limited application except for highly
specialized or standard designs.
33CONSTRUCTION CONTRACTS
- A contract is an agreement between two (2) or
more parties for a specific purpose. For the
specific case of construction, it is an agreement
between the owner and the contractor to get a
facility built. However, there may be other
contracts in a construction contracts such as the
contract between a supplier/sub-contractor and
the main contractor.
34- Conditions for contracts
- 1. Consideration (the purposed obligation between
both parties) "Contract cannot be signed for
nothing". - 2. Meeting of minds
- Both parties have the same "objectives" to enter
the contract. - 3. Intention to enter into binding agreement
- Each party has a willingness to enter the
contract.
35- Entering into a contract usually progresses
through three (3) stages - 1. Invitation to treat
- A first party (A) makes an invitation to another
party (B) to consider entering into a contract
for a stated purpose. In a construction contract,
the owner usually invites contractors to bid by
making bidding documents available to them. - 2. Offer
- Party B having throughly considered the
conditions attached to A's invitation, may decide
to act on the invitation by making an offer. For
instance, the contractor may decide to submit a
bid and by the bid, he offers to build for a
price and is at liberty to state his conditions. - 3. Acceptance
- Party A concludes the contract by accepting B's
offer. A contract is then signed between the two
parties and the work, in the case of
consideration, executed according to the contract
conditions.
36Four (4) basic type of construction contracts
- 1. Lump-sum contract
- Lump sum contract, is sometimes referred to as
"fixed cost contract" which the contract price is
stated as a total sum of the project. This is
based on the estimates of costs by the contractor
and addition to cover profit and risk. It is
assumed that the contract work will be undertaken
for that price. It is the contractor's
responsibility to estimate costs carefully, and
ensure that construction costs on site are well
calculated for prompt payments. - This method can be applied only in case that the
scope of work is clearly defined. In other words,
design drawings and all the related documents
such as specification are completed and
available. In practice, this method is suitable
for the project which construction period is
relatively short (say ? 1 year). - Price Cost Markup (profit, tax, overhead,
risk)
37- 2. Time-materials contract
- The contractor undertakes the job, the owner pays
for construction costs and "adds" a fee for
management by the contractor. It is necessary to
have a reputable and efficient contractor who
will undertake detailed accounting for this
contract. The contract type is very good when
work must be started early of time is the
critical issue and for construction of
specialized projects. - Time-materials contract, is sometimes referred to
as "cost plus contracts" comprise four (4)
different categories - 2.1 Cost plus fixed fee,
- Price Cost Specified amount of fee,
- 2.2 Cost plus fluctuated fee
- Price Cost Amount of fee depending on
fluctuation of construction cost, - 2.3 Cost plus percentage fixed fee,
- Price Cost Percent fixed fee,
- 2.4 Cost plus percentage fluctuated fee
- Price Cost Percent fluctuated fee.
38- 3. Guaranteed-maximum-price contract
- The contractor agrees to undertake the project
for a fixed price (X) and also gives a guarantee
that a ceiling price will not be exceeded unless
the owner makes further additions to the work.
Good management by the contractor is crucial to
successful application of this type of contract. - In guaranteed-maximum-price contract, the owner
gets savings while the contractor takes the risk.
- Price Fixed price with a guarantee that a
ceiling price will not be exceeded unless the
owner makes further additions to the work.
39- 4. Management contract
- A contractor takes over the responsibility of
management for a contract. He/she may or may not
execute part of the work himself/herself but has
overall responsibility to plan and supervise
construction work, approve changes, budget and
control the execution of the project.
40Build-operate-transfer (BOT) project and contract
- Build-operate-transfer were developed a means for
involving private developers in government
infrastructures projects. Many developing
countries now see this approach as the best way
to provide basic infrastructures. transit system. - Arrangement of BOT projects
- 1. Build
- 1.1 Inception and Concessionaire,
- 1.2 Design,
- 1.3 Management of project and implementation,
- 1.4 Carrying out the procurement,
- 1.5 Construction (build the project),
- 1.6 Finance (getting loan and debt services),
- 2. Operate
- 2.1 Management and operation,
- 2.2 Maintenances,
- 2.3 Delivery of product and/or services,
- 2.4 Receive delivery payment,
- 3. Transfer
- Handover in operating condition at the end of
contract period to the responsible sector/agency.
41- Forms of contracts
- Forms of contract usually follow the type of
contract. However, a form may be prepared by
different organizations. Contract forms can be
classified under the followings - 1. International forms, for example, FIDIC,
- 2. Local forms,
- 3. Company/organization forms.
- Forms of contract need specific tailoring to suit
project situations.
42- Award of contract
- Most construction contracts are awarded on the
basis of competitive bidding. A contract is
usually awarded to the "lowest responsible
bidder" (or "lowest responsive bidder"). Nearly
all public contracts use this approach. - The owner makes decision regarding responsibility
after the bid has been opened. The lowest
responsible bidder has been defined as "the
lowest bidder whose offer best responds in
quality, fitness and capacity to the particular
requirements of the proposed work".
43- The owner may request qualification information
to be submitted with bids or undertake
pre-qualification of contractors. Followings may
be included as criteria for judging
irresponsibility - 1. Default on previous contract,
- 2. Proof of dishonesty,
- 3. Past difficulties in completing projects on
time, - 4. Reputation for uncooperativeness and
non-standard practices. - The surety's recommendation may be relied upon
for judging responsibility. The surety, for the
purpose of issuing bonds will consider the
followings - 1. Finances,
- 2. Experience record,
- 3. Other qualifications.
- The chosen contractor is issued a "notice of
award" which is forwarded with information on how
and when the contract will be signed. The notice
sets forth the conditions of award in form of a
letter.
44- Letter of intent
- In some cases, the owner may want the contractor
to start working before contracts can be signed.
A letter of intent is issued by the owner to the
contractor a evidence that there is intention to
enter a legal relation. The letter will also
state the limits of liability as well as the
types of work that the contractor should begin.
45- The contract documents
- The contract defines exactly and explicitly the
rights and obligations of each party to the
contract. Construction contracts are
traditionally lengthier than other commercial
contracts because of the unique nature of the
product or service. - The essential documents that make up the
construction contracts are as follows - 1. General conditions,
- 2. Supplementary conditions,
- 3. Technical specifications,
- 4. Drawings,
- 5. Addenda (which are others documents/things
needed to be included), - 6. Agreement.
46- Advertisement, invitation for bids, instructions
to bidders and proposal are preliminary to the
contract but are usually included by reference.
Performance and payment bonds may also be
considered as part of the documents. - The documents collectively define what is
intended by the contracting parties. A person
should read before signing as failure to do so
does not excuse one from the contract. - Standard forms of contracts are in general use
because contractors prefer documents and terms
with which they are familiar.
47- The agreement
- The agreement is specifically designed to
formalize the contract. It is the single
instrument that brings together the contract
segments by reference and functions for the
formal execution of the contract. It presents a
condensation of the contract elements, stating
the work to be done and the price to be paid for
it, and providing suitable spaces for the
signatures of the parties. The agreement usually
contains clauses not in the conditions
(supplementary clauses) such as the completion
time of the project, liquidated damages, penalty,
particulars concerning the payments to the
contractor and that list the contract documents.
48- The agreement may be a standard form or specially
prepared for that purpose. - Types of construction contracts shall be as
follow - 1. The lump-sum contract,
- 2. The unit-price contract,
- 3. Cost plus contracts,
- 4. Special reimbursable contracts,
- 5. Cost-plus-percentage-of-cost contracts,
- 6. Cost-plus-fixed-fee contracts,
- 7. Incentive contracts,
- 8. Guaranteed maximum cost contract.
49- Contract clauses
- Clauses are nontechnical provision that pertain
to the conduct of the work. Contract clause
constitute the general conditions, supplementary
conditions and provisions of the agreement.
50CONSTRUCTION INSURANCE
- Construction harzards
- Discussion on accidents in construction has shown
that construction is a hazadous undertaking. The
contractor therefore, needs to protect
himself/herself against liabilities that may be
incurred through accidents, strikes, etc to
prevent ruinous financial losses. - Liabilitiy for accidents can devolve on the owner
or architect/engineer as well as on the main
contractor and sub-contractors. Contracts
normally, require the contractor to protect the
owner against such liabilities. Thus, the
contractor is often required to protect others as
well as himself/herself.
51- Insurance policy
- An insurance policy is a conditional contract in
which the insurer promise for a consideration, to
assume financial responsibility for a "specific"
loss or liability. It is a legal document
containing many provisions pertaining to the loss
against which it affords protection. - The law of insurance is very close to law of
contracts. Each country of state will have laws
regulating insurance practice. - A loss suffered by the contractor as a result of
own deliberate actions cannot be recorded under
the insurance policy. His/her negligence will not
invalidate the policy. Premiums are usually paid
before policies take effect and the contractor
may only claim to the extent of loss. - An insurance firm may either be organized as a
stock company or as a mutual company. In stock
companies, ownership is vested in the
stockholders. In mutual companies, policy holders
constitute the members of the insurance company
or association.
52- Contract requirements
- A standard contract normally requires the
contractor to provide certain convergences such
as followings - workmen's compensation insurance,
- contractor's public liability and property
damage insurance, - contingent liability insurance.
- Property insurance and owner's liability
insurance may be made the responsibility of
owners or contractors. Special insurances may
also be required depending on the perceived risks
of the project.
53- Legal requirements
- Workmen's compensation, mortor vehicle,
unemployment and social security insurance and
others may be required by the law. As such, the
contractor has to provide these insurances
whether or not they are included in the contract.
- The main contractor has a contingent liability
for the action of sub-contractors.
54- Analysis of insurance risks
- It is not economical for the contractor to carry
all insurances available, otherwise, too much
premiums will be paid. For insurable risks, the
cost of premiums must be balanced against the
"likely" loss. - Careful planning and sticking to the rules in
construction may minimize the need for insurance.
Calculated risks may be taken rather than
providing insurance, for examples, working near
existing/old structures, piling, water damage,
etc.
55- Factors to be considered
- In arriving at a decision to what to insure and
what costs to pay, following factors have to be
considered. - 1) The obligation under the contract for loss or
damage to the work and injury or damage to third
parties. - 2) The probabilities of loss inherent in the type
of project. - 3) The geographical location of the project.
- 4) Exposure to specific perils such as
earthquake, flood, etc. - 5) Whether major parts of the work are to be done
by sub-contrcators. - 6) The comparative cost of a full insurance
program versus self-insurance and.or deductible
forms of insurance.
56- Check list for construction insurance
- 1. Property insurance on project
- 1.1 All risk, builder's risk insurance
- 1.2 Builder's risk for fire
- 1.2.1 Extended coverage endorsement
- 1.2.2 Vandalism or malicious mischief
endorsement - 1.2.3 Water damage endorsement
- 1.2.4 Sprinkler leakage endorsement
- 1?3 Earthquake insurance
- 1.4 Bridge insurance
- 1.5 Steam boiler and machinery insurance
- 1.6 Installation floater policy
57- 2. Property insurance on contractor's own
property - 2.1 Fire insurance on contractor's own building
- 2.2 Contractor's equipment insurance
- 2.3 Motor truck cargo policy
- 2.4 Transportation floater
- 2.5 Burglary robbery and theft insurance
- 2.6 Fidelity bond
- 2.7 Dishonesty, destruction and disappearance
policy - 2.8 Valuable papers destruction insurance
- 3. Liability insurance
- 3.1 Employer's liability insurance
- 3.2 Contractor's public liability and property
damage insurance - 3.3 Contractor's protective public and property
damage liability insurance - 3.4 Contractual liability insurance
- 3.5 Owner's protective liability insurance
- 3.6 Completed operations liability insurance
58- 4. Employee insurance
- 4.1 Workmen's compensation insurance
- 4.2 Old-age, survivors and disability insurance
- 4.3 Unemployment insurance
- 4.4 Disability insurance
- 5. Motor vehicle insurance
- Various types are available both to protect own
vehicles and vehicles used on behalf of the
contractor. - 6. Business accident and life insurance
- 6.1 Business interuption insurance
- 6.2 Sole propietorship insurance
- 6.3 Accident insurance on partners or keymen
- 6.4 Life insurance on partners or keymen
- 6.5 Group life insurance
- 6.6 Group hospitalisation insurance
59- Project property insurance
- It is depended on the contractors to protect the
project from loss or damage and to see that
suitable insurance cover is provided. The
construction contract may specify what covers are
mandatory. The contractor may take additional
steps to protect himself/herself as the job is
his/her responsibility except where "acts of
devil (natural disasters)" are involved. - All risks builder's insurance
- This type is commonly used for building projects
and covers the project and temporary structures.
Materials already bought irrespective of their
locations and equipment on site except if under
another cover, are covered by this insurance.
60- Builder's risk fire insurance
- The basic form protects against direct loss due
to fire and lightning. It usually covers only the
items stated in it or all materials adjacent to
the structure and supplies incidental to the
construction. - The policy may cease if the structure is occupied
or abandoned for more than 60 days. - Endorsement to the basic coverage are usually
purchased to extend the cover to other items such
as wind, earthquake, etc.
61- Builder's risk premium
- 1. Reporting form
- Reporting form requires the contractor to report
progress of work and materials in store monthly
to enable the insurable value to be determined,
The premium is paid in monthly installment. - 2. Completed value form
- Completed value form is paid lump-sum in advance
and covers the value of the completed structure.
The premium is fifty (50) percent of maximum fee
as the work is assumed to have zero (0) value at
the begining progressing linearly.
62- Contractor's equipment floater
- This protects from loss or damage to construction
equipment, but does not include liability
coverage. It can cover all equipment for which
the contractor is legally responsible. - Large equipment must be listed with all details
while small items are given blanket cover. The
equipment is usually insured against the
depreciated or value. - The cover can be made flexible as the contractor
desires.
63- Fidelity bonds
- A fidelity bond is a contract under which any
loss sustained by an employer because of the
dishonestly of the employee covered by the
contract are made good by the surety. There are
three (3) types of fidelity bonds. - 1) Name bond,
- 2) Position bond,
- 3) Blanket bond.
- Statutes of limitations
- Many countries and states have statutes that
protect the contractor from indefinite liability
for failure of constructed facilities. Such
limitations vary from four (4) years to twenty
(20) years depending on local laws. - Insurance claim
- It is important that all compensable claims be
brought to the attention of the insurers at the
shortest possible time. To this end, the
contractor needs to designate someone for the
purpose of renewals of policies, reporting,
filing, cancellations, etc.
64???????????????????????????(Project Planning)
9
65??????????????????????(Human Management)
10
66????????????????????????(Safety Management)
11
67 ????????????????? (Information Technology)
12
68 ???????????????? (Project Control)
13
69?????????????????????????????(Claims and
Disputes)
14
70??????????????????????????????????????????????????
???? (Other Related Topics)
15
71 ???????????????????? (Class Presentations)
16