ERIE PIER - PowerPoint PPT Presentation

1 / 33
About This Presentation
Title:

ERIE PIER

Description:

ERIE PIER – PowerPoint PPT presentation

Number of Views:63
Avg rating:3.0/5.0
Slides: 34
Provided by: johnml6
Category:
Tags: erie | pier | ube

less

Transcript and Presenter's Notes

Title: ERIE PIER


1
ERIE PIER
Detroit District
GREAT LAKES COMMISSION 3 October 2006 John M.
Larson, P.E.
2
Naturally Shallow Harbor COE dredges 100,000
cubic yards per year
Duluth Entry
Harbor depth 8 of less outside federal channel
28 Channel
Duluth, Minnesota
27 Channel
Superior Entry
23 Channel
Superior, Wisconsin
21 Channel
Duluth-Superior Harbor, MN/WI
3
Erie Pier
4
ERIE PIER
N
5
ERIE PIER
N
Rail Road Tracks
Off Loading
Perimeter Road
6
ERIE PIER
N
7
ERIE PIER
N
8
ERIE PIER HISTORY
  • ERIE PIER CONFINED DISPOSAL FACILITY
    Duluth-Superior Harbor dredging goes back to the
    19th Century when Congress first authorized
    construction of piers and breakwaters at both
    harbor entries and the dredging and maintenance
    of the connecting channels. Historically,
    material dredged from the channels was used in
    the construction of waterfront property and docks
    as well as some of the islands within the harbor.
    Barkers and Hearding Islands and the Duluth
    Seaway Port Terminal are examples. Some material
    was also used in beach nourishment projects.
    Subsequent to Public Law 91-611, River and Harbor
    Act of 1970, Section 123 authorizing the Corps of
    Engineers to construct, operate, and maintain
    confined disposal facilities, maintenance
    dredging materials have been disposed of at the
    Erie Pier site in West Duluth.
  • Erie Pier Confined Disposal Facility was
    constructed in 1978-79. Preliminary analyses of
    the Erie Pier site made it obvious that
    sheet-pile walls would be very expensive,
    therefore, an earthen dike was constructed using
    an impervious synthetic liner along the dock
    walls to confine the polluted materials and
    prevent seepage into the bay. The site was
    completed in 1979 with a capacity of 1.1 million
    cubic yards and a 10-year life expectancy. Some
    2.1 million cubic yards of material have been
    deposited at the site through 1997.
  • Erie Pier interior dikes were raised in 1997
    adding an additional 600,000 cubic yard and
    prolonging the life of the CDF. With the
    washing process resulting in the re-using of
    about 250,000 cubic yards of dredged material.
    With these efforts the facility was projected to
    be active for another 10-15 years, depending on
    dredge material management.
  • In 2006 the Corps of Engineers spent 534,000 in
    the effort to transform the Confined Disposal
    Facility into a Dredge Material Placement/Reuse
    Facility. Utilizing numerous programs and working
    with all level of government, a plan is being put
    together that will market and manage the
    material, with the goal of and lowering the berm
    elevation.

9
(No Transcript)
10
MECHANICAL DREDGING OPERATION
11
(No Transcript)
12
HYDRALIC DREDGING OPERATION
13
(No Transcript)
14
ERIE PIER OPERATIONS
Washing Bowl
15
(No Transcript)
16
(No Transcript)
17
ERIE PIER OPERATIONS
Sluiceway
18
ERIE PIER OPERATIONS
Washed Material being staged for removal
Fines flowing down the sluiceway
19
ERIE PIER OPERATIONS
Virgin Material
Plastic Clay Material
Very soft clay/silt with organics
20
ERIE PIER OPERATIONS
Material flows to reach its own elevation in CDF
21
ERIE PIER ORENTATION
Material Placement Site
Entrance Road
Rail Road Tracks
Pond
Offload site
22
NEW ERIE PIER OPERATIONS
Material Off/On Load site
Material Cell
Material Placement Site
Elev. 620
Elev. 607
Ramp
Sluiceway
Transfer Site
Move Off Loading Site.
Elev. 640
Filter System
Rock Staging Area
Pond
Elev. 605
Discharge
Elev. 603
23
(No Transcript)
24
(No Transcript)
25
(No Transcript)
26
(No Transcript)
27
(No Transcript)
28
(No Transcript)
29
(No Transcript)
30
(No Transcript)
31
(No Transcript)
32
(No Transcript)
33
(No Transcript)
34
ERIE PIER MATERIAL
20,000 CY
60,000 CY
15,000 CY
35
(No Transcript)
36
(No Transcript)
37
ERIE PIER DEWATERING AND FILTERING SYSTEM
OUTSIDE CELL
INSIDE CELL
WIER STRUCTURES
ELEV 614-603
BERM ELEV 620
DOCK
FILTER SYSTEM
ROAD
PIER ELEV 605
RCP PIPE
DISCHARGE EVEV 603
WATER ELEV 601
DESIGN FOR 200 GMP AT 1 HEAD
38
ERIE PIER MATERIAL RECOVERY
  • 2004 30,900 CYS
  • 2003 17,600 CYS
  • 2002 14,500 CYS
  • 2001 3,400 CYS
  • 2000 110,000 CYS
  • 1999 12,300 CYS

39
ISSUES
Detroit District
Water Management Filter System WLSSD Market
ing Material Unclassified Fill General
Construction Mine Reclamation Initiative WLSSD
Soils Program City of Superior use as landfill
daily cover Invasive Species Removal from Erie
Pier Long-term monitoring plan of sites where
Erie Pier material is placed
40
WAY AHEAD
Detroit District
Make infrastructure Improvement on an on-going
basis Work with MPCA on discharge permit, MNWI
DNRs on soils Issues. Establish a marketing
plan for material removal (i.e. bring the berm
elevations down) Work through HTAC Dredging
Sub-committee, HTAC and MIC
41
Infrastructure Expenditures
Detroit District
Off/On Loading Area (Taconite Aggregate) Perimeter
Road Maintenance 3,000 CYs (Taconite
Aggregate) Ramps (Taconite Aggregate) Filter
System Design and Construction (Taconite Filter
System) Berm Maintenance Aerial Photo Invasive
Species Clear Grub - 2 Acres
42
QUESTIONS?
Detroit District
Write a Comment
User Comments (0)
About PowerShow.com