Title: BUMBUNA HYDROELECTRIC PROJECT
1- BUMBUNA HYDROELECTRIC PROJECT
2- BUMBUNA HYDROELECTRIC PROJECT
3Overview
- Major Issues in SLs Power Sector
- Reducing poverty and catalyzing economic growth
through reliable power supply - Introduction of the Bumbuna Hydroelectric Project
- how Bumbuna addresses the issues in SLs Power
Sector - Status of BHP Implementation
4Overview(contd.)
- WBs safeguard policies
- Schedule for completing BHP
- Implementation arrangements for the BHP
- Cost estimate for completion of BHP
- Preliminary Donors commitment for completion of
BHP - Governments financial commitments
- Closing the financing gap
5Major Issues in the SLs Power Sector
- Unreliable Power Supply
- Extremely high tariffs (about US 19 cts/kWh)
- High system losses (about 35 for the moment)
- High operational costs (fuel)
6Reducing poverty and catalyzing economic growth
through reliable power supply
- Providing electricity for schools, health
clinics, small scale industries, private
households - Improving security in urban environment
- Providing power for industry and commerce
7Introduction into the BHP
- Located in the Northern Province some 200 km from
Freetown - Preparations under way since the 1970s
8Description of Works
- Civil Works comprising a 88 m high rockfill Dam,
a Power House, Switchyard, two diversion tunnels,
spillway discharges and bottom outlet - Electromechanical Equipment including two
turbines, two generators with output of 25 MW
each, step-up transformers, switchgears, etc - Hydromechanical Equipment comprising an Intake
Tower, two Spillways and other accessories. - Transmission Line consisting of 200 kilometres
single-circuit conductors at 161 kV from Bumbuna
to the substation in Freetown - Shield-wire system to provide power to towns
along the T/L, namely Makeni, Magburka, Lunsar,
Port Loko, Masiaka, Kambia, etc.
9How Bumbuna addresses issues in Sierra Leones
Power Sector
- will provide reliable low cost power
- will lead to significant reduction in electricity
tariffs - will lead to significant reductions in oil
imports - will widen access to electricity particularly in
towns along the transmission line
10STATUS OF PROJECT
- Project to date has been supported by the
Government of Italy (GOI) and AfDB
- Works suspended since 1st June 1997 due to rebel
activity
- Works completed at suspension time is almost 85
- A consulting firm commissioned by the AFDB and
GOSL undertook a technical and financial audit
of the project in 2002 they concluded that the
quality of workmanship during construction was
good and that the work should be completed by the
existing contractors
- For reasons explained, the GOSL has decided that
the BHP be completed as soon as possible.
11WBs safeguard policies
Compliance with World Bank safeguard and other
policies on HEP of this stature, Government is
taking the following measures
- Update of the Environmental Assessment and
undertaking the Resettlement Action Plan
- Institutionalizing an Environmental experts
panel for the BHP
- Institutionalizing a dam safety panel and
preparation of an emergency Preparedness
Emergency Plan
- TA- Study for the post-commission Operation
- Assignment of an experienced HEP Engineer to the
PIU
12Implementation arrangements for the BHP
- Involves the GOSL
- Ministry of Energy and Power
- BHP Steering Committee
- PIU
- Consultants
- Studio Ing. Pietrangeli
- Contractors
- Transmission Line and Freetown Substation ABB -
Italy - all other Contracts under leadership of Salini
Construttori
13Fairness in contracts
- The existing contracts between the GOSL and the
Contractors need to be negotiated and need to be
faire to all concerned. - They will need to be acceptable to the major
donors involved in this project
14COST ESTIMATES(for details refer to table 1)
LOCAL COST
Le 23.52 BILLION
FOREIGN COST
US 42.82 MILLION
TOTAL COST
US 52.60 MILLION
OUTSTANDING CLAIMS
US 8.65 MILLION
TOTAL COST FOR IMPLEMENTATION OF PROJECT
US 61.52 MILLION
15Preliminary Donor Commitments
AfDB Residual balance from previous loans
US 9.6 million US 8 Million to be used to
pay outstanding claims GOI
Committed US 11.5 Million IDA PPF of US
2.0 Million PRG of US 20 Million
16Government's financial commitments
- Settlement of outstanding contractors bills by
the end of September 2003, - Supporting the PIU (the estimated cost are about
Le 2.9 billion) - Supporting other local cost (estimated at about
Le 3.4 billion)
17Closing the financing gap
- The AfDB/GOI/WB mission estimated the financing
gap in foreign cost at about US 7.76 million - for the local costs, the financing gap is about
Le 17.96 billion (equivalent to some US 7.49
million) - the total financing gap is about US 15.25
million
Government requests donors to assist in closing
the financing gap
18Schedule for completing the BHP
- Settlement of outstanding bills/claims
mid October 2003
- Project condition assessment
mid October - November 2003
- Negotiation of Contract amendments
December 2003
- Commencement of Implementation
January 2004
- Undertaking environmental, resettlement other
studies
December 2003/ April 2004
December 2005