Title: EU DANEX 2006
1EU DANEX 2006
2Project Organization
Project Forum (Senior Management)
Project Owners Anders Nørregaard Jørgen Holst
Hansen
National Board DEMA, MoFA, MoD, CHOD, Police SRSA
International Boards EU, UN OCHA, Participating
Countries
Project Manager Michael Elmquist
Project Team John Clausen Henrik Frimor Hans
Bruhn Per Sloth Møller Per Bach Jensen Inge-Lise
Mortensen
Ressource Persons Finance, IT, Communikations, Log
istics, etc.
Denmark Estonia Germany Hungary Lithuania Portugal
Slovenia Sweden
Working Group
Working Group
Working Group
3Timeline
- December 2005
- Establishment of project organization
- E-253 (08 Jan 2006)
- DEMA Key Planning Group Meeting
- E-237 (24 Jan 2006)
- Invitation sent to international participants
4Timeline
- E-222 (08 February 2006)
- Host Country Board Meeting
- E-202 (28 February 2006)
- Kick-off meeting, Brussels
- E-170 (02 April 2006)
- Host Country Planning Workshop
- E-90 (21 June 2006)
- Final Planning Conference
5Timeline
- E-30 (19 August 2006)
- Media Release 1
- E-2 (16 September 2006)
- Media Release 2
- E-Day (18 September 2006)
- Exercise starts
6Timeline
- E2 (20 September 2006)
- Media Release 3
- E3 (21 September 2006)
- Media Release 4
- E4 (22 September 2006)
- Exercise ends. Media Release 5
7Timeline
- E20 (08 October 2006)
- Host Nation Evaluation Workshop
- E60 (17 November 2006)
- Final technical report. Media Release 5.
8The Exercise
- E Day (Monday 18 September 2006)
- Exercise OSOCC and MIC established
- Arrival of participants
9The Exercise
- E1 (Tuesday 19 September 2006)
- Observers programme starts
- Incident 1
- Detection and identification of potential toxic
substances in train derailed in tunnel. - Decontamination of wounded and contaminated
passengers. - Medical care of contaminated passengers.
- Shoring of heavy concrete structure after
discharge.
10The Exercise
- E1½ (Tuesday 19 September 2006)
- Incident 2
- Fighting fire in natural gas plant and sealing
leaking (large) gas pipes. - Incident 3
- Detection and identification of potential
bio-hazardous substance in quarantined airplane. - Medical care of potentially affected passengers.
11The Exercise
- E2 (Wednesday 20 September 2006)
- Redeployment
12The Exercise
- E3 (Thursday 21 September 2006)
- Incident 4
- Detection of potential leak at live nuclear
plant. - Incident 5
- Fighting leaks of liquid and gaseous (live)
ammonia at major ammonia storage facility.
13The Exercise
- E3 (Thursday 21 September 2006)
- Incident 6
- Detection and identification of potential
chemical warfare agents at hospital (military
facility) - Incident 7
- Clearing of major roads from falling trees.
14Budget
- Personnel
- Travel and subsistance
- Other direct costs
- Overheads (max 7)
- Total
269.348 265.230 112.064 45.265 691.907
15Budget Personnel
- Project Manager
- Planning Officer
- Planning NCO
- Exercise Direction Officer
- Exercise Direction NCO
- Exercise Direction Rescue Worker
- Total
69.011 69.011 49.073 43.633 17.009
21.611 269.348
16Budget Travel and Subsistence
- Planning and preparation
- Observers
- Exercise participation
- Evaluation and reporting
- Total
40.990 37.081 175.295 11.864 265.230
17Budget Other Direct Costs
- Exercise info and documentation
- Exercise preparation and construction
- Translation of evaluation report
- Printing of evaluation report
- Total
2.681 100.000 2.681 6.702 112.064
18How to reach us
- E-mail eudanex_at_brs.dk
- Fax 45 4590 6060
- Tel. 45 4590 6102 (Inge-Lise Mortensen)
- Web www.brs.dk/eudanex (to be developed)