EERI Presentation - PowerPoint PPT Presentation

1 / 39
About This Presentation
Title:

EERI Presentation

Description:

EERI Presentation – PowerPoint PPT presentation

Number of Views:50
Avg rating:3.0/5.0
Slides: 40
Provided by: jared73
Category:
Tags: eeri | presentation | vms

less

Transcript and Presenter's Notes

Title: EERI Presentation


1
EARTHQUAKEVULNERABILITIES AND PERFORMANCE OF
HIGH-VOLTAGE ELECTRICAL POWER TRANSMISSION SYSTEMS
Leon Kempner Jr Bonneville Power Administration
2
ELECTRICAL POWER FACILITIES
3
Colima Mexico Earthquake, Jan. 22, 2003
Schiff
LIVE TANK POWER CIRCUIT BREAKERS
Estimated g-level 0.1 0.15g, M7.8
4
VULNERABILITIES
TRANSFOMER
Schiff
BushingPorcelain Failure
Radiator Removed Manifold Leakage
Bushing Slippage
Schiff
5
TRANSFORMER VULNERABILITIES
Unanchored Transf.
Schiff
6
Failed 500 kV Disconnect Switch
Before
After
Duvall 5.4 Mw (1996)
7
Satsop 5.9 Mw (1999)
Duvall 5.4 Mw (1996)
Nisqually 6.8 Mw (2001)
Bus Riser Failures 500 kV
8
Bus Riser Failure 230 kV
Nisqually 6.8 Mw (2001)
9
BATTERIES
Peru 7.8 Mw (1970)
Taiwan 7.3 Mw (1999)
10
San Fernando 6.6 Mw (1971)
Pipe Failures
EQE
Taiwan 7.3 Mw , 1999
Engine Generator
11
Spare Parts Storage
12
TRANSMISSION TOWERS
Niigata, Japan 7.4 Mw (1964)
Ridge Shatter
Liquefaction
Northridge 6.7 MW (1995)
Fault
Turkey Earthquake 7.4 Mw (1999)
Landers 7.4 Mw (1992)
Fault
13
Olympia 6.5 M (1965)
Nisqually 6.8 Mw (2001)
Transmission Line Sectionalizing Switch
14
RISK REDUCTION SOULTIONS
DETERMINE RISK Identify And Quantify Potential
Losses
IDENTIFY STRATEGIES
Design Strategies
Response Strategies
Business Strategies
Response plan and Materials
ReduceHazard
ReduceVulnerability
Accept Risks
Emergency Operation Centers
Evaluate and Select Optimal Combination of
Strategies
15
ReduceVulnerability
NEW EQUIPMENT
EXISTING EQUIPMENT
IEEE 693 Recommended Practice for Seismic Design
of Substations Seismic Qualification
RETROFIT VULNERABLE EQUIPMENT
IEEE 693 Moderate
IEEE 693 High
16
INVESTMENT PROTECTION
POWER SYSTEM RECOVERY
17
Pad Mounted Transformers
Rail Mounted Transformers
18
TransformersMitigation Connection Flexibility
and Bracing
19
Mitigation Flexible Bus Riser
Flexible Cable
20
Mitigation Adding Flexible Connections
Flexible Conductor

Flexible Conductor

Disconnect Switch
Dead Tank Circuit Breaker
21
Power Circuit Breaker Mitigation Adding
Flexible Connections

500 kV Disconnect Switch
500 kV Power Circuit Breaker
22
500kV Power Circuit Breaker Mitigation
Mitigation Adding Structural Dampers
23
Battery Systems
24
Bushing Storage - Seismic Hardening
Hardened
Unanchored
Anchored Spare Transformers
25
SYSTEM EARTHQUAKE RISK ASSESSMENT
  • System Inventory
  • Equipment Fragility
  • Scenario Earthquakes
  • SERA Results
  • Originally developed for Southern California
    Edison (SCE), 1990
  • Recently used to evaluate the San Francisco BART
    system
  • GE Engineering Systems, Inc. Version

26
Purpose of SERA Studies
  • What damage might occur to BPA in future
    earthquakes?
  • What seismic upgrades are reasonable at
    BPAs substations? How much will it cost?
  • What are the benefits? Are the benefits worth
    the cost?
  • Training of Staff i.e. Dispatchers

27
Eidinger
28
Example Scenario Earthquakes
  • Puget Sound Scenario Earthquakes
  • Seattle Fault M 7.1
  • South Whidbey Island M 7.0
  • Cascadia Subduction Zone M 9.0
  • CSZ Intraplate beneath Tacoma M 7.5
  • Portland Scenario Earthquakes
  • Portland Hills Fault M 7
  • Lackamas Creek M 6.7
  • Grant Butte/Damascus M 6.7
  • Cascadia Subduction Zone M 9.0
  • CSZ Intraplate Allston-Keeler M 7.5

29
CSZ INTRAPLATE M 7.5
CSZ M 9.0
30
Eidinger
31
Inventory
1. 85 substations 2. Inventory based on the
1-line diagrams and field inspection 3.
Approximately 13,000 plus components are modeled
1 component 1 phase 4. Photos of every
component
2004
2008
2007
2005
2006
32
2. System Inventory
33
3. Equipment Fragility
Bushing Gasket Leak
Radiator
Porcelain Breakage
Anchorage Failure
Overturn
34
Eidinger
35
Results
  • Damage Level at Each Substation
  • - Components (No Damage, Partial, Total)
  • Transmission Line Outages, based on substation
    damage
  • Repair Costs
  • Outage Time, based on temporary repairs, 90
    Capacity
  • Repair Time, based on final repairs, 100
    Capacity

36
South WhIdbey Fault
37
LANDSLIDES
www.OregonGeology.com
38
LIQUEFACTION
39
THE END
Write a Comment
User Comments (0)
About PowerShow.com