Title: Overview
1Overview Remedial Technologies
Philip B. Bedient Rice University
2How Remediation Technology Evolves
Cost-Effective Technology
Proven Technology
Large-Scale Field Trials
Emerging Technology
Uncontrolled Pilot Trials
Prototypes and Controlled Field Experiments
Experimental Technology
Bench Studies Concept / Problem Identification
CONCEPTS
Source Cherry, 1992
3Original Paradigm 1980s Groundwater Pump and
Treat Will Remediate Sites
4Bad News
Conc
?
Cleanup Standard
Time
5EPAs 19 Site Study
19 Sites With Five Years of Operating
Data Restoration Slower Than
Expected Three Causes Hydrology, Design
Flaws, NAPLs Update At 20 of 24 Sites,
DNAPL Probably Present
6(No Transcript)
7Forming Residual NAPL
Snap-Off Mechanism
Other Mechanisms Bypass, Etc.
8NAPLs and Capillary Forces
NAPL
NAPL
NAPL
9Residual vs. Free-Phase DNAPL
Free-Phase DNAPL
Residual DNAPL
10Residual NAPL Long-Term Source
- Cant Remove Residual
- Dissolves Slowly
- Large Mass Compared to Dissolution Rate
11Recovering LNAPL
Separator
Saturated Zone
Screen
Sand Pack
Pump
DNAPL Pool
12Recovering LNAPL Other Configurations
Dual Recovery Wells Pump Cans Skimmers Adsorbants
Trenches
DNAPL Pool
13DNAPL Conceptual Model
DNAPL Entry Zone
Residual DNAPL
Sand
Fractured Clay
Sand
Dissolved Phase Plume
DNAPL Pool
14Recovering DNAPL
DNAPL / Water Separator
Pump
Saturated Zone
Screen
Sand Pack
DNAPL Pool
Impervious Barrier
Sump
15DNAPL Pumping Design Process
- Choose Location of DNAPL Wells
- Select Pumps and Materials
- Assess EOR Technologies
- Vacuum-Enhanced Pumping
- Waterflooding
- Surfactants
- Steam
- Design Treatment System
16Remediation Technologies
Introduction - Why Are We Here Product
Removal and Source Control Groundwater pump
and treat Remedial Technologies in Use
17Pump-and-Treat (Dissolution)
- Dissolves Residual NAPL
- Key Concept Number of Pore Volumes
- Takes a Long Time
18Applicability of Dissolution of NAPLs
- NAPLs in Saturated Zone
- NAPL with Very Soluble Components
- Sites With Low Amounts of NAPL
- Highly Permeable Aquifers
19Proven/Emerging Remediation Technologies
- Excavation and Disposal / Treatment
- Soil Vapor Extraction (SVE) / Bioventing
- In-Situ Biodegradation / Oxygen Releasing
Compounds - Air Sparging
- Barriers
- Containment
- RBCA / Natural Attenuation
20Excavation and Disposal / Treatment
Haul To Off-Site Landfill
On-Site or Off-Site Thermal Treatment
On-Site Physical / Biological Treatment
21Applicability of Excavation
- Standard Construction Practice to 25 Feet Depth
- Dewatering Required if Below Water Table
- Unconsolidated Material
- Best Technology for Small Volumes
22Soil Vapor Extraction
Vapor Treatment System (Where Required)
Blower or Vacuum Pump
Air / Vapor Manifold
Clay
Grout Seal
Screen
Sand Pack
Contaminated Soils
Water Table
23Applicability of SVE
Vapor Pressure (mm Hg)
Likelihood of Success
Soil Air Permeability
104
HIGH (Coarse Sand / Gravel)
Very Likely
Butane
103
102
Benzene
101
MEDIUM (Fine Sand)
Xylene
Somewhat Likely
100
10-1
LOW (Clay or Silt)
10-2
10-3
Less Likely
10-4
Aldicarb
Source CDM, 1988
24Design Basis Information SVE
- Air Permeability
- Estimated from Soil Properties
- Measured With Test in Field
- Contaminant Characteristics
- DNAPL Composition
- Volatility (Vapor Pressure, Henrys Law
Coefficient) - Air Flow
- Stratigraphy
- Need for Impermeable Cap
- Water Table and Need for Pumping
25SVE Design Process
- Choose Number of Vapor Extraction Wells
- Choose Well Spacing, Inlet Wells, Seals
- Design Well Screens and Construction
- Remember Vapor Treatment
- Check for Groundwater Upwelling
Source Johnson 1990
26Bioventing
Ref. Hinchee
Blower
If Air Injection Rate is Slow Enough No Vapor
Treatment Is Needed
Unsaturated Zone
Saturated Zone
Slowly Adds Oxygen to Unsaturated Zone for
Biodegradation
27Bioventing Process Overview
- Inject Air Into Unsaturated Zone
- Primary Process Aerobic In-Situ
Biodegradation - Injection Is Slow to Minimize Release of Organics
to Surface or Buildings - No Need to Treat Vapors
28Bioventing Design Approach
- In-Situ Permeability Test
- In-Situ Respiration Test (24 - 80 hrs)
- Install Wells and Inject
- Ususally 2 in. PVC Vent Wells
- Water Table lt 20 ft Screen 10 - 20 ft
- Water Table gt 20 ft Through Contaminated Zone
- Spacing 5 to 60 ft, Depends on Depth and Soil
Type - Injection Rate Variable
29Proven/Emerging Remediation Technologies
- Excavation and Disposal / Treatment
- Soil Vapor Extraction (SVE) / Bioventing
- In-Situ Biodegradation / Oxygen Releasing
Compounds - Air Sparging
- Barriers
- Containment
- RBCA / Natural Attenuation
30In-Situ Biodegradation
Oxygen Addition
To Treatment Treatment / Recycle Recycle
Recovery Well
Injection Well
Nutrient Addition
DNAPL
In-Situ Biodegradation Zone
31Applicability of In-Situ Biodeg.
- Sites With Non-Chlorinated Compounds
- BTEX
- Creosote Sites (Napthalene, PAHs)
- Coal Tar
- Sites With Depressed Oxygen in Plume Area
- Aquifers With High Permeability
32In-Situ Biodeg. Design Process
- Estimate Total NAPL Mass
- Calculate Required Mass of Oxygen to Be Injected
- Yield 2 gms Oxygen for 1 gm Hydrocarbon
- Select Method to Add Oxygen to Injection Water
- Bubble Air in Injection Water 10 mg/l
- Pure Oxygen 25 mg/l
- Hydrogen Peroxide 100 mg/l (?)
- Calculate Water Needed
- Size Recovery Well System
33Oxygen Releasing Compound (ORC)
Magnesium peroxide compound activated by
moisture Patented technology controls and
prolongs release Moderate pH levels Pure
oxygen source (more dissolved O2 than
sparging)
34Air Sparging
Air Compressor
Blower
Vapor Treatment
SVE Well
Tiny Bubbles
NAPL
Volatilizes Organics and Promotes In-Situ Biodeg.
35Air Sparging Process Review
- Air Pathway
- Forms A Few Small Channels
- Remarkably Sensitive to Heterogeneities
- Air Flow From Top of Screen
- Remediation Processes
- Volatilization of NAPLs
- Air Stripping of Dissolved Organics
- Oxygenation of Water Enhances In-Situ Biodeg.
36Air Sparging Design Issues
- Well Configuration
- Usually 1-2 inch PVC Wells, 2-5 ft Screens
- Spacing 10 - 20 ft (Billings)
- Spacing 50 - 75 ft (Brown)
- Spacing 5 - 15 ft (Newell)
- Injection Pressure 1-10 psig
- Air Flowrates
- lt 10 SCFM per well
- Helps to Cycle (Hours, Not Days)
37Air Channel Pattern at Moderate Air Injection
Rate in a Medium Mixture of Two Bead Sizes With
38 of 0.75 mm and 62 of 0.3 mm
Overburden with 4 mm beads
Mixture of two size beads
Source Ji et al, 1993
38Air Channels at Low Air Injection Rate in 0.75
mm Uniform Bead Medium
Overburden with 4 mm beads
0.75 mm beads
Source Ji et al, 1993
39Short Circuiting in Air Sparging System
Air Flow
Contaminated Zone
Low Permeability Zone
Air bubble
40Proven/Emerging Remediation Technologies
- Excavation and Disposal / Treatment
- Soil Vapor Extraction (SVE) / Bioventing
- In-Situ Biodegradation / Oxygen Releasing
Compounds - Air Sparging
- Barriers
- Containment
- RBCA / Natural Attenuation
41Physical Barriers
- Purpose
- Prevent Outward Migration of Organics
- Reduce Inflow of Groundwater
- Design
- Types
- Keyed Into Confining Unit
- Partial vs. Complete Enclosures
- Construction
- Routinely Installed Down to 50 feet
- Cost 10 - 20 per sq. ft. for Slurry Wall
42Cutoff-Wall Keyed into Clay
43Cutoff Wall Hanging
44Hydraulic Containment
Pumping Well
Streamlines
Plume
Capture Zone
- Design Methods
- Javendahl Capture Zone Curves
- Computer Models
- Operational Factors
- Well Efficiency
- Seasonal / Annual Effects
45Hydraulic Containment With Slurry Wall
Slurry Wall
Slurry Wall
Well
Frac. Clay
Aquifers
Unfract. Clay
Drinking Water Aquifer
46Funnel and Gate Systems
47SKIMMING NAPLs IN SOURCE ZONES
- Interceptor trenches - collect free product
- Single pumping system
- Dual pumping system
- Combined water and product pumps
- Oil water separator at surface
48Typical NAPL Migration Pattern
49Interceptor Trench for DNAPL
50NAPL PLUME FROM FUEL SPILL
51(No Transcript)
52NAPL RECOVERY SYSTEMTWO WELLSTWO PUMPS
53NAPL RECOVERYSYSTEM ONE WELLTWO PUMPS
54Natural Attenuation A New Approach
Basic Philosophy We Know It is Difficult to
Remove All Contaminants..... But We Can Predict
What Happens to Them.
55Overview of Natural Attenuation
Destruction of Contaminants via
Biodegradation Observed at Numerous Field
Sites Studied in Detail at Several Research
Sites Policy Guidance Now Recognize Natural
Att. Scientific Understanding is Rapidly
Increasing
56Natural Attenuation Under RCRA
Proposed Subpart S Preamble Natural Attenuation
Could Be the Most Appropriate Approach At Many
Sites and May Play a Major Role Conditions
Standards Achieved in a Reasonable Time
Likelihood of Exposure Is Minimal
57Obstacles to Natural Attenuation
? Associated with No Action ? Preference for
Zero Plume Growth ? Preference for Rapid
Remediation
58Evidence of Natural Attenuation
Criteria
? Plume stable or shrinking ? Plume is shorter
than would be expected ? Depletion of measurable
electron acceptors (OXYGEN, NITRATE OR SULFATE)
observed ? Metabolic by-products (FERROUS IRON
AND METHANE) observed ? Presence of active,
heterotrophic bacteria
59Evidence of Natural Attenuation
No BTEX
Map and Perform Mass Balance on Electron
Acceptors and Byproducts Oxygen Nitrate
Iron Sulfate CO2
BTEX
BTEX
Oxygen
Dissolved Oxygen
No Oxygen
60RISK-BASED CORRECTIVE ACTION
GROUNDWATER SERVICES, INC. John A. Connor,
P.E. Charles J. Newell, Ph.D., P.E. J. Peter Nevin
61Risk Assessment Fundamentals
Risk Management
Transport
RECEPTOR
SOURCE
Minimize risk by preventing exposure.
62Risk-Based Corrective Action Procedures
RISK-BASED APPROACH
TRADITIONAL APPROACH
Remedial Investigation
Remedial Investigation
Risk Assessment
Corrective Measure Study
Corrective Measure Study
Corrective Measure Implementation
Corrective Measure Implementation
63GRBCA(Gut-Feel Risk Based Corrective Action)
BAD
NOT SO BAD
64Baseline Risk Calculation
Exposure Concentration
x
Exposure Factors
Health Risk
x
Toxicity
Source Conc.
65Groundwater Services RBCA Tool Kit
www.gsi-net.com
Exposure Concentration
x
Exposure Factors
Health Risk
x
Toxicity
SOURCE CLEANUP LEVEL
66ASTM Guide for RBCA
ASTM RBCA Program
Site Classification and Response
? Classification Classify site per immediacy
and magnitude of risk, based on current snap
shot.
? Response Implement appropriate response
action for each class.
67Groundwater Exposure Pathway
3) Soil Leaching to Groundwater Ingestion
On-Site
Off-Site
Affected Soil
Affected Groundwater
4) Dissolved or Free-Phase Groundwater Plume
Ingestion
Potential Point of Human Exposure (i.e.,
on-site or off-site).
Affected Groundwater
68Proven/Emerging Remediation Technologies
- Excavation and Disposal / Treatment
- Soil Vapor Extraction (SVE) / Bioventing
- In-Situ Biodegradation / Oxygen Releasing
Compounds - Air Sparging
- Barriers
- Containment
- RBCA / Natural Attenuation