LISA Pathfinder Mission Status - PowerPoint PPT Presentation

1 / 9
About This Presentation
Title:

LISA Pathfinder Mission Status

Description:

A disposable propulsion module for apogee raising. Ground interface: single 15m X-band antenna. ... Micro-propulsion technology work in progress: ... – PowerPoint PPT presentation

Number of Views:54
Avg rating:3.0/5.0
Slides: 10
Provided by: lucast2
Category:

less

Transcript and Presenter's Notes

Title: LISA Pathfinder Mission Status


1
LISA Pathfinder Mission Status
2
Mission Elements
  • The launcher services are baselined to be
    provided by Eurockot, backup DNEPR
  • The Spacecraft Prime Contractor is Astrium Ltd.
    (UK) with core industrial team including Astrium
    GmbH (D) and SciSys (UK)
  • The LISA Technology Package (LTP) is provided by
    an European team managed by the LTP Management
    Office
  • The Disturbance Reduction System (DRS) is an
    American equivalent of the LTP and is provided by
    NASA-JPL
  • The Ground Segment is designed and implemented by
    ESOC. The Science and Technology Operations
    Coordination (STOC) will be established at ESTEC

3
System
  • The space segment consists of
  • A science spacecraft which carries the technology
    packages
  • A disposable propulsion module for apogee raising
  • Ground interface single 15m X-band antenna.
  • 8 hours per day communication
  • 6 days timeline
  • 7 days data storage
  • Launch nominally on Rockot
  • Operations by ESOC
  • Science Technology Operations Centre at ESTEC

4
Launcher status I
  • Baseline launch vehicle Rockot
  • Procured from Eurockot, Bremen, D
  • Breeze KM upper stage
  • Proven vehicle with heritage
  • Launch from Plesetsk/Russia
  • Injection into 200x900 km orbit
  • Max lift-off weight of S/C 1910 kg
  • 1194 mm std separation system
  • Facility to be upgraded for bi-propellant
    fuelling (vapour traps, waste disposal, etc)

5
Launcher status II
  • Backup launch vehicle Dnepr
  • Procurement from Spacetech, D
  • Compatibility maintained until PDR
  • Proven vehicle
  • Silo-launch from Baikonur Kosmodrome
  • Injection into 300x2000 km orbit
  • Max lift-off weight of S/C 2250 kg

6
Contractual actions
  • LPF Contract with ASU (Scisys and ASD) for the
    Implementation Phase signed in May 2004
  • ITT for subcontractors were to be issued between
    Jan and Sep 2005
  • Multi Lateral Agreement approved by the Council
    in October 2004
  • Inclusion of France in MLA approved by SPC and
    AFC in February 2005 signed by all delegations
    in May
  • Contract with ASD negotiated and kicked-off on 26
    January 2005
  • ITT for caging Mechanism contract with Laben (
    subco) negotiated and kicked-off on 20 May
  • ITT for Acousto-Optic Modulation Unit offers
    received. Contractor has been selected
    (Contraves, CH) and kick-off on 7 July
  • IS offer by CGS/Laben evaluated by ASI (with
    ESA). Kick-off expected by July
  • Various µ-propulsion technology activities
    been/being kicked-off

7
Spacecraft Progress
  • LPF System Requirements Review held in May/June
    2004? additional analysis/work to be performed
  • System Requirements Review Close-out (including
    LTP) held in October November 2005 (Board on Nov
    5) ? Successful
  • System definition consolidation on going
  • Preparation of subcontractors ITT on-going
    according to schedule
  • Preparation for Preliminary Design Review to be
    held in July-September 2005
  • Micro-propulsion technology work in progress
  • FEEP at ALTA, Delta PDR for Microscope was held
    on 29-30 June (Board 28 Jul)
  • FEEP at ARCS new technology contract in progress
  • Cold-gas test results evaluation on going and new
    tests planned
  • Technology Readiness Review held in May/June 2005
    (Board 22 Jun) ? Successful

8
LTP problems
  • LTP continues to experience problems in meeting
    the programme deadlines
  • In mid 2003 (LPF ITT) LTP delivery to ASU was
    June 2006 (6 months contingency claimed)
  • In February 2004 (LPF negotiation) LTP delivery
    was December 2006 (contractual baseline to ASU)
  • In January 2005 (ASD LTP negotiation) LTP
    delivery was December 2007(subject of a CCN with
    ASU)
  • In March 2005 (ASD Progress Meeting) LTP
    delivery was March 2008
  • Cost increases wrt the original estimates of the
    ESA contribution (e.g. Caging Mechanism,
    integration activities)

9
LTP problems why?
  • Facts
  • Interdependency of deliveries (many suppliers
    depend on other suppliers, with no contractual
    bindings, for their final delivery)
  • Late start of the LTP contracts
  • Architect, started in Jan 2005
  • Italian IS contract not started yet
  • PRODEX contract for the IS FEE started in April
  • AOMU offer just selected
  • Caging Mechanism just kicked-off)
  • Design evolution (e.g. 1553 MIL bus, mass
    restriction, October 2004)
  • Other possible reasons
  • Apparent low commitment by the suppliers due to
    lack of resources (e.g. institutes limited buffer
    of resources)
  • Low (insufficient) budget allocated to the job by
    all parties
  • Protective attitude of some parties, not allowing
    the proper implementation of the rôle of the
    Architect as defined in the Management Plan
  • Insufficient commitment by the Architect to
    effectively operate as a Prime Contractor

10
Consequences
  • Delays in LTP delivery ( 1.5 years) reflects in
    additional cost to LPF Prime contractor (and ESA,
    CCN already negotiated)
  • Additional costs to LTP Architect (and ESA) due
    to late deliveries by suppliers
  • Additional costs due to the previous lower
    industrial estimates of the ESA LTP procurements
    (CMA and Integration) only partially offset by
    French contribution on the AOMU (also higher than
    estimated)
  • Delays in launch, hence delay in LISA

11
Remedy
  • Phasing period introduced in the LPF Prime
    contract to allow the LTP to Phase in
  • ESA Project Team to concentrate on critical LTP
    development
  • National suppliers to commit to current technical
    specifications, design baseline and plans
    (including delivery dates)
  • National suppliers to start contracts without
    delays
  • National suppliers to ensure funding and
    availability of contingency margins
  • National suppliers to guarantee adequacy of
    resources at institutes/industry
  • ESA/ASD to promote and maintain a culture of
    mutual trust, openness and team spirit.

12
LTP Short Term Planning
  • LTP situation needs to be redressed by September
    2005
  • A check point at the next Steering Committee
    meeting in July (date 14 July) shall ascertain
    that
  • Critical technologies are ready (TRR in June)
  • All contracts are in place
  • All parties have accepted the current
    specifications, design baseline and plans
  • All parties have ensured adequate resources
  • The LTP consortium is organised and committed to
    work as a team
  • LTP Preliminary Design Review successfully
    passed
  • The LTP development is managed by ESA/ASD/NPM
    according to the rules of the agreed Management
    Plan
  • Report to the SPC in November (verbal report in
    September) for reconfirmation after situation is
    sorted out

13
But what about the DRS?
  • JPL and NASA-HQ informed on the recommended
    cancellation of the GRS on April 27
  • ESA instructed ASU accordingly on April 29 in
    time for PDR in June. This change was beneficial
    to the spacecraft as would solve mass margin
    problem, mainly caused by envisaged non
    compliance of the LTP (25 kg)
  • NASA-HQ informed ESA on the GRS reinstatement on
    May 27
  • In order to solve mass and financial problems ESA
    decided to delete one redundant micropropulsion
    system (the cold gas)
  • PDR to be delayed of one month doc delivery end
    July, Board 29 September
  • Open issues
  • GRS reinstatement Stanford/JPL relations?
    Configuration change? Schedule change?
  • How do we protect programme against a FEEP
    failure? Back-up on ground (CG or FEEP)? Back-up
    on orbit (two FEEP systems)? Back-up by DRS
    colloidal?

14
To be confirmed
Write a Comment
User Comments (0)
About PowerShow.com