Title: NGAO System Design Phase Update
1NGAO System Design PhaseUpdate
- Peter Wizinowich, Rich Dekany, Don Gavel, Claire
Max, Sean Adkins - for NGAO Team
- SSC Meeting
- February 20, 2008
2Presentation Sequence
- Management
- Science Case Requirements
- System Design
- Summary
3Management
10/1/06
4/21/08
PDR
System Design Started
System Design Review
now
4Project Update
- Report 6 submitted to Directors on 2/4/08.
- http//www.oir.caltech.edu/twiki_oir/bin/view.cgi/
Keck/NGAO/SystemDesignPhasePlanning - Emphasis during this report period has been on
- Subsystem design (Sept. Feb.)
- Including updates to the functional requirements
- Systems Engineering Management Plan (Jan. Mar.)
- Other major completed activities
- Project replan science case requirements
- NSF TSIP funding awarded for preliminary design
phase - 2M of 2.7M preliminary design budget
- MOU for telescope time complete. Contract being
drafted. - No news yet on ATI proposal
5System Design Milestones
MILESTONE DATE STATUS
1 SD SEMP Approved 10/9/06 Complete
2 SD phase contracts in place 10/27/06 Complete
3 Science Requirements Summary v1.0 Release 10/27/06 Complete
4 System Requirements Document (SRD) v1.0 Release 12/8/06 Complete
5 Performance Budgets Summary v1.0 Release 6/15/07 Complete
6 SRD v2.0 Release 5/22/07 Nearly complete
7 Trade Studies Complete 6/22/07 Complete
8 SRD v3.0 Release 9/7/07 Not started
9 System Design Manual (SDM) v1.0 Release 9/21/07 Complete
10 Technical Risk Analysis V1.0 Release 9/21/07 Complete
11 Cost Review Complete 12/7/07 In process
12 SDM v2.0 Release 2/12/08 In process
13 System Design ReviewPackage Distributed 3/4/08 New date 3/18/08
14 System Design Review 3/31/08 New date 4/21/08
15 SDR Report Project Planning Presentation at SSC meeting 4/14/08 New date 4/30/08
Requirements ? Performance Budgets Trade
Studies ? System Architecture Functional
Requirements ? Subsystem Design Functional
Requirements ? Management Plan (post-SDR)
6Schedule Budget
- Schedule 73 of System Design Phase work
complete through Jan. - 48 of remaining work is system design. Wrapping
up at conceptual level. - Budget 89 of SD Phase budget (1170k) spent
through Jan.
7System Design Review
- Date April 21, 2008.
- Reviewers
- Brent Ellerbroek (TMT)
- Bob Fugate (formerly of SOR)
- Andrea Ghez (UCLA)
- Norbert Hubin (ESO, Chair)
- Nick Scoville (Caltech)
- Gary Sanders (TMT)
- Review will follow WMKO guidelines
- SDR package distributed with 2 weeks for reviewer
comments - Reviewer response distributed prior to review
final agenda set - SDR will focus on issues identified by reviewers
- Charter draft materials can be found at
http//www.oir.caltech.edu/twiki_oir/bin/view/Keck
/NGAO/SystemDesignReview
8Science Case Requirements
9Progress on Defining Science Requirements
- Release 2 of the Science Case Requirements
Document is complete - Release 2 of System Requirements Document is
almost complete - Observatory requirements further developed
- Remaining tasks identified and assigned
- David Le Mignant Liz McGrath supporting this
effort
10Updated Science Requirements Summary
11Each Science Driver has a Requirements Table
- Summarizes requirements discussed in text and
figures - Formatted for input into System Requirements
Document and into the Contour Database of
Functional Requirements - Example part of the Requirements Table for
High-Redshift Galaxies
12Progress on Science Cases
- Key Science Drivers new analysis and content
- Galaxy Assembly and Star Formation History
analysis of cooling requirements to decrease
background - Nearby Active Galactic Nuclei discussion of
required spatial resolution - General Relativity Effects at the Galactic Center
- Extrasolar Planets around Low-Mass Stars
definition of 3 target sets with distinct
requirements - Multiplicity of Minor Planets optimum
wavelengths and sampling - Science Drivers new analysis and content
- QSO Host Galaxies
- Gravitational Lensing (by galaxies and clusters)
- Characterization of Gas Giant and Ice Giant
Planets their Moons - Backup Science (be sure we can do good NGS
science when laser cant be used)
13NGAO System Design
14AO Opto-Mechanical Design
NGS WFS
Visible Imager
Rotator
DM2
DM1
to OSIRIS
NIR Imager
LGS WFS
Deployable IFS
15AO Wavefront Sensor Design
LGS pickoff WFS
Tip-Tilt Sensor
16System Configurations
Science Cases drive the AO system configurations
(i.e., required hardware control)
17System Configurations
18Summary
- Management
- Replan for remainder of system design phase
completed - Good progress on Systems Engineering Management
Plan - On track for System Design Review
- NSF TSIP funding for preliminary design!
- Technical
- Subsystem design phase completed
- Functional requirements completed
Team remains committed excited about NGAO!