Munawar B' Ahmad, PE - PowerPoint PPT Presentation

1 / 12
About This Presentation
Title:

Munawar B' Ahmad, PE

Description:

New power generation has remained static for about 7 years (Fig. VIII ) ... The NEA would be responsible for, and have the authority to undertake strategic ... – PowerPoint PPT presentation

Number of Views:44
Avg rating:3.0/5.0
Slides: 13
Provided by: energyup
Category:

less

Transcript and Presenter's Notes

Title: Munawar B' Ahmad, PE


1
Energy is our business
A NEW ENERGY MIX FOR PAKISTAN
THE PAKISTAN AND REGIONAL ENERGY FORUM
MOVING TOWARDS ENERGY SUFFICIENCY,
SUSTAINABILITY SOVEREIGNTY
by Munawar B. Ahmad, PE EMR-Consult Oct. 2009
2
Energy is our business
1. ROOTS OF PAKISTANS ENERGY CRISIS
  • Pakistan today is caught up in an acute Energy
    Crisis which has its roots in five (5) distinct
    causes, namely
  • Lack of Integrated Energy Planning Demand
    Forecasting and absence of central focused
    entity responsible for the Energy Sector
  • Imbalanced Energy Mix with heavy reliance on gas
    (47.5) and Oil (30.5) (72 imported)
  • Non-utilization of vast indigenous resources of
    Thar Coal and Hydel potential
  • Lack of effective project structuring, planning
    and implementation of indentified and viable
    projects
  • Inadequate Primary Energy Sources or access to,
    or local availability / development


3
Energy is our business
1. ROOTS OF PAKISTANS ENERGY CRISIS
  • As a consequence the energy shortages have
    snowballed with major supply chain and
    infrastructure gaps, namely
  • The Electric Power Sector has been in static
    non-growth mode from 2003-2008, and the peak
    supply-demand gap has grown to about 3,500 -
    4,000 MW from about 1,000 MW in 2006. (Fig. I
    (a), I (b) )
  • In the Gas Sector the demand - supply gap that
    emerged in 2007 has grown to about 800 MMcfd in
    2009 due to stalled import projects (Mashal, IPI,
    PGP) and local fields not developed / put in
    production for 5 years ( 500 MMcfd) (Fig.
    II )
  • Inadequate Energy Infrastructure supply to end
    customers both for electric power as well as fuel
    oil for Power Plants  has been constrained
  • Short Supply of Gas/Oil to Power Plants the
    crisis has been aggravated due to gas supply
    shortfall and reduced oil supply due to
    non-payment to OMCs


4
Energy is our business
4.1 - PAKISTANS PRIMARY ENERGY MIX
  • Pakistans Primary Energy Mix is essentially
    imbalanced even on a worldwide comparative basis,
    with dependence on gas at 47.5, oil at 30.5
    (72 imported) (Fig. V )
  • The 2005 Energy Plan, projected a continuing
    dependence of about 48 on Natural Gas in the
    2030 scenario, based on mega imports thru
    Transnational Pipelines (6.5 bcfd) and LNG (1.5
    bcfd) (Fig. VI )
  • With the continuing delay in the planned TNPs and
    LNG import projects (Mashal, PGP, Engro etc) the
    primary energy gap is increasing at an alarming
    rate
  • By 2015 the natural gas supply-demand gap after
    LNG imports of 1.0 bcfd (if implemented) will
    increase to 1.7 bcfd, and is unlikely to be
    covered as IPI cannot be completed in this time
    frame
  • There is clearly an essential need to plan a
    revised Primary Energy Mix along with a revised
    electricity generation plan by source in the 2010
    2030 scenario


5
Energy is our business
4.2 - PAKISTANS POWER GENERATION BY SOURCE
  • With rising cost of crude oil from 60 in 2005
    to 147 in 2008, Pakistans oil based thermal
    generation (32) became unsustainable and has
    resulted in a massive Energy Sector debt ( 3.6
    billion)
  • Coal utilization is about 9 in the Energy Mix,
    and only 0.1 for Power Generation vs. 72 in
    China, 56 in India and more than 50 in the
    USA (Fig. VII )
  • New power generation has remained static for
    about 7 years (Fig. VIII )
  • A more rational and Sustainable Energy Mix must
    be planned for the 2010-2030 scenario.
  • Significant increase in hydel power generation
    and optimum use of coal thru gasification and
    clean coal technologies
  • As a strategic priority Nuclear Electric Energy
    has to be increased to about 5 and Renewable to
    about 3 in the 2030 scenario



6
Energy is our business
5.1 THAR COAL UTILIZATION
Pakistans Thar Coal Potential
  • Worlds Single largest contiguous Coal field
    extending over 10,000 Sq KMs (Fig- IX )
  • Reserves of 175 200 billions tons exceed oil
    equivalent reserves of Saudi Arabia, Iraq, Iran,
    with a value of several trillion US (Figure-X
    )
  • Phased development can lead to 400 600 mt /year
    coal mining in 20 years
  • All of Pakistans energy requirements (Electric,
    Power, Gas, Diesel) can be met in 2020 2030
    scenario
  • The most recent ADB report (May 2007) states
    Thar lignite once mined, is a useable fuel or
    carbon resource and Coal to liquids-CTL is
    considered a serious utilization option
  • In addition to Electric Power, SNG, Chemicals,
    Fertilizer, etc can be produced for self
    consumption and surplus can be exported
    (Figure-XI )
  • Contribution to GDP in plants, products,
    services, employment, etc, would be in the range
    of 200b-300b which exceeds Pakistans current
    GDP of 170 b
  • Thar Coal is Gods Gift of Black Gold to the
    People of Pakistan and will ensure the Nations
    Energy Economic Future


6
7
Energy is our business
5.1 THAR COAL UTILIZATION
Co-Production Plants based on Thar Coal
Gasification
  • Coal production costs have to be in the range of
    20 - 25 /tons, which equates to a crude oil
    cost of about 50 per barrel in order to achieve
    economical levels
  • To achieve cost benchmark mine capacity of 50
    mtons/year is required in three phases of (1) 15
    mtons/yr (2) 30 mtons/yr and (3) 50 mtons/yr
  • Following co-production plants will need to be
    set-up in the three phases to match with coal
    production over 3-5 years
  • Phase 1) IGCC 500 mw (3 mtons/yr) and SNG 250
    mmcfd (12 mtons/yr). Total 15 mt/yr
  • Phase 2) IGCC 500 mw (3 mtons/yr) and FTD
    30,000 barrels/day (12 mtons/yr). Total 30 mt/yr
  • Phase 3) SNG 250 mmcfd (12 mtons/yr) and FTD
    20,000 barrels/day (8 mtons/yr). Total 50 mt/yr
  • In subsequent phases, chemical and fertilizer
    plants would be set-up as part of a Mega
    Petro-Chemical Complex which would be supported
    by additional coal mining
  • Power transmission line of 500 KV will be planned
    and constructed for 1000 mw power dispersal to
    NTDC Network
  • A 36-42 Hi-Pressure Gas Transmission Pipeline
    will be planned and constructed to connect to the
    SSGC Network at Hyderabad / Jamshoro

7
8
Energy is our business
5.2 - HYDEL POWER GENERATION
  • The country has an estimated Hydro Resources
    Potential of about 45,000 MW, currently whereas
    only 6,500 MW have been installed with 11 share
    in the Energy Mix.
  • It is proposed in the long term scenario to
    increase share of Hydro in Primary Energy from
    6,500 MW (11) at present to about 32,100 MW
    (20) by 2030 (30 share in Power Generation)
  • This will entail set up of 8,000 MW small/medium
    hydro units on rivers/canals, run of the river
    plants and four large hydro multipurpose
    reservoirs/dams with capacity of about 17,600 MW
    upto 2030
  • The four large Hydro Dams are, (i) Kalabagh
    3,800 MW, (ii) Bhasha 4,600 MW, (iii) Bunji
    5,400 MW, (iv) Dasu 3,800 MW
  • It is necessary to maintain an optimal
    Hydro/Thermal Mix, in base load operations to
    cater for reduction in output during low hydel
    periods.

8
9
Energy is our business
7. SET-UP OF NATIONAL ENERGY AUTHORITY - NEA
  • An essential step towards preparation and
    implementation of a National Energy Plan is the
    set-up of a statutory body, The National Energy
    Authority (NEA)
  • The NEA would be an independent and focal entity
    with a Chairman and 12 Board members, (6 private
    sector professionals and 6 energy sector experts,
    MDs etc from the Public Sector/GOP)
  • The NEA would be responsible for, and have the
    authority to undertake strategic planning in the
    Energy Sector and prepare a comprehensive ENERGY
    POLICY.
  • The NEA would prepare an integrated and
    Comprehensive National Energy Plan (NEP) for the
    Short, Medium and Long Term based on robust
    projections on a scientific basis.
  • The NEA would also identify, plan and pursue
    implementation of Energy Sector Infrastructure
    augmentation/expansion by the OMCs, PEPCO, SSGC,
    SNGPL etc.
  • The NEA would coordinate with the sectoral
    organizations, public companies OMCs, EP
    Companies, IPPs etc and relevant Ministries etc
    for the NEP implementation
  • The NEA will also act as a monitoring authority
    for all Energy Sector projects, and ensure
    compliance to project road-maps and milestones


10
Figure-VII
Energy is our business
PRIMARY ENERGY SUPPLY BY SOURCE 2007-2008
ELECTRICITY GENERATION BY SOURCE 2007-2008
Coal Power Generation
11
Figure- XII
Energy is our business
PRIMARY ENERGY MIX (a)
Current 2008
2030 Per 2005 Energy Plan
Revised Plan 2030
12
Figure- XIII
Energy is our business
ELECTRICITY GENERATION BY SOURCE (b)
Current 2008
2030 Per 2005 Energy Plan
Revised Plan 2030
Write a Comment
User Comments (0)
About PowerShow.com