Title: Munawar B' Ahmad, PE
1 Energy is our business
A NEW ENERGY MIX FOR PAKISTAN
THE PAKISTAN AND REGIONAL ENERGY FORUM
MOVING TOWARDS ENERGY SUFFICIENCY,
SUSTAINABILITY SOVEREIGNTY
by Munawar B. Ahmad, PE EMR-Consult Oct. 2009
2 Energy is our business
1. ROOTS OF PAKISTANS ENERGY CRISIS
- Pakistan today is caught up in an acute Energy
Crisis which has its roots in five (5) distinct
causes, namely - Lack of Integrated Energy Planning Demand
Forecasting and absence of central focused
entity responsible for the Energy Sector - Imbalanced Energy Mix with heavy reliance on gas
(47.5) and Oil (30.5) (72 imported) - Non-utilization of vast indigenous resources of
Thar Coal and Hydel potential - Lack of effective project structuring, planning
and implementation of indentified and viable
projects - Inadequate Primary Energy Sources or access to,
or local availability / development
3 Energy is our business
1. ROOTS OF PAKISTANS ENERGY CRISIS
- As a consequence the energy shortages have
snowballed with major supply chain and
infrastructure gaps, namely - The Electric Power Sector has been in static
non-growth mode from 2003-2008, and the peak
supply-demand gap has grown to about 3,500 -
4,000 MW from about 1,000 MW in 2006. (Fig. I
(a), I (b) ) - In the Gas Sector the demand - supply gap that
emerged in 2007 has grown to about 800 MMcfd in
2009 due to stalled import projects (Mashal, IPI,
PGP) and local fields not developed / put in
production for 5 years ( 500 MMcfd) (Fig.
II ) - Inadequate Energy Infrastructure supply to end
customers both for electric power as well as fuel
oil for Power Plants has been constrained - Short Supply of Gas/Oil to Power Plants the
crisis has been aggravated due to gas supply
shortfall and reduced oil supply due to
non-payment to OMCs
4 Energy is our business
4.1 - PAKISTANS PRIMARY ENERGY MIX
- Pakistans Primary Energy Mix is essentially
imbalanced even on a worldwide comparative basis,
with dependence on gas at 47.5, oil at 30.5
(72 imported) (Fig. V ) - The 2005 Energy Plan, projected a continuing
dependence of about 48 on Natural Gas in the
2030 scenario, based on mega imports thru
Transnational Pipelines (6.5 bcfd) and LNG (1.5
bcfd) (Fig. VI ) - With the continuing delay in the planned TNPs and
LNG import projects (Mashal, PGP, Engro etc) the
primary energy gap is increasing at an alarming
rate - By 2015 the natural gas supply-demand gap after
LNG imports of 1.0 bcfd (if implemented) will
increase to 1.7 bcfd, and is unlikely to be
covered as IPI cannot be completed in this time
frame - There is clearly an essential need to plan a
revised Primary Energy Mix along with a revised
electricity generation plan by source in the 2010
2030 scenario
5 Energy is our business
4.2 - PAKISTANS POWER GENERATION BY SOURCE
- With rising cost of crude oil from 60 in 2005
to 147 in 2008, Pakistans oil based thermal
generation (32) became unsustainable and has
resulted in a massive Energy Sector debt ( 3.6
billion) - Coal utilization is about 9 in the Energy Mix,
and only 0.1 for Power Generation vs. 72 in
China, 56 in India and more than 50 in the
USA (Fig. VII ) - New power generation has remained static for
about 7 years (Fig. VIII ) - A more rational and Sustainable Energy Mix must
be planned for the 2010-2030 scenario. - Significant increase in hydel power generation
and optimum use of coal thru gasification and
clean coal technologies - As a strategic priority Nuclear Electric Energy
has to be increased to about 5 and Renewable to
about 3 in the 2030 scenario
6 Energy is our business
5.1 THAR COAL UTILIZATION
Pakistans Thar Coal Potential
- Worlds Single largest contiguous Coal field
extending over 10,000 Sq KMs (Fig- IX ) - Reserves of 175 200 billions tons exceed oil
equivalent reserves of Saudi Arabia, Iraq, Iran,
with a value of several trillion US (Figure-X
) - Phased development can lead to 400 600 mt /year
coal mining in 20 years - All of Pakistans energy requirements (Electric,
Power, Gas, Diesel) can be met in 2020 2030
scenario - The most recent ADB report (May 2007) states
Thar lignite once mined, is a useable fuel or
carbon resource and Coal to liquids-CTL is
considered a serious utilization option - In addition to Electric Power, SNG, Chemicals,
Fertilizer, etc can be produced for self
consumption and surplus can be exported
(Figure-XI ) - Contribution to GDP in plants, products,
services, employment, etc, would be in the range
of 200b-300b which exceeds Pakistans current
GDP of 170 b - Thar Coal is Gods Gift of Black Gold to the
People of Pakistan and will ensure the Nations
Energy Economic Future
6
7 Energy is our business
5.1 THAR COAL UTILIZATION
Co-Production Plants based on Thar Coal
Gasification
- Coal production costs have to be in the range of
20 - 25 /tons, which equates to a crude oil
cost of about 50 per barrel in order to achieve
economical levels - To achieve cost benchmark mine capacity of 50
mtons/year is required in three phases of (1) 15
mtons/yr (2) 30 mtons/yr and (3) 50 mtons/yr - Following co-production plants will need to be
set-up in the three phases to match with coal
production over 3-5 years - Phase 1) IGCC 500 mw (3 mtons/yr) and SNG 250
mmcfd (12 mtons/yr). Total 15 mt/yr - Phase 2) IGCC 500 mw (3 mtons/yr) and FTD
30,000 barrels/day (12 mtons/yr). Total 30 mt/yr - Phase 3) SNG 250 mmcfd (12 mtons/yr) and FTD
20,000 barrels/day (8 mtons/yr). Total 50 mt/yr - In subsequent phases, chemical and fertilizer
plants would be set-up as part of a Mega
Petro-Chemical Complex which would be supported
by additional coal mining - Power transmission line of 500 KV will be planned
and constructed for 1000 mw power dispersal to
NTDC Network - A 36-42 Hi-Pressure Gas Transmission Pipeline
will be planned and constructed to connect to the
SSGC Network at Hyderabad / Jamshoro -
7
8 Energy is our business
5.2 - HYDEL POWER GENERATION
- The country has an estimated Hydro Resources
Potential of about 45,000 MW, currently whereas
only 6,500 MW have been installed with 11 share
in the Energy Mix. - It is proposed in the long term scenario to
increase share of Hydro in Primary Energy from
6,500 MW (11) at present to about 32,100 MW
(20) by 2030 (30 share in Power Generation) - This will entail set up of 8,000 MW small/medium
hydro units on rivers/canals, run of the river
plants and four large hydro multipurpose
reservoirs/dams with capacity of about 17,600 MW
upto 2030 - The four large Hydro Dams are, (i) Kalabagh
3,800 MW, (ii) Bhasha 4,600 MW, (iii) Bunji
5,400 MW, (iv) Dasu 3,800 MW - It is necessary to maintain an optimal
Hydro/Thermal Mix, in base load operations to
cater for reduction in output during low hydel
periods.
8
9 Energy is our business
7. SET-UP OF NATIONAL ENERGY AUTHORITY - NEA
- An essential step towards preparation and
implementation of a National Energy Plan is the
set-up of a statutory body, The National Energy
Authority (NEA) - The NEA would be an independent and focal entity
with a Chairman and 12 Board members, (6 private
sector professionals and 6 energy sector experts,
MDs etc from the Public Sector/GOP) - The NEA would be responsible for, and have the
authority to undertake strategic planning in the
Energy Sector and prepare a comprehensive ENERGY
POLICY. - The NEA would prepare an integrated and
Comprehensive National Energy Plan (NEP) for the
Short, Medium and Long Term based on robust
projections on a scientific basis. - The NEA would also identify, plan and pursue
implementation of Energy Sector Infrastructure
augmentation/expansion by the OMCs, PEPCO, SSGC,
SNGPL etc. - The NEA would coordinate with the sectoral
organizations, public companies OMCs, EP
Companies, IPPs etc and relevant Ministries etc
for the NEP implementation - The NEA will also act as a monitoring authority
for all Energy Sector projects, and ensure
compliance to project road-maps and milestones
10Figure-VII
Energy is our business
PRIMARY ENERGY SUPPLY BY SOURCE 2007-2008
ELECTRICITY GENERATION BY SOURCE 2007-2008
Coal Power Generation
11Figure- XII
Energy is our business
PRIMARY ENERGY MIX (a)
Current 2008
2030 Per 2005 Energy Plan
Revised Plan 2030
12Figure- XIII
Energy is our business
ELECTRICITY GENERATION BY SOURCE (b)
Current 2008
2030 Per 2005 Energy Plan
Revised Plan 2030