Transcript and Presenter's Notes

Title: US ATLAS Tier 1 Facility


1
US ATLAS Tier 1 Facility
  • Rich Baker
  • Brookhaven National Laboratory
  • Review of U.S. LHC Software and Computing
    Projects
  • Fermi National Laboratory
  • November 27-30, 2001

2
Tier 1 Status, Fall 2000
  • Small but Growing User Community
  • CPU Dominated Facility (FY 00 Purchase)
  • Monte Carlo Production Use
  • Many Facility Components Shared with RCF
  • Plans for FY 01
  • Milestone Tier 1 Storage Prototype September,
    2001
  • Purchase and Deploy ATLAS HW for Storage Systems
  • Address Scalability for Data Challenges
  • Begin Staffing for Data Challenges
  • Reduce RCF Dependence

3

4
Progress in FY 01
  • Supplemental Funding in August 2001
  • Milestone Tier 1 Storage Prototype September
    2001
  • Goal Purchase and Deploy ATLAS HW for Storage
  • HPSS Dedicated Service Established October 2001
  • Still Use RCF Core Services
  • AFS /afs/usatlas Cell Commissioned November 2001
  • NFS Deferred until June 2002
  • Staffing Delayed November 2001 Hire
  • Technology Evaluation in Progress

5
Progress in FY 01 (2)
  • Goal Address Scalability for Data Challenges
  • LAN Upgrade Cisco 6500 Series Switch
    Sufficient for DC2 Requirements
  • All Storage Systems are Expandable
  • Processor Farm also Expandable
  • No Infrastructure Limitations Foreseen

6
Progress in FY 01 (3)
  • Goal Begin Staffing for Data Challenges
  • Funding Constraints Limit Progress in Staffing
  • Support for Data Challenges will be Stressed

Tier 1 Facility Staffing Levels
Includes 0.5 FTE PPDG Effort for 2002 and 2003
7
Recent Staffing and Near Term Plan
  • Dantong Yu Network, Grid, Monitoring - April,
    2001
  • 0.5 FTE PPDG Funding 2002 2004
  • Jason Smith Software Projects, Grid - July, 2001
  • Significant Improvement in User Support
  • John McCarthy Solaris, Disk Storage - November,
    2001
  • Will Support Disk Technology Evaluation Effort
  • Projected Hires for FY 03
  • Linux Support
  • Network
  • Mass Storage

8
Progress in FY 01 (4)
  • Goal Reduce RCF Dependence
  • LAN is (mostly) Isolated
  • Storage Systems Increasingly Separated from RCF
  • Most Utility Services now Independent

9

10
New Cisco Switch
11
Intel/Linux Farm
12
Tier 1 Status, Fall 2001
  • More than 100 Registered Users and Growing
  • (Still) CPU Dominated Facility
  • Monte Carlo Production Use Still Dominates
  • Facility Hardware Configured for Expandability
  • Plans for FY 02
  • Complete Deployment of Storage System Prototypes
  • Encourage Transition to Distributed Analysis
    Environment
  • Post DC1 GriPhyN Goal Serve All ESD for GRID
    Users
  • Evaluate ATLAS World Wide Computing Model
  • Develop Tools for Distributed Monitoring and
    Network Support
  • Next Major Milestones Data Challenge 2 in FY 03