Title: RPF Binder Distributor Task Team Feedback


1
RPF Binder Distributor Task Team Feedback
  • 21 May 2003
  • Pietermaritzburg

2
Task Team Mandate
  • A resolution was passed at the May 2002 RPF to
    form a task team to address issues relating to
    binder distributors namely
  • Appropriate validation period for calibration
    certificates
  • Develop a rational method for the bakkie test
  • Compliance criteria for transverse distribution
  • Spray tolerances for various binders
  • Protocol for flushing and testing spray bars
    on-site in line with HSE requirements

3
Recommendations of Task Team
  • Agreement was reached by the Task Team on the
    following issues
  • 12 month validation period for calibration
    certificates
  • Test method protocol for bakkie test
  • Bakkie test tolerances
  • Bakkie test register
  • Spray rate tolerances
  • Where applicable the above proposals to be
    included in the revision of TRH 3

4
Bakkie test tolerances
5
Recommendations of Task Team
  • Agreement was reached by the Task Team on the
    following issues
  • 12 month validation period for calibration
    certificates
  • Test method protocol for bakkie test
  • Bakkie test tolerances
  • Bakkie test register
  • Spray rate tolerances
  • Where applicable the above proposals to be
    included in the revision of TRH 3

6
Spray rate tolerances
  • Max variation from specified rate to be largest
    value of
  • - 0.06 l/m2 for any binders (net cold)
  • - 5 at spray temperature for
  • Conventional binders (pen, cut, emul)
  • PMBs
  • Bitumen rubber
  • - 5 at net cold for bitumen emulsions
  • Payment reduction factors and remedial measures
  • Min lot size of 4,000 litres

7
Best practice related to binder distributors
the environment
  • Update Sabita Manual 8 to incorporate best
    practice wrt
  • Latest HSE legislation
  • Transporting, storage and application of binders
    on-site
  • Latest Austroads publication Bitumen Sealing
    Safety Guide
  • Draft document to be submitted to Sabitas COSHEC
    focus group for approval

8
Outstanding issues
  • Complete investigation into pad test to measure
    transverse longitudinal distribution
  • Revision of TMH 2 fixed pit calibration of
    binder distributors
  • Update COTO General specifications for roads
    bridge works

9
Summary
  • Concern over updating existing COLTO TRH 2
    documents
  • Above recommendations to be circulated for
    comments tdistin_at_colas.co.za
  • Although mandated tasks are complete the task
    team will continue to meet to address outstanding
    issues