PERT - PowerPoint PPT Presentation

1 / 9
About This Presentation
Title:

PERT

Description:

... activity duration in CPM to work out the critical path and the project duration ... First, work out a value (calles the normal variate) Z, as follows: Z=(T ... – PowerPoint PPT presentation

Number of Views:32
Avg rating:3.0/5.0
Slides: 10
Provided by: perdanaFs
Category:
Tags: pert | critical

less

Transcript and Presenter's Notes

Title: PERT


1
PERT
2
What is PERT?
  • Cases where activity durations are uncertain or
    subject to uncontrollable variation, exact
    project duration cannot be worked out. In this
    case use PERT
  • PERT uses 3 estimates instead of one for each
    activity
  • From these, the mean duration for each activity
    can be computed
  • The statistical standard deviation of the
    activity duration can also be computed
  • From the mean, we can compute (by theory of
    statistics)
  • The standard deviation of the project duration
  • The probabililty of the project being completed
    within certain times
  • PERT suitable for RD projects

3
Time Estimates
  • For each activity, 3 estimates of the activity
    duration are needed
  • aoptimistic time (if execution goes well)
  • bpessimistic time (if execution goes badly)
  • mmost likely time (if execution is normal)
  • The mean
  • Te(a4mb)/6
  • The standard deviation which gives an indication
    of the possible spread of activity duration
  • ?i(b-a)/6

4
Mean and Standard Deviation of Project Duration
  • Once the expected time te for all activities has
    been computed, proceed to use te in place of the
    single activity duration in CPM to work out the
    critical path and the project duration
  • The resulting project duration is the mean
    project duration TE
  • We also need to work out the standard deviation
    of the project duration ? as follows
  • Project Duration ? ?(Summation of ?i2 f all the
    activities on the critical path)

5
Probability of Different Project Durations
  • From statistics, once we know the mean project
    duration, TE, and the standard deviation of the
    project duration, ? we can work out the
    probability that the project duration will be
    shorter than any specific time, T (i.e. the
    project will take T days or less) through the
    following formula
  • Z(T- TE )/ ? , where Z is the quantity called
    the Normal variate
  • Knowing Z, we can read off the probability from
    Normal Distribution Tables which are provided in
    nest slides

6
Normal Distribution Table for Negative Values of Z
7
Normal Distribution Table for Positive Values of Z
Z Probability --------------------- 0.0
0.5000 0.1 0.5398 0.2 0.5793 0.3 0.6179
0.4 0.6554 0.5 0.6915 0.6 0.7257 0.7
0.7580 0.8 0.7881 0.9 0.8159 1.0 0.8413
1.1 0.8643 1.2 0.8849 1.3 0.9032 1.4
0.9192 1.5 0.9332
Z Probability --------------------- 1.6
0.9452 1.7 0.9554 1.8 0.9641 1.9
0.9713 2.0 0.9772 2.1 0.9821 2.2
0.9861 2.3 0.9893 2.4 0.9918 2.5
0.9938 2.6 0.9953 2.7 0.9965 2.8
0.9974 2.9 0.9981 3.0 0.9987 gt3.0 1
8
Example
  • Consider a project with TE 5days and ?2
    days.If we wish to find out the probability that
    the project will take 7 days or less. Thus
    T7days. First, work out a value (calles the
    normal variate) Z, as follows
  • Z(T- TE )/ ?(7-5)/21
  • Read off the Normal Distribution Tables, the
    probability for Z1. We get the value 0.8413.
    Thus the probability that the project will take 7
    days or less is 0.8413
  • If we need to find the probability that the
    project takes more than 7 days, we make use of
    the fact that
  • Probability that project takes more than x days
    1-Probability that project takes x days or less
  • Probability that project takes more than 7 days
    1-Probability that project takes 7 days or less
    1-0.84130.1587

9
Interpolating from the Normal Distribution Table
  • In the previous example, the Z value was 1.0
    and could be read off directly. If you had a
    value like 1.01, you could still round it off to
    1.0
  • However there will be instances when you will get
    a value like 1.275, in which case you will need
    to interpolate from the table
  • From the table Z11.2, P10.8849
  • Z21.3, P20.9039
  • Use the interpolation formula
  • PP1Z-Z1 (P2-P1)
  • Z2-Z1
  • Therefore at Z1.275,
  • P0.8849 1.275 -1.2 (0.9039-0.8849) 0.8992
  • 1.3-1.2
Write a Comment
User Comments (0)
About PowerShow.com