Title: PERT
1PERT
2What is PERT?
- Cases where activity durations are uncertain or
subject to uncontrollable variation, exact
project duration cannot be worked out. In this
case use PERT - PERT uses 3 estimates instead of one for each
activity - From these, the mean duration for each activity
can be computed - The statistical standard deviation of the
activity duration can also be computed - From the mean, we can compute (by theory of
statistics) - The standard deviation of the project duration
- The probabililty of the project being completed
within certain times - PERT suitable for RD projects
3Time Estimates
- For each activity, 3 estimates of the activity
duration are needed - aoptimistic time (if execution goes well)
- bpessimistic time (if execution goes badly)
- mmost likely time (if execution is normal)
- The mean
- Te(a4mb)/6
- The standard deviation which gives an indication
of the possible spread of activity duration - ?i(b-a)/6
4Mean and Standard Deviation of Project Duration
- Once the expected time te for all activities has
been computed, proceed to use te in place of the
single activity duration in CPM to work out the
critical path and the project duration - The resulting project duration is the mean
project duration TE - We also need to work out the standard deviation
of the project duration ? as follows - Project Duration ? ?(Summation of ?i2 f all the
activities on the critical path)
5Probability of Different Project Durations
- From statistics, once we know the mean project
duration, TE, and the standard deviation of the
project duration, ? we can work out the
probability that the project duration will be
shorter than any specific time, T (i.e. the
project will take T days or less) through the
following formula - Z(T- TE )/ ? , where Z is the quantity called
the Normal variate - Knowing Z, we can read off the probability from
Normal Distribution Tables which are provided in
nest slides
6Normal Distribution Table for Negative Values of Z
7Normal Distribution Table for Positive Values of Z
Z Probability --------------------- 0.0
0.5000 0.1 0.5398 0.2 0.5793 0.3 0.6179
0.4 0.6554 0.5 0.6915 0.6 0.7257 0.7
0.7580 0.8 0.7881 0.9 0.8159 1.0 0.8413
1.1 0.8643 1.2 0.8849 1.3 0.9032 1.4
0.9192 1.5 0.9332
Z Probability --------------------- 1.6
0.9452 1.7 0.9554 1.8 0.9641 1.9
0.9713 2.0 0.9772 2.1 0.9821 2.2
0.9861 2.3 0.9893 2.4 0.9918 2.5
0.9938 2.6 0.9953 2.7 0.9965 2.8
0.9974 2.9 0.9981 3.0 0.9987 gt3.0 1
8Example
- Consider a project with TE 5days and ?2
days.If we wish to find out the probability that
the project will take 7 days or less. Thus
T7days. First, work out a value (calles the
normal variate) Z, as follows - Z(T- TE )/ ?(7-5)/21
- Read off the Normal Distribution Tables, the
probability for Z1. We get the value 0.8413.
Thus the probability that the project will take 7
days or less is 0.8413 - If we need to find the probability that the
project takes more than 7 days, we make use of
the fact that - Probability that project takes more than x days
1-Probability that project takes x days or less - Probability that project takes more than 7 days
1-Probability that project takes 7 days or less
1-0.84130.1587
9Interpolating from the Normal Distribution Table
- In the previous example, the Z value was 1.0
and could be read off directly. If you had a
value like 1.01, you could still round it off to
1.0 - However there will be instances when you will get
a value like 1.275, in which case you will need
to interpolate from the table - From the table Z11.2, P10.8849
- Z21.3, P20.9039
- Use the interpolation formula
- PP1Z-Z1 (P2-P1)
- Z2-Z1
- Therefore at Z1.275,
- P0.8849 1.275 -1.2 (0.9039-0.8849) 0.8992
- 1.3-1.2