HERA Machine Developement - PowerPoint PPT Presentation

1 / 12
About This Presentation
Title:

HERA Machine Developement

Description:

Demonstrate, that the IR vacuum and proton background conditions is improving by ... protons, new coils for p low-b quads, DC-bias a sc couplers, improvemens in ... – PowerPoint PPT presentation

Number of Views:23
Avg rating:3.0/5.0
Slides: 13
Provided by: ferdinan6
Category:

less

Transcript and Presenter's Notes

Title: HERA Machine Developement


1
HERA Machine Developement
  • January-February 2003
  • F. Willleke, MHE

2
Preliminary HERA Schedule 2003 Preliminary HERA Schedule 2003 Preliminary HERA Schedule 2003 Preliminary HERA Schedule 2003 Preliminary HERA Schedule 2003 Preliminary HERA Schedule 2003
Status of 1/16/2003 1302        
    Begin   Days   End
Startup 2003   2-Jan-03   6   8-Jan-03
Luminosity Operation   8-Jan-03   29   6-Feb-03
Maintenance day   6-Feb-03   1   7-Feb-03
Luminosity Operation   7-Feb-03   10   17-Feb-03
Polarisation Studies   17-Feb-03   14   3-Mar-03
Shut Down   3-Mar-03   126   7-Jul-03
Start-up   7-Jul-03   7   13-Jul-03
Machine Studies   13-Jul-03   14   27-Jul-03
Polarization Studies   27-Jul-03   11   7-Aug-03
Maintenance day   7-Aug-03   1   8-Aug-03
Luminosity Operation   8-Aug-03   27   4-Sep-03
Maintenance day   4-Sep-03   1   5-Sep-03
Luminosity Operation   5-Sep-03   27   2-Oct-03
Maintenance day   2-Oct-03   1   3-Oct-03
Luminosity Operation   3-Oct-03   34   6-Nov-03
Maintenance day   6-Nov-03   1   7-Nov-03
Luminosity Operation   7-Nov-03   27   4-Dec-03
Maintenance day   4-Dec-03   1   5-Dec-03
Luminosity Operation   5-Dec-03   10   15-Dec-03
Machine Studies   15-Dec-03   7   22-Dec-03
Shut Down   22-Dec-03   14   5-Jan-04
3
HERA Goals in January/February 2003 last update
January 13, 2003-01-13
  • High Priority Items
  • Demonstrate, that the IR vacuum and proton
    background conditions is improving by continuous
    running
  • Demonstrate safe running with 50mA of Positrons
  • Demonstrate a luminosity of at least 4 x 1031
    cm-2 s-1
  • Turn on rotators North and South and store and
    accelerate high intensity positron beam
  • Demonstrate polarized beams with 3 rotators

4
Plan for HERA Machine Studies (update
08.01.2003)
  • PARASITIC
  • check consistency optics optimization ?operation
  • bunch-to-bunch Q_s spread check whether 47kHz
    amplit. mod. of on 208MHz system damps
    longitudinal multibunch instabilities (done)
  • test lumi optimization autopilot (looks good)
  • test F.Brinkers program for viewing the e orbit
    at IPs
  • Test new version of Auto OrbCorr which
    incorporates other than IR-coils
  • practice e-ramp lumi procedure with increasing
    current (progress delayed by a least 1 week)
  • machine file service (regularly)
  • Injection optimization (regularly)

5
TODO
  • MAXIMUM SPECIFIC (and ABSOLUTE) LUMINOSITY
  • condition p-ring towards I_p gt 100mA
  • BB-beta-beat minimize BB-beta-beat with phase
    trombone prepare an optics with fixed phase
    shift in the west
  • measure BB tune shift and L_spec vs. proton bunch
    current with collisions at only one IP at time
  • Miscellaneous
  • RF-calibration 208MHz 52MHz
  • Analyse the 28Hz line that comes from 52MHz
    system 2
  • IR-magnet alignment vs. positron current at
    27.5GeV
  • understand the -1.5mm horizontal orbit shift at
    H1
  • dynamical aperture HERA e/p
  • beam based alignment / straight N S
  • try to understand phase jumps at QP33 S / QP35 S
    then ORM
  • Test improved phase loop-I

6
TODO
  • MAXIMUM POLARIZATION WITH ALL THREE ROTATOR PAIRS
  • (N,O,S) (w/o solenoids at first...)
  • Re-establish polarization tunes
  • measure the dispersion
  • scan Qs and Qx for synchrotron sidebands
  • phase advance between cavity section
  • prepare an optics with fixed phase shift in the
    west
  • dispersion e emittance vs. lumi-bump-H4A (H1
    ZEUS) use the wire-scanner measure dispersion
  • Vary dispersion in cavities
  • POLARIZATION TUNING
  • rotator pair OL/OR only
  • tunes, orbit, E-scan, harmonic bumps, etc.
  • all three pairs tunes, orbit, Energy-scan,
    harmonic bumps, etc.

7
TODO
  • BACKGROUND STUDIES
  • long positron-only run with high initial current
  • Vary (up/down) f0 to increase/decrease bunch
    length watching vacuum pressure and H1 beam-pipe
    temperature first tests already
    done in December

8
HERA Operational Efficiency
  • HERA I had two difficult problems
  • Dust problem for electron operation,
    mitigated by replacing the intergrate ion pumps
    by NEG pumps
  • Availability of the Accelerator Complex
    Operational Efficiency
    improved by a major upgrade in SD97/98
    addional RF station, new 8kA PS for protons, new
    coils for p low-b quads, DC-bias a sc couplers,
    improvemens in p-Inj line, Improvements in e-Inj,
    ..

9
(No Transcript)
10
Lessons learnedagrees with Tevatron, SLC, LEP
Experience
  • Dont do regular machine study which interupts
    routineoperations
  • Dont do frequent regular maintenance
  • Dont do long shudowns
  • Dont cange operational procedures and
    operational parameters
  • Push smoothly and continuously for better
    performance
  • Do long runs
  • all this was violated for most of
    2002 running

11
  • Frequent changes of Operation mode (p, e
    only, different bunch patters, high/low
    intensity, with/without collision, scubbing)
  • Machine studies severval topics not
    satisfactorily explored in 2001 coupling,
    beam optics verification, beam based alignment,
    e-beam stability, investigation of beam-beam
    effect, e/p injection efficiency

12
Injection times improved
Scheduled downtime plus long time vacuum
interventions
Background studies, single beam runs, etc
Write a Comment
User Comments (0)
About PowerShow.com