Schedule Tasks - PowerPoint PPT Presentation

1 / 36
About This Presentation
Title:

Schedule Tasks

Description:

... can use groups to indicate the department a human resource belongs to or to ... You can also click Address and select a resource from your e-mail address book ... – PowerPoint PPT presentation

Number of Views:25
Avg rating:3.0/5.0
Slides: 37
Provided by: perdanaFs
Category:

less

Transcript and Presenter's Notes

Title: Schedule Tasks


1
Schedule Tasks
2
Lesson When will tasks start and finish?
  • how to address the tasks relate to each other and
    to specific dates. There are many types of task
    relationships, such as links that show one task
    starting as another finishes. These links are
    called task dependencies. Microsoft Project
    automatically determines the start and finish
    dates for tasks that have dependencies to other
    tasks.
  • The advantage of dependencies or "linked" tasks
    is that whenever a task changes, linked tasks are
    automatically rescheduled. You can refine task
    schedules using constraints, overlap or delay
    tasks, and split tasks when work stops
    temporarily.

3
Establish relationships between tasks
  • To establish relationships between tasks, use
    task dependencies. First, select the related
    tasks, link them, and then change the dependency
    type, if necessary. The task whose start or
    finish depends on another task is the successor.
    The task that the successor is dependent on is
    the predecessor. For example, if you link "Hang
    clock" to "Paint wall," then "Hang clock" is the
    successor and "Paint wall" is the predecessor.
  • After the tasks are linked, changes to the
    predecessor's dates affect the successor's dates.
    Microsoft Project creates a finish-to-start task
    dependency by default. Because a finish-to-start
    dependency does not work in every situation, you
    can change the task link to start-to-start,
    finish-to-finish, or start-to-finish to model
    your project realistically.

4
How?
  • On the View menu, click Gantt Chart.
  • In the Task Name field, select two or more tasks
    to link in the order you want them linked. To
    select adjacent tasks, hold down SHIFT, and then
    click the first and last task you want to link.
  • To select nonadjacent tasks, hold down CTRL, and
    then click the tasks you want to link, in order.
  • Click Link Tasks
  • To change the task link, double-click the link
    line between the tasks you want to change.
  • The Task Dependency dialog box appears. If the
    Bar Styles dialog box appears, you didn't click
    precisely on the task link and need to close this
    dialog box and click on the task link again.
  • 5. In the Type box, select the task link you
    want, and then click OK.
  • Note   To unlink tasks, select the tasks you want
    to unlink in the Task Name field, and then click
    Unlink Tasks . The tasks are rescheduled based
    on existing links to other tasks, or constraints.

5
Link task
Unlink task
6
Overlap tasks or add lag time between them
  • After you've sequenced tasks by linking them, you
    can overlap or delay them as well. In Microsoft
    Project, delay tasks by adding lag time to the
    predecessor task, and overlap tasks by entering
    lead time. You can also enter lead or lag time as
    a percentage of the task.
  • 1 In the Task Name field, click the task you want
    to add lead or lag time to (it must have
    predecessors), and then click Task Information
  • 2 Click the Predecessors tab.
  • 3 In the Lag column, type the lead time or lag
    time you want, as a duration or as a percentage
    of the predecessor task duration.
  • Type lead time as a negative number (for example,
    2d for two days lead time) or as a percentage.
  • Type lag time as a positive number or as a
    percentage.
  • 4 Click OK.

7
Set a specific start or finish date for a task
  • You can schedule your tasks most effectively by
    entering task durations, creating dependencies
    between tasks, and then letting Microsoft Project
    calculate the start and finish dates for you.
    However, you can set a specific start or finish
    date for a task if necessary. Task constraints
    that tie tasks to specific dates are called
    inflexible constraints the most inflexible
    constraints are specific start or finish dates.
    Because Microsoft Project takes constraints into
    account when calculating your schedule, use these
    inflexible constraints only when tasks must start
    or finish on a specific date.
  • 1 In the Task Name field, click the task you want
    to set a start or finish date for, and then click
    Task Information .
  • 2 Click the Advanced tab.
  • 3 In the Constraint type box, click a constraint
    type.
  • 4 Type or select a date in the Constraint date
    box, and then click OK.
  • Note   If you select a start date for a task in
    the Start field of the Gantt Chart, or if you
    drag a Gantt bar to change the start date,
    Microsoft Project sets a Start No Earlier Than
    (SNET) constraint based on the new start date. If
    you select a finish date for a task, Microsoft
    Project automatically assigns a Finish No Earlier
    Than (FNET) constraint.

8
Add a deadline to a task
  • When you set a deadline for a task, Microsoft
    Project displays an indicator if the task is
    scheduled to finish after the deadline.
  • Setting a deadline doesn't affect how tasks are
    scheduled. It's just a way to have Microsoft
    Project inform you that a task will finish past
    its deadline. You then have the option of
    adjusting the schedule to meet that deadline.
  • 1 On the View menu, click Gantt Chart.
  • 2 In the Task Name field, click the task that you
    want to set a deadline for.
  • 3 Click Task Information and then click the
    Advanced tab.
  • 4 Under Constrain task, type or select the
    deadline date in the Deadline box, and then click
    OK.
  • Tip   You can drag the deadline symbol on the
    Gantt Chart to change the deadline date.

9
Split a task into segments
  • You can split a task if work on the task is
    interrupted and then resumes later in the
    schedule. This is useful, for example, when you
    need to temporarily stop work on a task to work
    on another task. You can split a task as many
    times as necessary.
  • Note that splitting a task into parts is not the
    same as entering a recurring task, a task that
    occurs at regular intervals, such as a staff
    meeting.
  • 1 On the View menu, click Gantt Chart.
  • 2 Click Split Task .
  • 3 On the task's Gantt bar, click the date where
    you want the split to occur and drag the second
    part of the bar to the date that you want work to
    begin again.
  • Tip   You can remove the split by dragging a
    portion of a split task so that it touches
    another portion.

10
Adding Resources
11
Lesson How do you assign resources?
  • You should assign resources to tasks when you
    want to
  • Track the amount of work done by people and
    equipment assigned to tasks or monitor materials
    used.
  • Have more flexibility in scheduling tasks.
  • Monitor resources with too little or too much
    work assigned

12
Create a resource list
  • You can use the Resource Sheet in Microsoft
    Project to create a list of the people,
    equipment, and material resources that make up
    your team and carry out the project tasks.
  • Your resource list will consist of work
    resources or material resources. Work resources
    are people or equipment material resources are
    consumable materials or supplies, such as
    concrete, wood, or nails

13
How
  • 1 On the View menu, click Resource Sheet.
  • 2 On the View menu, point to Table, and then
    click Entry.
  • 3 In the Resource Name field, type a resource
    name.
  • 4 To designate resource groups, in the Group
    field for the resource name, type the name of the
    group.
  • 5 In the Type field, specify the resource type
  • For a work resource (people or equipment), set
    the resource type to Work.
  • For a material resource (consumed throughout the
    project) set the resource type to Material.
  • 6 For each work resource (people or equipment),
    type the number of resource units available for
    this resource in the Max. Units field, as a
    percentage. For example, type 300 to indicate
    three full-time units of a particular resource.
  • 7 For each material resource (supplies consumed
    throughout the project), in the Material Label
    field, type a measurement unit for the material
    resource, such as ton.

14
(No Transcript)
15
Notes
  • Resource groups can be used for sorting,
    filtering, or grouping tasks by resources
    belonging to a particular group. You can use
    groups to indicate the department a human
    resource belongs to or to specify accounting
    codes for billing purposes.
  • You cannot assign resource groups to tasks. If
    you want to specify consolidated resources, such
    as "Carpenters" or "Editors" or "Engineers,"
    enter that as the resource name, and then assign
    the consolidated resource name to tasks.
  • Tip   As you work in the Gantt Chart or other
    task views, you can enter additional resource
    names. To assign additional resources, click
    Assign Resources , and then type a resource name
    in the Name field. You can also click Address and
    select a resource from your e-mail address book

16
Change the work schedule for a resource
  • The working hours and days off defined in the
    project calendar are the default working hours
    and days off for each resource. When an
    individual resource works a different schedule
    entirely, or when you need to account for
    vacations or equipment downtime, you can modify
    an individual resource calendar.

17
How
  • 1 On the View menu, click Resource Sheet, and
    then select the resource whose schedule you want
    to change.
  • 2 On the Project menu, click Resource
    Information, and then click the Working Time tab.
  • 3 On the calendar, select the days you want to
    change. To change a day of the week for the
    entire calendar, click the abbreviation for the
    day at the top of the calendar.
  • 4 Click Use default, Nonworking time, or
    Nondefault working time. When you click Use
    default, the selected days return to the
    Microsoft Project Standard calendar default,
    which is Monday through Friday, 800 A.M. to
    1200 P.M., and 100 P.M. to 500 P.M.
  • 5 If you clicked Nondefault working time in step
    4, type the times that you want work to start in
    the From boxes and the times that you want work
    to end in the To boxes.6Click OK.

18
(No Transcript)
19
Tip  
  • If a group of resources has the same special
    working hours and days off, you can create a new
    base calendar for them. On the Tools menu, click
    Change Working Time. Click New, and type a name
    for the new base calendar. Click Create new base
    calendar to begin with a default calendar.
  • Or to base the new calendar on an existing
    calendar, click Make a copy of, and then click
    the calendar name of the existing calendar in the
    Calendar box. Click OK, and then modify the days
    and hours on the calendar. On the View menu,
    click Resource Sheet, and select the new base
    calendar in the Base Calendar field for each
    resource that you want to assign the calendar to.

20
(No Transcript)
21
Assign resources to tasks
  • When you assign a resource to a task, you create
    an assignment. You can assign any resource to any
    task and change assignments at any time.
  • You can assign more than one resource to a task
    and specify whether a resource works full-time or
    part-time on a task. If the work assigned to a
    resource exceeds the daily full-time allotment
    indicated in the resource's working times
    calendar, Microsoft Project displays the name of
    the overallocated resource in red in resource
    views.

22
How
  • 1 On the View menu, click Gantt Chart.
  • 2 In the Task Name field, click the task to which
    you want to assign a resource, and then click
    Assign Resources .
  • 3 In the Name field, click the resource you want
    to assign to the task.
  • 4 To assign a resource part-time, type or select
    a percentage less than 100 in the Units column to
    represent the percentage of working time you want
    the resource to spend on the task.
  • To assign several different resources, hold down
    CTRL and click the names of the resources.
  • To assign more than one of the same resource
    (such as two carpenters), type or select a
    percentage greater than 100 in the Units column.
    If necessary, type the name of a new resource in
    the Name column.
  • 5 Click Assign.
  • A check mark to the left of the Name column
    indicates that the resource is assigned to the
    selected task.
  • 6 Click Close.

23
(No Transcript)
24
Tip  
  • You can replace one resource with another. Select
    the task whose resource you want to replace. In
    the Assign Resources dialog box, select the
    assigned resource and click Replace. Select one
    or more resources to assign, and then click OK.

25
Enter Cost
26
Lesson How do you enter costs?
  • Whether you need to account for each task's
    expenses or the overall cost of the project,
    entering rates for a resource's work on tasks or
    for fixed task costs enables you to see whether
    you are staying within budget.
  • You can choose when to accrue costs, enter
    per-use and overtime rates for resources, and
    plan for raises.
  • When you've completed this lesson, you will have
    entered cost information for resources and tasks.
    If you don't need to keep track of costs in your
    project, click View the schedule at the left to
    go on to the next lesson.
  • This lesson has five procedures. Use the
    navigation bar at the top of the screen to move
    through the lesson

27
Assign costs to resources
  • Microsoft Project allows you to assign rates to
    human and material resources so you can manage
    project costs accurately. You can assign standard
    rates, overtime rates, or per-use rates to
    resources.

28
How
  • 1 On the View menu, click Resource Sheet.
  • 2 On the View menu, point to Table, and then
    click Entry.
  • 3 In the Resource Name field, select a resource
    or type a new resource name.
  • 4 In the Type field, click Work if the resource
    is a worker or machine, or Material if the
    resource is material or supplies (such as
    cement).
  • 5 For a work resource, in the Std. Rate, Ovt.
    Rate, or Cost/Use fields, type the resource
    rates. For a material resource, in the Material
    Label field, type a measurement unit for the
    material resource (such as ton), and in the Std.
    Rate or Cost/Use fields, type a rate.
  • 6 Press ENTER.

29
(No Transcript)
30
Tip  
  • You can set the default standard and overtime
    rates for any new resources you enter. On the
    Tools menu, click Options, and then click the
    General tab. In the Default standard rate and
    Default overtime rate boxes, type the new rates.
    If you want to set this default for all future
    projects, click Set as Default.
  • Note   If the rate for a resource will change
    over the course of the project or if the resource
    will be paid at different rates for different
    assignments, or if you work with different grades
    of material, click Resource Sheet on the View
    menu. In the Resource Name field, select a
    resource and then click Resource Information .
    Then, enter the information on the Costs tab

31
Set fixed task costs
  • When you know an exact cost associated with a
    task, such as equipment costs, you can enter a
    fixed cost.
  • 1 On the View menu, click Gantt Chart.
  • 2 On the View menu, point to Table, and then
    click Cost.
  • 3 In the Fixed Cost field for the task, type the
    cost.
  • 4 Press ENTER.
  • Tip   In the Cost table, you can also change when
    the fixed cost is accrued by selecting an accrual
    method in the Fixed Cost Accrual field.

32
Define when costs accrue
  • In Microsoft Project, resource costs are prorated
    by default. Their accrual is distributed over its
    duration. You can, however, change the accrual
    method so that resource costs take effect at the
    start or end of the task instead.
  • 1 On the View menu, click Resource Sheet.
  • 2 On the View menu, point to Table, and then
    click Entry.
  • 3 In the Accrue At field, click the accrual
    method you want to use.
  • Notes
  • When you enter timephased rate changes for a
    resource and use the prorated cost accrual
    method, your costs will be calculated using the
    rates for the appropriate time periods and may
    change during the completion of the task.
  • You cannot prorate per-use resource costs or
    accrue them at the end of a task assignment. They
    always accrue at the start of the assignment.

33
(No Transcript)
34
See the cost of tasks or resources
  • After you assign rates to resources or fixed
    costs to tasks, you may want to review the total
    cost of these assignments to make sure they fall
    within your expectations. If the total cost of a
    task or resource does not meet your budget, you
    may need to examine each individual task's costs
    and each resource's task assignments to see where
    costs can be reduced.
  • 1 To see task costs, on the View menu, click More
    Views, and then click Task Sheet. To see resource
    costs, on the View menu, click Resource Sheet.
  • 2 On the View menu, point to Table, and then
    click Cost.

35
Tips
  • You can also view how costs are distributed over
    a task's duration in the Task Usage view by
    displaying its cost details. On the View menu,
    click Task Usage. On the Format menu, point to
    Details, and then click Cost.
  • You can view resource costs in more detail by
    clicking Resource Usage on the View menu,
    pointing to Details on the Format menu, and then
    clicking Cost. You can also see resource cost
    totals displayed graphically by clicking Resource
    Graph on the View menu, pointing to Details on
    the Format menu, and then clicking Cost or
    Cumulative Cost.

36
See the cost of the entire project
  • You can view your project's current, baseline,
    actual, and remaining costs to see whether you're
    staying within your overall budget. These costs
    are updated each time Microsoft Project
    recalculates your project.
  • 1 On the Project menu, click Project Information.
  • 2 Click Statistics.
  • 3 Under Cost in the Current row, view the total
    planned cost of the project.
  • Tips
  • After you set a baseline and begin to track
    actual costs, you can compare the Baseline and
    Actual fields to see if total project costs are
    progressing as expected.
  • As actual work progresses, you can also compare
    the variance between the Current and Remaining
    fields to see if you will have enough money to
    complete the project.
Write a Comment
User Comments (0)
About PowerShow.com