Title: Project Management Certificate Program Defining Project Schedule
1Project Management Certificate ProgramDefining
Project Schedule
2Resource Breakdown Structure
Time Management Resource Estimating
- A catalogue of the resources available for
assignment to project activities - Used to link Work Packages in the Work Breakdown
Structure to organizational components performing
project work - Shows
- Where resources are located
- How much might be available
3Example - RBS
Time Management Resource Estimating
4Scheduling Terms
Time Management Resource Estimating
- Duration
- The number of work periods scheduled for task
performance (days, weeks, etc) - Effort
- The amount of work required for task completion
- E.g. staff-hours, person-days, etc
- Resource Intensity
- Effort divided by Duration
- Example four workers at a time to complete the
scheduled task - Rate Quantity per unit time (dollars/hour)
Note Effort rarely equals Duration
5Activity Duration Estimating
Time Management Duration Estimating
- Estimating the number of work periods needed to
complete all activities. - Factors
- Resource requirements
- Resource capabilities
- Resource availability
- Methods
- Analogous estimates
- Parametric estimates
- Three point estimates (PERT)
6Basis for Duration Estimates
Time Management Duration Estimating
- Duration includes the actual amount of time
worked on a task elapsed time - Effort in the number of work hours required to
complete a task - Consider the following
- resource capability, availability cost
- elapsed time
- alternatives
Note Effort rarely equals Duration
7PERT
Time Management Duration Estimating
- Program Evaluation Review Technique (PERT)
- Similar to Critical Path Method (CPM)
- Based on precedence network
- Used to account for uncertainty in activity
duration estimates
O 4M P 6
Expected Activity Duration (D)
8Resource Leveling
Time Management The Schedule
- Reducing workload to normal levels.
- Approaches
- Modify the schedule by manually redefining,
moving, or otherwise changing task definitions,
durations, and/or relationships. - Use resource leveling capabilities in software
packages.
9Project Schedule
Time Management The Schedule
10Resource Loading
Time Management The Schedule
11Project Workload
Time Management The Schedule
12Resource Leveling
Time Management The Schedule
13Resource Leveling
Time Management The Schedule
14Resource Leveling
Time Management The Schedule
15Schedule Compression
Time Management The Schedule
- Resource leveling usually results in schedule
extension. - Schedule compression can be used both to level
workload and to compress schedule - Techniques
- Fast Tracking
- Crashing
- Reduce Project Scope
16Fast Tracking
Time Management The Schedule
- Revise the precedence network to convert
sequential tasks into parallel tasks. - Change precedence relationships to overlap task
execution.
17Crashing
Time Management The Schedule
- Three approaches to reducing project schedule
duration - Reduce project scope by eliminating tasks or
reducing task durations. - Work overtime and accept additional costs.
- Allocate additional resources in a way that
minimizes additional costs.
18Project Management Certificate ProgramDefining
Project ScheduleCritical Path
19Critical Path
Project Schedule Critical Path
- The sequence of schedule activities that
determines the duration of the project - In other words .
- the longest path through the activity network
- the path with zero slack (float)
- earliest completion date for a project
- monitor it closely take corrective action
Note Critical Path can change over time
20Key Terms
Project Schedule Critical Path
- Forward Pass defines the earliest date each
activity can start and finish, thereby
determining project duration - Backward Pass defines the latest date each
activity can start and finish without delaying
project completion
21More Terms
Project Schedule Critical Path
- Total Slack (Float) amount of time an activity
can be delayed without delaying project
completion - Free Slack (Float) amount of time an activity
may be delayed without delaying the completion of
another activity
Note Float Slack
22Precedence Diagramming Method (PDM)
Project Schedule Critical Path
Forward Pass - Add Start End dates Duration
Activity on Node diagram (AON)
23Precedence Diagramming Method (PDM)
Project Schedule Critical Path
Determine Earliest Finish Date
12/27
24Precedence Diagramming Method (PDM)
Project Schedule Critical Path
Backward Pass ? Late Start Finish Dates
12/27
Next Step Calculate Slack (Float)
25Precedence Diagramming Method (PDM)
Project Schedule Critical Path
Calculate Slack (Float) Difference between Early
Late Start Dates
12/27
Critical Path Zero (0) Slack
26Critical Path Zero Slack/Float
Project Schedule Critical Path
12/01 7 12/07
12/26 2 12/27
12/12 12 12/23
12/08 4 12/11
Task A
Task B
Task C
Task D
12/01 0 12/07
12/10 2 12/13
12/14 2 12/25
12/26 0 12/27
12/27
12/08 12 12/19
12/20 6 12/25
Task I
Task J
Start
Finish
12/20 0 12/26
12/08 0 12/19
12/01 10 12/10
12/11 4 12/14
12/20 3 12/22
12/15 5 12/19
Task E
Task F
Task G
Task H
12/25 5 12/27
12/20 5 12/24
12/16 5 12/19
12/06 5 12/15
ES DUR EF
Task
LS FLT LF