LAr ROD Status. Arno Straessner. and Alain, Daniel, Annie, Manuel, Imma, Laurent, ... From time to time there is a problem with one HOLASlink fiber connection ... – PowerPoint PPT presentation

Number of Views:23
Avg rating:3.0/5.0
Slides: 7
Provided by: arn51
Category:
Tags: rod | hola | lar | status

less

Transcript and Presenter's Notes

Title: LAr ROD Status


1
LAr ROD Status
  • Arno Straessner
  • and Alain, Daniel, Annie, Manuel, Imma, Laurent,
  • Eric, Jean-Pierre, Gilbert, ...
  • ATLAS Geneva
  • DPNC
  • April 1st, 2005

2
Test Bench in Geneva
  • All hardware parts are ready
  • From time to time there is a problem with one
    HOLA?Slink fiber connection
  • All tests are included in software package
  • Static tests (connection lines)
  • Datapath tests on the board (internal)
  • Datapath tests with injector and Slink (external)
  • Interrupt tests (VME)
  • Database interface ready

3
Production Status
  • First 3 boards tested successfully
  • Final PUs mounted
  • All functional tests passed
  • Another batch of 12 boards arrived
  • Should have been 17 but there were problems
    detected during the JTAG/boundary scan
  • All 12 boards equipped with cooling plates and
    protection foils
  • Test results of 6 boards (6 were sent to LAPP)
  • 1 board ok
  • Various problems on the other 5 boards, mainly on
    data and communication lines
  • Optical receivers are all ok
  • Debugging ongoing

4
Cooling system
  • Cooling system in USA15
  • Mechanical work finished
  • Electrical part will be done until May 15, as
    planned
  • In the first period of installation it will work
    with a local steering system
  • Cooling drawers
  • Final mechanical design changes done (arrangement
    of pipes)
  • Started to order the material
  • Need to hurry a bit to set up the test crate at
    EMF

5
Installation and Commissioning
  • First real crate test with 14 RODs foreseen for
    mid April
  • Important to show that the full system works
  • Started installation one final crate transported
    to EMF test area
  • Installation of crate next week water cooling
    system needs to be modified again
  • Installation in USA15 starts when crates are
    delivered
  • Hopefully in May Contract date 8 weeks time
    for load-tests
  • Infrastructure will be supplied by CERN
  • Rack rails, power cables in rack, side panels
  • Lifting device for crates
  • All crates power supplies will be installed at
    once
  • Electronic equipment will be received, registered
    and tested at EMF before installation in USA15
  • Target date 4 crates fully functional by August

6
Summary
  • Need to identify problems with pre-series ROD
    boards and repair the boards
  • A 16 yield is not acceptable find ways to
    improve production
  • Crate delivery date in May, as foreseen at the
    beginning
  • Cooling station is advancing
  • Cooling drawers need to be built now