D0 Trigger Status - PowerPoint PPT Presentation

1 / 25
About This Presentation
Title:

D0 Trigger Status

Description:

One day of beam for timing. Completion dates for various subsystems ... Expect luminosity will be logged and made available on ACCNET within 1 week of first beam ... – PowerPoint PPT presentation

Number of Views:27
Avg rating:3.0/5.0
Slides: 26
Provided by: GeraldC1
Category:
Tags: day | finder | of | status | the | trigger | week

less

Transcript and Presenter's Notes

Title: D0 Trigger Status


1
D0 Trigger Status
7 MHz input rate
Data
Framework
Data Log
L2 100ms
L1 4.2 ms
L3 48 ms
50 Hz
5-10 kHz
1000 Hz
48 nodes
256 terms 128 bits
128 bits
  • Status reports
  • March and Beyond

2
Detector/L1/L2 Components
L1 LUM
LUM
L2Cal
CAL
L1 FPS
L2PS
FPS
Global L2
CFT/ CPS
L1 CTP
L2CFT
L2STT
SMT
L2 Muon
L1 Muon
Muon
L2FWCombined objects (e, m, j)
L1FPD
FPD
L1FW towers, tracks, correlations
3
Luminosity Monitor March 1
  • Electronics
  • TDC preprod boards expected this week
  • 9 production boards arrive in March
  • Vertex FPGA design nearly complete
  • 2 Vertex boards finished in April
  • Installation
  • Detector mounted for 10 months.
  • Cables Installation started, 1-2 wks.
  • One day of beam for timing.
  • Completion dates for various subsystems
  • Expect minbias triggers to be available at first
    beam, with Run I electronics.
  • Expect luminosity will be logged and made
    available on ACCNET within 1 week of first beam
  • Expect all electronics to be in place by the end
    of April
  • Expect multiple interaction triggers, luminosity
    database to be completed by the end of the year

March L1 Luminosity Minbias
4
L1 CTP/FPS/FPD Analog Status
  • AFE 8MCM (CFTax),(Fermilab-D0)
  • Have ten prototypes.
  • On bench, expect 2 weeks for LHB/RHB noise tests
    (lt7 fC roughly 1 P.E.)
  • Four weeks to build, eights weeks to stuff. RHB
    mid/late-April. LHB mid-May. Need at least two
    weeks to check.
  • Earliest installation early May.
  • Order enough for entire central tracker.
  • AFE 12MCM (FPS)
  • Motherboard layout nearly done.
  • Daughterboard prototype has been simplified to
    reduce power consumption, heat load, and
    real-estate.
  • Corresponding reduction of capability L3 readout
    of discriminated bits.
  • Prototype some time in April.
  • In April decide between modified AFE8 or AFE12

5
L1 CTP/FPS/FPD Digital Status
  • Mixer(Fermilab-CD)
  • A half super-sector expected this month. Bare
    boards this week (2 of 20 boards.)
  • Place order in March
  • Full Mixer April-May
  • Crate/PS on hand
  • DFEA/DFES/Broadcasters/ Collecters(Fermi-D0)
  • All 120 Motherboards here.
  • All 125 Transition modules here.
  • 35 of 88 DFEA single-wide daughter boards here.
    Complete boards this wk.
  • Double wide daughter boards here, parts mostly
    here.
  • Crates 4/4 DFE, 1of2 CTT, 2/2 PS

6
Firmware Status
  • AFE Complete
  • Digital Design 90 / Code70 / Implementation
    60 / 7 out of 14 units tested in hardware
  • Simulated/implemented entire DFEFFPSSFPTT
    Chain.
  • DFEACTOCCTTT next few weeks
  • Expect CFT occupancy and track trigger April 2.

7
L1 CTP/FPS/FPD in March
  • Analog
  • 5-10 AFE8 prototypes.
  • Populate outer layers of upward pointing sector.
    Need to coordinate overlap with minimal L1 Muon
    configuration
  • Balance installed May-June
  • Digital
  • One-half sector mixer available
  • Some broadcaster/collector complement available.
  • Useful commissioning exercise.
  • Hit, track trigger.

March 1 Some capability, mostly
Installation/commissioning
8
L1 CAL Component Status
  • 10000 first stage adders(SUSB)
  • One for each electromagnetic and hadronic tower
  • Printed circuit boards complement mid-February
  • Require surface mounted resistors. Values
    recently determined imminently. Delivery late
    March.
  • Will concentrate on CC
  • 2500 Drivers(SUSB)
  • 4 calorimeter, 1 trigger tower per driver
  • Hybrid prototypes, 2 week turnaround, balance,
    six weeks.
  • Also need resistor values
  • Sufficient prototypes for 8-10 trigger towers
  • 320 analog pick-offs(MSU)
  • Now prototyped. Days.
  • Goal 0.8 lt h lt 0.8 by March 15th
  • Operating Status
  • Powered
  • New Control Software running.
  • Peparing to replace analog pickoffs.

9
L1 Cal in March
  • Tower Availability
  • March 1st a few (lt10) towers
  • March 15th-20th CC
  • Depends on availability of adders/drivers/access
  • Towers over threshold
  • Global terms
  • March 30th Start EC
  • Detector/Trigger Commissioning.
  • Beam data to time in calorimeter towers.
    Starting w/ scopes.
  • Calibrate L1 calorimeter trigger
  • Turn to EC

March L1 Calorimeter Commission w/ handful of
towers Increasing capability through month
10
L1 MUON Component Status
  • Crate Manager(10)
  • 4/10 production available reading out
  • Still verifying functions
  • Motherboard(62)
  • Production versions arriving 18/62, remainder
    ordered.
  • Testing in progress, worked out of box!
  • Preproduction as backup.
  • Trigger Manager Flavor Board(8)
  • 8/8 production due soon (lt2weeks).
  • Should know soon if ready for March, very similar
    to preproduction
  • Preproduction as backup
  • Scintillator Flavor Board(28)
  • Submitted for production last week
  • Delivery 4 weeks for stuffed boards.
  • Preproduction as backup

11
L1 MUON Component Status
  • PDT Flavor Boards(28)
  • 5/28 due soon (lt2weeks)
  • Preproduction as backup
  • Infrastructure Software
  • Cables/PS in progress
  • Still need ORC.
  • Download in place
  • Preproduction versions of all firmware.
  • No alarms, monitoring
  • MCEN crate manager
  • Preprod testing in progress
  • Begin fabrication early April
  • MCEN Centroid finder
  • Production layout in progress
  • Begin fabrication early March
  • MCEN Physics Boards
  • Production starting (lt2weeks)

12
L1 Muon Outlook
  • March 30
  • Central trigger crate with several wire and
    scintillator octants (prod)
  • End trigger crates each with one scintillator
    octant (prod)
  • One MCEN crate readout with a few MCENs
    (preprod)
  • April 30
  • Trigger crates fully populated, cards in hand,
    depends on testing
  • July 1
  • MCEN crates fully populated, in hand, depends on
    testing.

March L1 Muon A few central octants to
start Increasing capability through month
13
L2 Component Status
  • a-processors (MSU,UIC,UVa) (15 minimum)
  • Production Status
  • Preproduction 2 worked out-of-the-box.
  • First production failed 0/25 boards
  • Diagnostics _at_ CD,UIC
  • Since November Extensive repair program at CD,
    UIC
  • Problems with broken chips, vias, non-standard
    design practices.
  • Three boards work! Two more with minor problems,
    Six more promising
  • Future
  • Continuing Effort. Expect 6-11 cards by March
    1st.
  • Examining layout, use remaining parts to make 12
    new boards. In progress. May-June?
  • Complete redesign based on off-the-shelf
    hardware, prototype summer (L2BETA)

14
L2 Components Cont.
  • MBT I/O Cards(U-Maryland) (30)
  • All production cards received.
  • To be checked by the end of March
  • Firmware functionality 90 done, complete
    mid-March
  • FIC L1/L2 Interface(SACLAY, UIC) (12)
  • Boards complete
  • Some transmission errors noted.
  • Modified a single card at Saclay, testing this
    week.
  • SLIC Parallel Proc.(NIU,Columbia)(25)
  • Boards complete
  • DSP Central algorithm meet speed/efficiency
    requirements. Significant work on DSP forward.
  • Full development of software another 2 months.
  • CIC, SFO Muon/L2 Interface (U-Neb)
  • 2 CIC preprod 1 passes, 1 has errors
  • SFO preprod passes most tests
  • Looking for production delivery end of April

15
L2 Status Continued
  • Operating Software
  • C Framework exists
  • Various Drivers in place by mid-March to April
  • Processor algorithms,fairly well developed
  • Global in simulation January
  • Cal in simulator January
  • Muon March
  • Infrastructure
  • MCH and test stand racks and crates 95 done.
  • Cabling 65, long runs complete, will start final
    dressing soon.
  • Complete in March

16
L2 Prospects
  • Feb/March
  • 6-11 Alphas Test Stand (2), Global (2), Muon or
    Cal (2)
  • Attempt to complete Muon Integration
    (CIC/SLIC/SFO/ MBT/ALPHA)
  • Begin Cal Integration (FIC/MBT/ALPHA)
  • April/May
  • 6-23 Alphas Test Stand (2), Global (2), Muon
    (2-4) or Cal (2-4), CTT/PS (2-5)
  • Preprocessors to Global
  • L3/DAQ
  • Start PS/CTT

March L2 Depends on Repair Success, Commissioning
Muon/CAL.
17
DAQ/L3
  • Currently VRC, SB, ETG emulated w/ capability of
    500 kByte/second.

18
Implementation December, 2000
  • Four unique types of cards
  • Event Tag Generator (ETG) (1)
  • Event Tag Generator Int. (ETGI) (4)
  • VBD Interface (VBDI) (8)
  • Serial Interface Board (SIB) (256)
  • SIB appeared in almost all components
  • VRC VBDI SIB
  • SB ETGI 12 SIB
  • Node Motherboard 4 SIB
  • SIB design nearly complete but could not be
    routed according to design rules. Too ambitious
    for form factor.

19
Implementation January 2001
  • Response
  • Simplify designs by building cards with
    functionality limited to specific site.
  • Short term
  • Build a SIB1 or SIBling with functionality only
    required for VRC (to be used later in ETG)
  • Supplement this with increased ethernet
    capabilities. 100Hz
  • Long term
  • Stage upgrade by building SIB2 and SIB3 which are
    more specifically targeted to SB, L3Nodes, ETG
    and final VRC.
  • Current Status
  • SIB1
  • At vendor, 20 bare boards to be shipped between
    Thursday and Tuesday
  • Assembled, at Brown 2/22
  • VBDi
  • At vendor today or tomorrow.
  • Assembled, at Brown 2/22
  • Designs of other cards well along, can be derived
    from work with original SIB

20
L3/DAQ Schedule
  • Stage1 3/22
  • 50 Hz
  • VBDi/SIB at D0
  • Ethernet upgrade
  • gt100 Hz
  • Still discussing implementation
  • Stage 2 6/14
  • 200 Hz
  • Additional VRC,SB Hardware
  • Stage 3 7/19
  • 1 kHz
  • Final Hardware
  • L3 Review Committee (Schamberger, Fuess, Blazey)
    reviewing design, schedule weekly

March L3 50 Hz Improving Capability
21
Filtering
  • Extensive Operating Experience
  • July Participated in SiDet 10 tests.
  • Sept unpacking calorimeter, muon
  • Nov Demonstrated streaming
  • January MarkPass, muon unpacking, TFW
  • Currently ported to NT
  • Filtering Control L3FMarkandPass, L3Prescale
  • Filter tools l3tCalunptool, l3fmuo_unpack
  • At First Beam
  • Calorimeter MarkandPass, Calunpack, Single Jet,
    Missing Et
  • Muon Scintillator Coincidence

March L3filtering Calorimeter unpacking Muon
scintillator coincidence
22
Database
  • Trigger Database design nearly complete, includes
    all three levels.
  • Contains triggers lists for online running,
    trigger simulation, early running.
  • Production release soon. Hope to go on-line
    within a month or two.
  • Starting to work on user interfaces.

23
Trigsim
  • Production Release p06.00.01 now available
  • All L3 levels in ROOT format
  • Raw Data and Cal Trigger Tower Chunks
  • Default output
  • MC information
  • L1 Cal towers
  • L1FT, PS
  • L1 FWK
  • L2 Cal jet, mEt, electrons
  • L2 global jets, electrons
  • L3 Cal mEt, jets, kt jets, electrons, cft, global
    tracking, smt, tau
  • Use d0sim p07.00.01
  • P08 Release
  • Will have a L1/L2 Trigger Menu
  • L1muon, L1ft, L2Global improvements

24
March Expectations
  • Level 1
  • Minbias trigger
  • Commissioning Track/Preshower Trigger
  • Handful Calorimeter Trigger Towers
  • A few Muon Octants
  • Level 2
  • Not in trigger
  • Depends on Alpha Repair
  • Integrating Muon first
  • Level 3
  • Optimistically 50 Hz
  • Cal/Muon filtering

March Enough to get started Rapidly Changing
25
Long Term Expectations
  • Luminosity April
  • L1 Tracker (Central) gtMay
  • L1 Tracker (Forward) gtJune
  • L1 Calorimeter May
  • L1 Muon May
  • L2 Global/Cal/Muon June
  • L3 1kHz July
  • Some final comments
  • Lots of progress
  • People are working very hard.
  • Still along way to go
  • Preoccupation with hardware has lead to a great
    need for help with on-line programming.
Write a Comment
User Comments (0)
About PowerShow.com