Title: VITAMIB sarl
1VITAMIB sarl
29, Bd des Alpes MEYLAN France Tel 33 476 618
881 Fax 33 476 614 427 Email
vitamib_at_vitamib.com
- Serving thousands of users over Europe
2Pr. Gérard BRUGAL
Université Joseph Fourier, Grenoble Consultant
VITAMIB Sarl, Grenoble
gbrugal_at_vitamib.com
3I Project vs Programme ?
All projects have common features independent
from the nature of the innovation they are meant
to achieve, i.e all the contrary of a programme
4Know the basics
- A PROJECT is a component of the social and
economic system - A PROJECT is driven by standard rules known as
MANAGEMENT - A PROJECT is basically different from a research
PROGRAMME
5European integration
ERA 2002
Needs
European Parliament 1962
Pool Charbon Acier 1950
CEE PAC Rome treaty 1957
FP
FP
FP1 to 6 1985
wishes
Obstacles
6Project features
Milestones
Product
Vision
Objective
Activities
Actors
Costs
Scope
7Project process
- Risk analysis
- Milestones
- Workpackages - Tasks
- Required resources
8Integrated Project
RTD1
RTD2
RTD3
Products nearing the market
9Programme features
Publications
Questions
Question
Knowledge
Daily work
Researchers Tech. staff
As many resources as possible
Costs
Excellence
Grant as a of GIP
10Programme process
- Available resources
- Experiments
- Publications
- Risks of interpretation
11Network of excellence
External experts
U
U
U
JPA
U
U
U
U
U
A new organisation for research
U
12II Project Road Map
Whatever its scope, any project goes through
an inevitable cascade of processes along time
13Project road map
14III Initiation
Turning a vision into project objectives, risks
analysis, team, workplan and budget, products
15Standard process
16Objectives 5 criteria
- Understandable by all
- Attainable
- Measurable
- Endorsable by the key actors
- Valuable for the funding parties
Any project is firstly assessed on the
objectives
17IV Risks Analysis
Risks analysis provides the rationale for
designing a workplan
18Risk analysis
The signature of management quality
19Converge asap
- Write as soon as possible
- Continuous update
- Maintain for project duration
- Be realistic
- Derive the milestones
Risk Management Worksheet
Description Evolution
Type of Risk
Jeopardy
Contingency plan
Severity
Milestone
20Workplan components
M1
M2
M3
M4
WP2
WP3
WP5
D
D
D
WP4
WP6
D
D
WP7
WP8
D
D
WP1 Project Management
D
D
D
D
D
21Workplan rationale
- PHASES periods of a project leading to
independant and specific objectives - MILESTONES ordered sequence of significant steps
that progressively decrease the internal risks - WORKPACKAGES consistent sets of tasks required
to reach a milestone - DELIVERABLES the results of a workpackage
22Down to tasks level
- TASKS are the only
- pieces of work that a
- specialist can weight
- with respect to
- Work to be done
- Time duration
- Efforts and skill
Workpackage
1 m
2 m
1.5 m
T2
T4
280 ph
2 m
T3
62 ph
130 ph
400 ph
Ex needs specification implementation -
evaluation
23V Project Team
An adequate team is a unique combination of
complementary skills to guarantee the promised
achievements
24Partners responsibilities
Coordinator
Manager
Coordination
Workpackages
Contractors
Associates
Tasks
Third party assistance
Sub-Contractors
25Cost Share model
FC
50 maximum of total costs reimbursed by CEC
(Less for demonstration and exploitation)
FCF
100 maximum of marginal costs reimbursed by CEC
ACF
n maximum reimbursed by CEC but varies for cost
categories
NA
26Sequence of signatures
2
4
CR
MOU
Contrat
AC
CR
Consortium Agreement
SC
Sub- Contract
AC
1
3
27Indicators and thresholds
Detect the alert signals
28PERT diagram
Performance Evaluation and Review Technique
Project months
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
Partner
WP1
T1
P1
840
12
P2
T4
908
21
WP2
T3
P3
98
6
T2
P1
717
10
T 5
820
135
P2
T6
80
9
WP3
P4
T7
995
Cost (K
73
Effort (ph)
M2
M1
4458 h
266 K
D1
D3
D2
60/h 8 K/m
29Value for money
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
Months
Workload
Results
D
D
D
Internal Risks
External Risks
M1
M2
Expenses
30VI Project Management
Project management is the art and technique of
combining systems, technologies and people to
successfully complete a project with regards to
objective, time scale, budget, quality and
results
31Art of management
Workplan
Objective
People
Anticipation Compromise
Cost
Funding parties
32Management techniques
One single proven Software
Adapted to the needs
Adopted by the Team members
Integrating activities and budget
Web enabled
PMI compliant
33VII Proof reading
Last but not least !
Thank you for your attention and good luck !