Title: School District of Osceola County Facilities, Planning, Maintenance
1School District of Osceola CountyFacilities,
Planning, Maintenance Construction
- Monthly Update June 2007
- Construction Workshop
- 26 June 2007
2Report Contents
- Planning Services Division Update
- Property Acquisition Summary
- General Issues Update
- Permitting Services Division Update
- Activity Report Permits, Inspections, C.O.s
- General Administrative Issues
- Design and Construction Services Division Update
- 2006-2007 Goals
- Capital Outlay Planned Projects Update
- Major Projects Highlight Reports
- Projects in Design Bidding
- Tax Savings Summary New Schools
- General Issues Update
- Maintenance
- Introduction
3Planning Services Property Acquisitions
- Elementary I (Anthem Park)
- Property acquisition has been closed. School is
scheduled to open in August 07. - Annexation into City of St. Cloud pending.
- Elementary J (Harmony)
- Closing for site acquisition is completed.
- Comprehensive Development Plan Application has
been submitted to Osceola County for Approval. - 3. Elementary K (Flora Ridge)
- Ownership of school site to be transferred from
EFBD to SDOC after construction of school. - Elementary L (Poinciana)
- Contract with Avatar Properties for acquisition
of the school site pending. - Staff working to determine scope and budget for
adjacent intersection improvements required by
Osceola County. - Comprehensive Development Plan Application has
been submitted to Osceola County for Approval. - Middle CC (Westside DRI)
- Developer will convey the property to the SDOC
through their EFBD in July 2007. Assessments
will be used to fund the site acquisition at no
cost to SDOC. - Site Due Diligence Underway
4Permitting Activity Report
- Activity Report
- May - June 2007 YTD
- Inspections Performed 30
396 - Inspection Hours 36
405 - Certificates of Occupancy 0
99 - Certificates of Completion
3 102 - Permits Issued 13 100
5Permitting Services Update
- General Issues
- All 761 existing portable inspections have been
completed. No major deficiencies have been noted
that would prevent usage. - Public Shelter Inspections (EHPAs) have been
completed. All eleven (11) designated shelter
school sites have satisfactorily passed
inspection. - L.P. tank inspections are complete. 34 code
violations are being resolved by the Maintenance
Department and our supplier Amerigas. All
corrections performed by Amerigas are at no
expense to SDOC. - Administrative Issues
- All portable additions have permits. Of the 100
new additions for the opening semester, 80 are
currently in place and inspections are currently
being performed.
6Design Construction Services Goals
- Completion/Start of all Capital Outlay Planned
Projects within the fiscal year. - Completion/Start of 90 of 06-07 projects by
July Workshop. - Construction complete and open new schools for
August 07. - Substantially Complete HS EEE July 07.
- Substantially Complete ES I July 07.
- 3. Design and start construction for new schools
opening in 08. - Start construction on ES J by July 07.
- Start construction on ES L by July 07, pending
site acquisition and approvals. - Substantially Complete ES K October 07.
- Start construction on Sports Authority Conversion
in 3rd Quarter, pending resolution on re-zoning
with City of Kissimmee. - 4. Implement Management Initiatives.
- Publish a Process Procedures Manual 50 1st
draft copy for January 07. - Development implementation of programs to
assist in department operations and project
administration.
7Capital Outlay Program Status 06-07
- The data provided reflects Capital Outlay amounts
based on Board approved budgets for planned
projects for renovation, remodeling, and other
cyclical renewal projects only. - 97 of the Planned Project Capital Program is
either completed or started. The Not Started
Projects are planned Summer Projects.
8Project Highlight Sunrise Elementary
9Project Highlight Elementary K
10Project Highlight Elementary K
11Project Highlight Elementary I
12Project Highlight Elementary I
13Project Highlight High School EEE
14Project Highlight High School EEE
15Project Highlight High School EEE
16Design Construction Request for Services
- 1. RFQs under development to Purchasing
June/July 2007 . - Geotechnical Materials Testing for OCSA and
Middle School CC - HVAC Test Balance for OCSA and Middle School
CC - CM _at_ Risk for HVAC Renovations at the Osceola
County School for the Arts - CM _at_ Risk for Middle School CC
- CM _at_ Risk for Schools Master Plan
- 2. Advertised RFQs June 2007.
- Continuing Services for Real Estate Appraisals
- Continuing Services for Survey and Mapping
- 3. In Review/Selection Process
- Continuing Services CM at Risk for
Miscellaneous Minor Projects - A/E Services for HVAC Renovations at the Osceola
County School for the Arts - Continuing Services for Civil Engineering
- Continuing Services for Permit/Plan Review and
Building Code Inspections
17Design Construction Owner Direct Purchase
Program
- Tax Savings Summary New Schools
18Wrap Up