Title: LHC Beam Instrumentation Readiness
1LHC Beam Instrumentation Readiness
- Overall State (Organization - Production
Installation HWC SW) - Details per Observables (Position Losses
Intensity Transverse Profiles Q Q
Luminosity) - Conclusions
2The new Baseline
3Overall State Organisation Phase I List
- The Phase I LHC Beam Instrumentation consists of
- Beam Position 1000 BPM (15 types)
- Beam Losses 4000 BLM (IC and SEM)
- Beam Intensity 4 BCTDC, 4 BCTFR (fast ring), 4
BCTFD (fast dump), 2 BSRA (abort gap), 1000 BPM - Beam Transverse Profile 2 BSRT (sync rad
telesc.), 2 BWS (wire scanners), 4 BGI
(Ionisation gas monitors) - Tune and Chromaticity 14 BPL, 4 BQK (tune
kickers), 4 BQS (Schottky) - Luminosity 8 BRA (2 types)
4Overall State Organisation BI Responsible
5Overall State Organisation Commissioners
6...
7Overall State Monitor Production/Installation
- Sofar, we managed to produce and install our
monitors on time with respect to the general
machine schedule. Look this for today details. - It should also be the case for the remaining.
- But the 2 BGIs (HV on Beam 2) installed in LSSR4
have been burned during bake out. We may be able
to rebuild one detector for the start-up. Please
select the plane!
8Overall State Monitor Installation and INB
- During installation, we identify via labels with
code bars - The functional slots
- The piece of equipments
- We update the layout database through the HWC
travelers - We will thus be Ok for INB issues
9Overall State HW Commissioning
- All our instrument HWC procedure have been
recorded and linked to the corresponding
travelers accessible from - The LHC layout entry page
- The LHC HWC links
10Overall State HW Commissioning
11Overall State HW Commissioning
12Overall State HW Commissioning
13Overall State HW Commissioning
14...
15Overall State SW specifications
- Based on the LHC BI functional specifications, we
are currently discussing/agreeing on the
corresponding operational software interfaces of
our front end server - We agree with
- the instrument commissioners
- the operational application developers
- The LHCCWG scenario builders
16Overall State SW specifications
- The following operational interfaces have been
agreed - Beam Position
- Beam Loss
- Beam Profiles (BWS, BSRT slow and fast, BGI)
- Work is in progress on Intensity and Q/Q
- The discussed interfaces are documented in
AB/BI/SW web pages
17Overall State SW specifications
18Overall State SW specifications
19Overall State SW Prototyping
- Based on these specifications, AB/BI/SW will
- deploy servers on BI LHC FECs emulating these
interfaces (requested for November by Mike) - We already have some BPM and BLM FEC running.
- Well have BWS and BSRT beginning of July.
- The rest will follow during the Summer.
- Transmit corresponding timing and logging
requirements to AB/CO
20...
21Overall State Commissioning with Beam
- Except for BLM followed by the MPWG, the
procedures for the beam instrument commissioning
with beam will be defined by BI for the different
instruments. - This work will start this Summer and could be
presented this Autumn.
22Details Per Instrument
...
23Details per Observable Position Status
- Monitors, electronics and front end software will
be ready for the start-up - Well basically have 5 types of acquisitions
- Threading For the first injections before RF
capture commissioning Asynchronous Ok for a
few turns. - And once beam is captured and our fine delays
tuned - Orbit latest orbit acquisition published at 1 Hz
(note orbit is acquired faster for RT) - Capture On request, acquires the beam position
for selected bunches over a selected number of
consecutive turns (see details on BI Web) - XPOC the position for the last turns prior to
every beam-dump event will be available for XPOC - Post Mortem Buffers will be sent on PM events via
the CO PM channel.
24Details per Observable Position Remaining Issues
- Front End SW
- Calibration settings handling (first day and
following maintenance tbd with AB/CO/DM) - Trigger sensitivity swapping necessary but slow
process (hundreds of ms) between pilot and
nominal intensity (LSA is informed). - Impact of capture data request on RT data
transmission (currently investigated with CO) - Development of the XPOC position interlock system
in point 6 (to be defined with Brennan)
25Details per Observable Position Remaining Issues
- HW
- HW commissioning (ongoing)
- Fine delays tuning (as soon as beam is captured).
- Operational Applications
- Full scale test (64 crates) for concentrators
(LSA and RT), logging - RT Feed-back BI-OP proposal start with a loop at
1Hz then try to increase speed to nominal 10 Hz
(or ultimate 25Hz) work in progress. - RT loop control
- Fixed displays definition and ad-hoc developments
(if necessary)
26...
27Details per Observable Losses Status
- Monitors, electronics and front end software will
be ready for the start-up - Well basically have 4 (1) acquisition modes
- Max Losses The highest loss observed at the
monitor since the last request (at 1Hz) over 12
different time periods (40uS, 80 uS, 320 uS, 640
uS, 2.54 mS, 10.24 mS, 81.92 mS, 655.36 mS, 1.31
S, 5.24 S, 20.97 S, 83.88 S) - Study Data triggered as and when required, the
granularity of this data will be per channel 1
data point every 40 microseconds covering the
last 1.3 secs. - XPOC Data Triggered every beam dump, will return
for each channel 1 data point every 40
microseconds covering the last 100ms before the
dump and the following 40ms. - Post Mortem Buffers will be sent on PM events via
the CO PM channel. - Collimation Data feed loss data into the
collimation control system to ensure that losses
dont exceed set limits during motion. This data
will be sent through a dedicated UDP layer and be
triggered by the collimation system.
28Details per Observable Losses Remaining Issues
- Front End SW
- Threshold handling (DB, Tools, procedures under
discussion) - Impact of MD data request on RT data transmission
(logging under investigation with CO) - HW
- Threshold evaluation (work in progress in BI)
- Commissioning with Beam (procedures, options
work in progress in MPWG) - Operational Applications
- Full scale tests
- Fixed displays definition and ad-hoc developments
(if necessary)
29...
30Details per Observable Trans. Prof. BWS Status
- Monitors, electronics and front end software will
be ready for the start-up - It will be possible to scan the to beams at the
same time but not the two planes on the same beam - 2 wires per plane per beam will be installed, 1
operational 1 hot spare.
31Details per Observable Trans. Prof. BWS
Remaining Issues
- Intensity Limitation
- Quench Limit on Beam Intensity (see details).
Current estimation is up to 1-6 1012 protons in
the circulating beam, ie. about 0.3-2 of the
nominal intensity at 7 TeV - Wire Damage Limit on Intensity difficult to
predict (new study in progress) but seems close
to the Quench limit. - BWS are calibration devices
- They should be used asap to cross-calibrate the
BSRT and BGI.
32Details per Observable Trans. Prof. Ionisation
Gaz Mon. Status
- Beam 1 monitors, electronics and front end
software will be ready for the start-up - Possibly one plan on Beam 2 (make your choice)
- Well basically have 1 continuous acquisition
mode Acquisition of one image per plane obtained
from the integration over 20ms of the rest gas
ionization signal. The measurement provides beam
profile, size and position at 1Hz. The signal
quality will depend on the external systems, i.e.
gas injection and B-field.
33Details per Observable Trans. Prof. Ionisation
Gaz Mon. Remaining Issues
- Front End SW
- Gas Injection Control (tbd with AT/VAC in
September) - B-field control and correction (under study
encouraging feed-back from Jorg) - Operational Applications
- Integration and commissioning of Gas injection
and B-Field control - Operational application to be started
34Details per Observable Trans. Prof. Synchroton
Light Status
- Monitors, electronics and front end software will
be ready for the start-up - Well basically have 3 acquisition modes
- Non Gated Full beam image (profile and sigmas)
integrated over 20 ms published at 1Hz - Gated
- Physics mode All bunches integrated over 1 turn
published as fast as possible (every minutes for
the 3564 buckets) - MD mode gated part of the beam (down to one
single bunch) over several (up to 3000)
consecutive turns
35Details per Observable Trans. Prof. Synchroton
Light Remaining Issues
- Front End SW
- Ethernet link towards the fast camera (in
progress) - Automatic gain setting implementation
commissioning - HW
- Commissioning with beam of the light sources
(Onduleur and D3) - Calibration Beam with different energy and
intensity conditions (as soon as possible!) - Reliability of the fast camera in tunnel
conditions
36...
37Details per Observable Intensity BCTDC Status
- Monitors, electronics and front end software will
be ready for the start-up - Well have 2 DC monitors per beam. One
operational, the second as spare (not hot) in
case of problems and specialist monitoring. - Well basically have 3 (1) acquisitions
- Injection beam current for each beam, before and
after an injection. Acquired and published every
injection. - Standart beam current for each beam acquired
and published continuously at 1 Hz. - Safe Beam Flag measured intensity will be
transmitted at 10Hz through a dedicated HW link
to the MP system. - Post Mortem Buffers will be sent on PM events via
the CO PM channel.
38Details per Observable Intensity. BCTDC
Remaining Issues
- HW
- Commissioning of the Intensity transmission HW
link - Cross-Calibration (Injection lines, fast ring
BCT) - No automatic arbitration between the 2 redundant
monitors for the start-up - Operational Applications
- Operational application to be started
39Details per Observable Intensity BCTF Status
- Monitors, electronics and front end software will
be ready for the start-up - Well have 2 fast monitors per beam in the ring
and 2 in the dump lines. One operational, the
second as spare (not hot) in case of problems
and specialist monitoring. - Well basically have 2 (1) acquisitions
- Capture provides intensities of selected
individual bunches (S) over N consecutive turns.
(S N lt 512K) The data-taking is started at
reception of a dedicated central timing. - Standart All individual bunch currents are
averaged over 227 turns (20ms). This measurement
is continuously repeated at 10Hz and published at
1Hz. Bunch and Beam lifetime will also be
computed and transmitted. - Post Mortem Buffers will be sent on PM events via
the CO PM channel.
40Details per Observable Intensity. BCTF
Remaining Issues
- HW
- Calibration with Beam
- No automatic arbitration between the 2 redundant
monitors for the start-up - Development and Commissioning of the dI/dt
monitoring to be done BI agreed on the
objective to have a prototype ready for Summer
2008. - Operational Applications
- Operational application to be started
- Fixed displays definition and ad-hoc developments
(if necessary)
41Details per Observable Intensity BSRA abort
gap Status
- Monitors, electronics and front end software will
be ready for the start-up - Well basically have 1 acquisition
- Standart The intensity values will be acquired
at 10 Hz. 30 intensity values will cover the
abort gap period. The DAB card will cumulate
these intensities over a pre-defined number of
turns (ex 1000). The acquisition result will
thus be an array of 30 average intensities, which
sum will represent the intensity in the gap - Post Mortem Buffers will be sent on PM events via
the CO PM channel.
42Details per Observable Intensity. BSRA abort
gap Remaining Issues
- HW
- Calibration with Beam
- This is just a monitoring. No action will be
triggered from the Front End computer itself. - Operational Application
- Operational application to be started
43Details per Observable Intensity via BPM Status
- Monitors, electronics and front end software will
be ready for the start-up - Well use the acquisition channel of beam 2 to
read intensity of beam 1 (and vice versa), i.e.
we lose beam position on the other beam
44Details per Observable Intensity. Via BPM
Remaining Issues
- HW
- Commissioning with beam if and when necessary
(i.e. unexplained obstruction somewhere in the
machine). - Operational applications
- This will remain an expert intervention. No
operational application is foreseen for this.
45...
46Details per Observable Q Q via BBQ Status
- Monitors, electronics and front end software will
be ready for the start-up - Well basically start with single kick method and
1 acquisition - we will return the raw data, the FFT and basic
peak detection for each measurement - these acquisitions will be triggered by a central
timing event also triggering the selected kicker
(tune kicker or damper). - PLL continuous measurement and RT monitoring will
come later (will require a few MDs)
47Details per Observable Q Q. Via BBQ
Remaining Issues
- HW
- Kicker selection (Tune Kicker or Damper) and
triggering?. (under discussion in ABCIS) - PLL commissioning (HW and FE SW will be ready but
will need MD time) - Feed back loop and commissioning (will be based
on BPM orbit feed-back infrastructure) - Operational Application
- Operational application to be started
48Details per Observable Q Q via Head Tail
Status
- Monitors, scope and front end software will be
ready for the start-up - Well start with a scope and basic FESA class
transmitting the raw data like in the SPS. - We plan to use the exiting expert application to
assess this system - No operational application is foreseen for the
start-up.
49Details per Observable Q Q via Schottky
monitors Status
- Monitors marked for phase II but ready and
installed. Well use the same electronics and
front end software than for the BBQ system - This is not a priority. The corresponding
operational application will be developed if time
allows.
50...
51Details per Observable Luminosity BRANA
BRANB Status
- Monitors will be ready for the start-up.
- 4 BRANA (left and right IP 1 and 5) developed by
Berkeley - 4 BRANB (left and right IP 2 and 8) developed by
AB/BI - AB/BI electronics and front end software will be
ready for the start-up. So should be Berkely. - Well basically have 2 acquisitions per IP
- Total relative luminosity at 1 Hz this quantity
is proportional in an unknown but constant way to
the actual luminosity the proportionality
constant may differ from IP to IP. - Bunch by bunch relative luminosity at 0.1 Hz
52Details per Observable Luminosity BRANA
BRANB Remaining Issues
- HW
- Commissioning with Beam
- Signal level and quality.
- Operational Application
- Operational application to be started
53Conclusions
...
54A word on a hypothetic sector test
- The new enlarged BPM (BPMWI) will be available
soon. - We still have to
- HW commission the LSS8 BTV
- Get missing Ethernet connections in UJ76
- We would install an ad-hoc system (not the final
one) to measure intensity from the BPM close to
the end. - So we could be ready if necessary.
55Conclusions
- Except for the BGI on beam 2 (destroyed during
bad bake-out), our instruments will be available
on time. - The targeted performances (in terms of accuracy
and resolution) of these instruments are the one
described in the LHC beam instrumentation
functional specifications. - But we will need a lot of MD time with stable
beam conditions to commission our instruments and
reach this performance. - We will discuss and document these commissioning
procedures during the coming months and come back
to you to fit the result in the 2 months for
commissioning to 7TeV ?