Title: Payload Safety Schedule


1
Payload Safety Schedule
  • AMS-02 KSC TIM
  • January 2005

2
AMS-02 Schedule - Planning
  • Previously Phase II Safety Review est. June 14,
    2005
  • This Schedule is at Significant Risk
  • Safety Data Package must be submitted no later
    than April 1, 2005
  • Final Review and Approval cycle (1 week)
  • Must occur no later than March 24, 2005
  • Integration of Review Cycle Comments (1 week)
  • Must begin no later than March 17, 2005
  • SDP Review by AMS-02 Community (2 Weeks)
  • Must begin no later than March 3, 2005
  • SDP Development must be complete by March 3, 2005

3
AMS-02 Schedule
  • SDP Must be complete to meet the June 14, 2005
    Phase II Safety Review Date by
  • March 3, 2005

4
Safety Review ScheduleRisks
  • All data must be provided well in advance of the
    SDP delivery date for AMS community review.
  • If all data waits to the last days to submit, it
    delays the generation and completion of the
    package, delaying the submittal to the safety
    panel and thus the meeting date.

5
Safety Review ScheduleRisks - Scheduling
  • Thermal Information is scheduled for delivery
    very late in the SDP development schedule. This
    date is earlier than original proposal for
    delivery per the TTCS Group.
  • Delivery of items in February will allow a
    minimum time to process and incorporate.
  • Lockheed Martin ? Jacobs/Sverdrup Transition

6
Safety Review ScheduleRisks
  • Currently safety data for the following lacks
    maturity
  • Cryocooler Loop Heat Pipe design change to
    propylene.
  • TTCS Carbon Dioxide Freezing Resolution
  • Warm Helium Supply Design

7
Remaining Work
  • Complete Hazard Reports
  • Majority Complete
  • Issues Remain and Are in Work
  • Develop Supporting Text for SDP
  • Descriptive Sections Lack Maturity
  • Provide Required Data Submitals That Must
    Accompany the Phase II Safety Data Package

8
Conclusion
  • June 14 safety review date is possible only with
    perfect delivery and no unforeseen events.
  • Recommend a reschedule of the Phase II Meeting
    Data no earlier than July-August timeframe.

9