Title: Waste Isolation Pilot Plant Progress Update
1(No Transcript)
2Waste Isolation Pilot Plant Progress Update
Western Governors Association WIPP
Transportation Advisory Group Meeting Denver,
CO September 28, 2004
Herb Cruickshank Carlsbad Field Office TRU Waste
Planning Manager
Casey Gadbury Carlsbad Field Office TRU Waste
Logistics Work Coordinator
3WIPP summary
4Panel 2 utilization
5Shipping corridors
121
Hanford
634
Idaho National Engineering and Environmental
Laboratory
Argonne National Laboratory - East
13
1,704
Nevada Test Site
Rocky Flats Environmental Technology Site
12
71
Los Alamos National Laboratory
445
Savannah River Site
3,000
Waste Isolation Pilot Plant
Transuranic waste removed
Total shipments as of 9/23/04
Rail
6Accomplishments - fiscal year 2004
- Safety
- Achieved 2 million safe work hours
- Received New Mexicos Mine Operator of the Year
for 17th consecutive year - Achieved DOEs highest safety rating for 9th
consecutive year - Transportation
- Received 3,000th shipment September 2004
- Completed removal of legacy CH-TRU waste from
Lawrence Berkeley National Laboratory May 2004 - Restarted shipments from Nevada Test Site
August 2004 - Regulatory
- Submitted Compliance Recertification Application
to Environmental Protection Agency (EPA) March
2004 - Obtained New Mexico Environment Department
approval to dispose of LANL sealed sources
March 2004 - Received approval from EPA on remote-handled
waste characterization procedures March 2004
7Accomplishments - fiscal year 2004 (continued)
- Operations (through September 10, 2004)
- Completed 5.5 safe years of operations
- Disposed of 8,297.66 cubic meters of TRU waste
most in any fiscal year - Completed mining of Panel 3
- Processed a record of 77 TRUPACT-IIs in a week
- Certified 7,745 drums with mobile
characterization at 3 facilities
8Objectives - fiscal year 2005
- Transportation
- Removal of legacy CH-TRU waste that meets WIPPs
Waste Acceptance Criteria from - Nevada Test Site
- Lawrence Livermore National Laboratory mid-year
- Rocky Flats Environmental Technology Site mid
year - Begin fabrication of TRUPACT-III test articles
- Operations
- Begin mining in Panel 4
- Closure of Panel 2 mid-year
- Process 87 TRUPACT-IIs per week
- Resume removal of high-wattage waste from Los
Alamos National Laboratory - Regulatory
- Receive approval of Compliance Recertification
Application from Environmental Protection Agency - Complete hearing before New Mexico Environment
Department on remote-handled permit modification
request
9WIPP recertification status
- WIPP submitted the Compliance Recertification
Application (CRA) to Environmental Protection
Agency (EPA) on March 26, 2004 - EPA must evaluate the completeness of the CRA
pursuant to 40 CFR 194.11 before processing the
application - EPA sent letters to DOE asking for additional
information and DOE is responding to these
requests - EPA held public meetings in Carlsbad,
Albuquerque, and Santa Fe, New Mexico the week of
July 26th - EPA indicates it may determine completeness of
application by the end of calendar year 2004 - Recertification of WIPP is expected 12 to 15
months after CRA submittal to the EPA
Determine completeness Determine continued
compliance Recertify
10TRUPACT-III status
- Packaging Technology (Pac-Tec) submitted safety
analysis report to Nuclear Regulatory Commission
(NRC) March 2004 - NRC raised questions during meeting July 2004
- Pac-Tec to submit a recovery plan
External measurements 82 x 88 x 1910.5
11Transportation recent events
- Two route deviations in Idaho
- Two shipments turned around en route
- Savannah River Site
- Idaho National Engineering and Environmental
Laboratory - Minor accident in Roswell, NM
- Avoidance of accident in Wyoming
12Route deviations in Idaho
- First Route Deviation
- Hanford shipment RL040013 deviated onto I-86 in
Idaho on April 6, 2004 at approximately 1030
p.m. - Driver not notified until the shipment was 55
miles off-route - Shipment back on approved route at 1225 a.m.,
April 7th - Lessons learned and actions
- Disciplinary actions - driver and WIPP operator
- Required Reading for WIPP operators
- Evaluation of TRANSCOM false alarms and
implemented corrective actions - Evaluation of GPS mapping system with route
deviation alert in cab - Quicker notification from CBFO to WGA and States
13Route deviations in Idaho
- Second Route Deviation
- Hanford shipment RL040013 deviated onto I-86 in
Idaho for 8 miles on June 3, 2004 - Driver turned around at emergency turn-around
- Investigation identified HRCQ procedural
violation - Immediate action to replace driver resulted in
minor shipment delay at Fort Collins, CO - CBFO notified WGA and affected States quickly
- Lessons learned and actions
- Disciplinary actions driver
- Mandatory procedural reviews and training
required for drivers
14En route SRS shipment returned
- Shipment summary
- June 9th - SRS shipment turned around near Pecos,
Texas - Possible prohibited item
- Upon receipt, shipment was evaluated
- No prohibited item was discovered
- Lessons learned and actions
- Administrative controls in place to ensure all
characterization questions are adequately
answered prior to shipment departure
15En route INEEL shipment returned
- Shipment summary
- INEEL shipment IN04029 turned around in southern
Colorado on July 14, 2004 - Discovery of certification authorization
non-compliance as required by WIPPs Hazardous
Waste Facility Permit - Certification authorization non-compliance
involved random sampling of waste drums added
to lot after random selection of drums sampling - CBFO identified the issue and made notifications
to WGA, affected states, INEEL, and New Mexico
Environment Department - INEEL corrected the deficiency through procedure
and process revisions - INEEL was authorized by NMED and CBFO to resume
shipments in September 2004
16INEEL shipment returned (continued)
- Follow-up activities
- Working with New Mexico Environment Department on
resolution of compliance order - Working with shipping sites to ensure procedures
are followed - Public risk and impacts
- Never any risk to workers, public or the
environment - No risk from waste already emplaced or negative
impact on future repository performance
17Accident in Roswell, New Mexico
- Event summary
- WIPP truck was stuck by a passenger vehicle on
Roswell relief route on July 23, 2004 at 1100
p.m. - Rocky Flats shipment received minor damage to
right front fender and wheel hub - No injuries
- No damage to trailer or payload
- Driver of passenger vehicle received citation
- State police conducted CVSA Level VI inspection
- Shipment released at 120 a.m. on July 24th
- Lessons learned and actions
- Good notifications from CMRO and CBFO to state
contacts
18Avoidance of accident in Wyoming
- Accident summary
- Multi-vehicle accident, August 19th, at 145 p.m.
- Sudden dense fog pocket on I-80 between Laramie
and Cheyenne - Driver of RL040053 went on road shoulder to avoid
collisions - Driver pulled an injured driver from burning
tractor-trailer - Drivers inspected shipment before leaving scene
- Escorted by Wyoming Highway Patrol to safe
parking at Warren Air Force Base overnight - Shipment left Warren Air Force Base about 8 a.m.
on August 20th - Excellent performance by drivers, including
actions above and beyond the call of duty
19Future scheduling
- Projected near-term schedule
- RFETS to ship about 15 shipments per week and
scheduled to complete shipments at end of April
2005 - INEEL to ship 6 - 7 shipments per week from
October 2004 through February 2005 then ramp up
to 15 - 19 shipments per week from May 2005
through December 2005 - NTS scheduled to complete about 31 shipments by
end of December 2004 - LLNL scheduled to complete about 20 shipments by
end of January 2005 - SRS and Hanford to ship approximately 2 4
shipments per week throughout federal FY 2005 - LANL scheduled to commence shipments Spring 2005
and ramp up to about 4 shipments per week - Three weeks of WIPP shutdown scheduled during
Thanksgiving and December holidays in 2004
20Future scheduling needs
- In order to meet commitments to remove TRU waste
- WIPP program needs flexibility in scheduling
- If a site is unable to ship as scheduled, CBFO
will determine if another site can ship - Two-week shipping request approval from DOE-HQ
- Will notify WGA prior to rescheduling
21Comments / Questions?