Title: Hybrid


1
Hybrid Module Testing Status
  • Week of 4/25-4/29

2
UCSB Hybrid Testing Status
Weekly Weekly Cumulative Cumulative  
Pass Fail Pass Fail Pass
L12pd 0 0 0 0 0.00
L34p 49 1 368 5 98.66
L56p 19 0 366 5 98.65
R5N 0 0 65 2 97.01
R5S 0 0 47 0 100.00
R6 0 0 87 1 98.86
R7 0 0 0 0 0.00
Total 68 1 932 13 98.62
Failing Hybrids Over-counted
3
UCSB Hybrid Testing Failures
  • This Week
  • 1 Too Many Opens
  • Damaged PA
  • Cumulative
  • 3 with Shorts in PA
  • Repairable
  • 1 Major Scratch in PA
  • 1 Smashed APV-PA Bonds
  • Repairable
  • 2 Failed Inspection
  • Never should have sent
  • 1 Broken Ceramic
  • 1 Bad Bond Feet
  • 1 Weak Wirebonds
  • 1 Too Many Opens
  • 2 with unknown failure

4
UCSB Hybrid Testing Issues
  • Need to finish validation of new software
  • Bruno contacted about bugs/features
  • Need to add automatic upload of data to new
    software
  • Hybrids with shorts need repairing
  • Once repaired need to keep bookkeeping straight

5
UCSB ARCS Testing Status
Weekly Weekly Weekly Cumulative Cumulative Cumulative  
A B F A B F A or B
L12pu 0 0 0 0 0 0 0.00
L12pd 0 0 0 0 0 0 0.00
L12su 0 0 0 0 0 0 0.00
L12sd 0 0 0 0 0 0 0.00
L34p 0 0 0 85 1 2 97.73
L56p 40 0 0 277 1 2 99.29
R5N 6 0 0 38 1 1 97.50
R5S 0 0 0 0 0 0 0.00
R6 44 0 0 68 0 0 100.00
R7 0 0 0 0 0 0 0.00
Total 90 0 0 468 3 5 98.95
6
UCSB ARCS Testing Failures
  • This Week
  • None
  • Cumulative
  • 1 with gt2 Bad Channels
  • Debris on sensor
  • 1 Bad DCU
  • 1 HV Shorted to CF Frame
  • 2 with gt20 mA Bias Current
  • 1 leaky pinhole
  • 1 scratched sensor

7
UCSB ARCS Testing Issues
  • Need to confirm cuts on TEC modules
  • Getting some confusion between 1SO/2SO
  • Have not produced TEC R6 modules in a year
  • Still need to validate ARCS 8.0
  • Currently using ARCS 7.2bugfix

8
UCSB LT Testing Status
Weekly Weekly Cumulative Cumulative  
Pass Fail Pass Fail Pass
L12pu 0 0 0 0 0.00
L12pd 0 0 0 0 0.00
L12su 0 0 0 0 0.00
L12sd 0 0 0 0 0.00
L34p 0 0 84 0 100.00
L56p 36 0 259 0 100.00
R5N 5 0 39 0 0.00
R5S 0 0 0 0 0.00
R6 28 0 43 0 100.00
R7 0 0 0 0 0.00
Total 69 0 425 0 100.00