SOT Initial Operation in Commissioning Phase - PowerPoint PPT Presentation

1 / 18
About This Presentation
Title:

SOT Initial Operation in Commissioning Phase

Description:

Run all the kinds of observables with combination. In ... Apogee (km) 630.0. Perigee-up maneuver #2. 3. 441.7. Perigee-up maneuver #1. 2. 253.3. Test maneuver ... – PowerPoint PPT presentation

Number of Views:30
Avg rating:3.0/5.0
Slides: 19
Provided by: solarb
Category:

less

Transcript and Presenter's Notes

Title: SOT Initial Operation in Commissioning Phase


1
SOT Initial Operation in Commissioning Phase
  • Y. Katsukawa (NAOJ)
  • SOT team

2
SOT initial operation overview
3
(I) Spacecraft verification and checkout phase
  • Period Launch ? Y20
  • Orbit control maneuvers are carried out several
    times to install the S/C to the sun-synchronous
    orbit.
  • Check-out of S/C attitude control system is also
    performed during this period.

4
(I) Spacecraft verification and checkout phase
5
(I) Spacecraft verification and checkout phase
  • After ?a1 (Y6), the altitude of S/C becomes
    high enough, and the attitude of S/C is
    controlled by MWs.
  • During the period between Y7 and Y20, we plan
    to do initial status check (temperatures) and CCD
    heater operation.
  • Primary objective is to decontaminate the CCDs.

?a2
MDP and FPP ON
CCD decontamination heater ON
3days
1.5 days
CCD decontamination heater OFF
FPP and MDP OFF
?a3
6
(II) SOT instrument checkout phase (1)
  • Period Y21 ? Y28 (TBD) (?1 week)
  • From the installation to the sun-synchronous
    polar orbit
  • To opening the SOT top door
  • The primary objectives are (1) decontamination of
    M1, M2, and HDM, and (2) initial functional
    checkout without sunlight into the telescope.
  • The test items of this phases are the following
  • Verify function of operational heaters for OTA
    and FPP
  • Open the telescope side door
  • Decontamination of M1, M2, and HDM
  • Verify function of mechanisms (shutters, filter
    wheels etc.)
  • FG, SP, and CT image acquisition
  • Automatic observation by MDP table control
  • Obtaining dark images is also important items
    especially for SP because there is no shutter in
    the SP optical path.

7
(II) SOT instrument checkout phase (1)
8
(II) SOT instrument checkout phase (1)
  • Obtaining dark images
  • Obtain the images with some camera setting
    (gain, amplifier)
  • Orbital variation, temperature dependence
  • Effect of cosmic radiation on the images
  • All the data taken during this period is to be
    down-linked at the Uchinoura station (USC).
  • Some of them will be down-linked at the Svalvard
    station (SVA) in order to test data transfer
    system from SVA to Japan.

9
(III) SOT instrument checkout phase (2)
  • Period Y30 ? Y45 (TBD) (?2 weeks)
  • First light phase after the telescope door is
    opened
  • The primary purpose of this period is
    verification of optical performance
  • Alignment with respect to sun-sensor, XRT, and
    EIS
  • Image quality and focus stability
  • Correlation tracker performance
  • Function of FG and SP observables, etc.
  • In-flight calibration of the instruments
  • Darks and flat fields
  • Polarization
  • TF wavelength tuning etc.

10
(III) SOT instrument checkout phase (2)
11
(III) SOT instrument checkout phase (2)
12
(1) Top-door opening / Initial optical check
  • One of the most critical event in the initial
    operation
  • Make the satellite pointing to the disk center
  • Light level is continuously monitored by CT live
    images when the door opening operation.
  • After the top-door is successfully opened, we
    plan to switch observation tables to carry out
    the initial optical checkout.
  • Light level check for FG (all the wavelengths),
    SP, and CT
  • SP 6301.5/6302.5 spectrum line positions and
    profiles
  • Alignment check to the sun-sensor (chromospheric
    features may provide pointing information even in
    QS)
  • Quick focus scan and adjustment are planned to be
    done in real-time operation half a day after the
    door operation.

13
(2) Background observations during the operation
of the other telescopes
  • SOT commanding operation cannot be done during
    the door opening operation of the other
    telescopes.
  • We plan to run some observation tables in
    background with low cadence in order to verify
    the following items.
  • Data transfer from Svalvard station
  • Image compression efficiency
  • Dark images, flat fielding (by averaging many
    images)
  • Camera noise (light transfer measurement)
  • Alignment with respect to XRT and EIS
  • CT diagnostic data to get S/C jitter information
  • SP full FOV scanning (to check vignetting and
    alignment)
  • BFI observations (e.g. G-band) with shorter
    exposure can be possibly carried out without
    correlation tracker. Such observations with
    longer duration may provide information on
    orbital variation of image quality.

14
(3) Correlation tracker servo-on / Detailed
verification of optical performance
  • After CT servo is turned on, we can go to
    detailed verification and calibration of optical
    performance.
  • Fine focus scan
  • Image quality evaluation
  • Co-focus among different channels
  • Adjust focus position if necessary
  • Continuous observations for several hours with a
    few wavelengths
  • Orbital variation of image quality
  • Inter-channel alignment
  • Image quality degradation by disturbance from
    FPP, XRT and EIS
  • Flat fielding
  • Flat fielding by intentionally move the tip-tilt
    mirror
  • Tunable filter (TF) wavelength scan/ NFI
    observables
  • TF spectroscopic performance
  • Update tuning parameters if necessary
  • Verification of MDP Doppler velocity compensation

15
(4) Limb observation
  • After optical performance verification is done
    near the disk center, we like to go to limb
    observation.
  • The verification items in the limb observation
    are
  • S/C pointing check
  • Image quality and focus change between DC obs and
    limb obs
  • Scattered light
  • TF wavelength tuning, MDP Doppler compensation
  • Function of the correlation tracker in limb obs.

16
Pointing and target selection in the first light
phase
  • We have to know misalignment with respect to the
    sun sensor (ACS), XRT, and EIS as fast as
    possible for the secure operation.
  • After the satellite pointing is established, we
    like to track a suitable active region near the
    disk center if we have for verification of the
    optical performance (as well as scientific
    interest).
  • When the verification near the disk center is
    done, the limb observation is necessary to verify
    performance of SOT at the limb. We may go to the
    limb observation automatically by tracking an
    active region in the first light phase.
  • After the limb observation, we can make SOT
    pointing to any region.

17
(IV) Performance verification (PV) phase
  • Period Y46 ? Y60 (TBD) (?2 weeks)
  • After the first light phase
  • The primary purpose in this phase is verification
    of scientific performance of the SOT observables
  • Background
  • SOT has a capability to observe various
    scientific targets.
  • Wavelength coverage
  • BFI 6 channels, NFI 6 channels, and SP 6302A
  • Many types of observables
  • Single image, LOS magnetograms, Stokes IQUV, and
    Dopplergrams
  • Temporal and spatial sampling
  • Knowledge obtained in this phase shall be used
    for following scientific operation.

18
(IV) Performance verification (PV) phase
  • Phase-I
  • At first, we verify performance of high-priority
    observables with a typical wavelength to verify
    basic scientific performance of SOT
  • Only one observable or simple combination are
    used for long duration (several hours ? half a
    day).
  • SP observations can be carried out simultaneous
    with FG.
  • Phase-II
  • After the verification of each observable is
    completed, we make combined observations with
    multiple wavelengths and observables.
  • SP observations can be carried out simultaneous
    with FG.

19
(IV) PV Phase-I
  • Make observations with some observables with
    typical wavelength for long duration to verify
    long-term stability.
  • Some of them can be carried out in the first
    light phase as background observation

Examples of FG observation sequences
20
(IV) PV Phase-I
Examples of SP observation sequences
  • Some FG observables, especially magnetograms and
    Dopplergrams, shall be carried out simultaneous
    with SP in order check their performance.

21
(IV) PV Phase-II
  • Make combined observations with multiple
    wavelengths and observables.

Examples of FG observation sequences (multiple
wavelength combination)
22
Target region selection in PV phase
  • In general, we track one active region for
    several days - one week.
  • When there is no active region on the sun, we
    observe quiet regions, dark filaments etc. with
    science priority.
Write a Comment
User Comments (0)
About PowerShow.com