Title: CD Project Status Meeting


1
A Pixel-Based Tracker to Probe the
Quark-Gluon Plasma at PHENIX
CD Project Status Meeting June 20th, 2006 Marcos
Turqueti
Electronic Systems Engineering
2
OVERVIEW
  • Colaboration between Los Alamos National
    Laboratory and Fermilab.
  • Funded by Los Alamos National Laboratory.
  • Design tracking stations in a forward tracking
    sector in the PHENIX(1) experiment at RHIC(2) .
  • The tracker will be used to identify Charm and
    Beauty quarks that are produced early in the
    heavy ion collisions.
  • The detectors, based on an Atlas/BTeV design,
    comprise approximately two million pixel elements.

(1)The PHENIX Experiment is the largest of the
four experiments currently taking data at the
Relativistic Heavy Ion Collider (RHIC).PHENIX,
the Pioneering High Energy Nuclear Interaction
eXperiment.
(2)The Relativistic Heavy Ion Collider (RHIC) at
Brookhaven National Laboratory is a world-class
scientific research facility that began operation
in 2000, following 10 years of development. and
construction.
3
(No Transcript)
4
WHAT ARE WE DOING?
Pixel Module HDI modification on existing
design. Pixel Module Test Board modification
on existing design. Pixel Plane PCB new
design. It requires intensive interaction with
same mechanical team we were working with for
BTeV ?good work relationship. Test Stand
integration of the new PTA card, it will consume
most of the effort. Five Tested Pixel Modules
quality will depend on bump-bonding and sensors.
Cant promise working modules.
5
WHERE ARE WE NOW?
6
HOW THE PIECES ARE COMING TOGETHER?
PIXEL MODULE
PIXEL TEST COMBO
STORAGE
PIXEL TEST CARD
OTHER MODULES
PIXEL TEST STAND
PIXEL PLANE
(A) CLASS MODULE
7
MODULE AND TEST CARD
PIXEL MODULE IS DONE, WAS MANUFACTURED AT CERN
AND IS BEING SHIPPED TO FNAL, SHOULD ARRIVE ON
JUNE 23.
TEST CARD IS DONE,WAITING FOR THE PIXEL MODULE TO
BE TESTED.
  • Stakeholders
  • Jeff Andresen, John Chramowicz, Guilherme Cardoso
    and Marcos Turqueti

8
PIXEL PLANE
WAITING FOR DEFINITIONS ON SPECIFICATIONS FROM
LOS ALAMOS, CURRENTLY SIMULATIONS AND PROOF OF
CONCEPT ARE BEING DONE.
  • Stakeholders
  • Guilherme Cardoso and Jeff Andresen

9
TEST STAND
FIRMWARE
PIXEL TEST COMBO
SOFTWARE
TEST
PC
PCI SLOT
10
TEST STAND FIRST RESULTS
  • Stakeholders
  • Marcos Turqueti and Guilherme Cardoso.

The analysis code was written by Sergey Butsyk
from Los Alamos National Laboratory and is
integrated on the main code.
11
SUMMARY
  • THE PROJECT HAS EVOLVING VERY FAST, SOME PARTS
    ARE ALREADY REACHING COMPLETION.
  • THE PARTS THAT ARE IN INITIAL STEPS OF DESIGN ARE
    DEPENDENT OF FURTHER INTERACTION WITH LOS ALAMOS.
  • THE TEST STAND IS ALREADY PRODUCING RESULTS AND
    EVEN BEING USED TO CHARACTERIZE THE NEW FPIX 2.1.
  • THE NEXT STEP WILL BE THE TEST OF THE PIXEL COMBO
    AND IN PARALELL THE DEVELOPMENT OF THE PIXEL
    PLANE.