Title: Cal J' Gendreau
12009 Construction Conference
- Cal J. Gendreau
- Construction Services Engineer
22008 Review
- Mission Providing a transportation system that
safely moves people and goods - 2008 Contacts Administrated 271,633,426 in
Contract improvements - 2008 Customer Survey 84 Overall Satisfied
(Residents, Motor Carriers, Government Officials,
Business) - Reason Foundations 17th Annual Report on the
Performance of State Highway Systems North
Dakota number 1 in Cost Effectiveness
3Looking Ahead to 2009
- The American Recovery and Reinvestment Act of
2009 - Roads and Bridges
- 27.5 Billion Dollars
- States must obligate 50 of the funding in 120
days - Remaining 50 within 1 year
- Goal 835,000 jobs created
- North Dakotas share? 170 Million
- 100 Federal Funded Projects
4Looking Ahead to 2009
- Workload by Dollar Amount
Estimated Construction Costs in Millions
5Looking Ahead to 2009
- State Workload by Staffing
Estimated Construction Costs in Millions
6New Employees
- 16 Engineers hired since January 2008
- Special Forces 5
- Materials and Research 3
- Planning 3
- Bridge Division 2
- Minot District 1
- Devils Lake District 1
- Grand Forks District 1
7New Employees
- 8 Technicians hired since January 2008
- Fargo District 3
- Grand Forks District 2
- Bismarck District 2
- Valley City District 1
8Special Forces
- Current Pool numbers are 14
- Transportation Engineer III 1
- Transportation Engineer I 11
- Engineering Technician III 1
- Engineering Technician II 1
9Rotational Training Program
- Mandatory for all Transportation Engineer Is
- Two Training Tiers available (1 year and 2 year)
- Rotation through Construction/District varies
between 3 and 12 months - Currently 8 employees that are not Special Forces
or District hires that will need rotations
through Districts
10Young Professional Award
- NDDOT named North Dakotas best place to work in
2008
11Engineering and Technical Training
- New Engineering Technical Training Manager
Position established - Establish Training Goals and Objectives for
Engineering and Technical training - Manage Training budget and contracts
- Develop Training Aids and Manuals
- Web-based Engineering and Technical Learning
Institute
12Contractor Competition
- Past trend down seems to be improving slightly
13Fuel Adjustment Clause
14Fuel Adjustment Clause
- No changes made after 1 year review with Industry
- 2008 Statistics About 40 of all Contracts
15Red Line / Green Line
- 2008 Reviews
- SS-RSS-6-032(034)130
- Cold In-Place Recycling and Hot Bituminous
Pavement - Contractor Mayo Construction
- Discussion Ride of the recycled pavement,
maintenance of the surface prior to overlay, cure
time, gradation and ownership of salvaged
materials - AC-HPP-NH-3-002(086)199
- Widening and Whitetopping
- Contractor Progressive Contractors
- Review Pending
- 2009 Projects
- Looking for Projects to include in the program
16Electronic Plans
- Since April 2008 Bid Opening, no longer printing
and mailing Project plans and proposals - Plans, Proposals, Soils Reports, Cross Sections
and Addendum all provided electronically via the
Web - Current Issues File size and downloading
- Future plans Provide a library function after
the bid opening to provide Public access to final
plans and Contract documents
172009 Emphasis Areas
- New Spec Book is out
- Quiz later
- Work Zone visibility
- ANSI 107-2004 Class 2 or 3 vest required by all
persons in the Right of Way - Flaggers
- New Flagger Handbook
- Inspection just like any other item of work
- Training Certificate
- Proper Signing
- Flagger Actions and Responsibilities
182009 Emphasis Areas
- Subcontractors Definition (Page 16)
An individual, or legal entity with whom the
Contractor sublets part of the Contract
Any work, except for off-site commercial
production of materials and manufactured
component products that the Contractor purchases
or their transportation to the project requires
a subcontract.
- Subcontractor Approval (104.02)
The Contractor shall not sublet, sell, transfer,
assign, or dispose of any portion of the Contract
or Contracts without written consent of the
Engineer.
192009 Emphasis Areas
- Requests to Sublet Approval
- Standard Form SFN 5682
- Maximum percentage that can be sublet is 70
- Items of work, and quantities of each item must
be shown. Partial items must be explained. - A copy of the subcontract agreement must be
provided - A Subcontractor must be either a Qualified
contractor, a Registered subcontractor, or a
Certified DBE. These current lists are provided
on NDDOT website - District Engineer has approval authority for all
Requests to Sublet
202009 Emphasis Areas
- Subcontractor Registration
- Standard Form SFN 52243
- Required yearly
- Goal
- Maintain some basic subcontractor information
- Data is recorded by NDDOT and used to fill
Subcontractor fields in CARS - Approval process both local and central
- Some regular subcontractors file this each year
automatically with Construction Services - Some dont file it until the first subcontract of
the year
212009 Emphasis Areas
- If you receive a Request to Sublet for a
subcontractor that is not registered - Ask the subcontractor to fill out the
Registration form - Review the form for completeness, notary and
signature - If the form is complete, the registration can be
considered approved. Same District Engineer
approval authority as the Request to Sublet. - Mail the Registration form together with the
Request to Sublet to Construction Services for
processing.
222009 Emphasis Areas
- Subcontract Form Processing
- After approval of a Request to Sublet, and if
necessary, a Subcontractor Registration form,
make a copy and send the original forms to
Construction Services - Construction Services then scans the original
Sublet form and provides a electronic Filenet
copy under the Project number - Originals forms are maintained in the Divisions
paper file - Questions?
23Change
- Definition
- A change is the difference between the contract
requirements at the time of bid and the actual
requirements imposed during construction - Why is the time of bid important in establishing
whether a difference occurred? - Change is inevitable in this kind of work
- Design-Bid-Build contracts include a changes
clause. Standard Specification 104.03
242008 Change Orders
- 271,633,426 in Contractor payments made
- 360 Change Orders issued
- 5,393,563 Change Order total
- 2.0 Increase due to Change Orders
252008 Change Orders by Approval Level
1 FHWA approval on Full Involvement Projects
Typically NHS projects gt 5,000,000
262008 Change Orders by Classification
27Unresolved Change
- Unresolved Change can lead to disputes, which can
lead to claims - Contractor does not agree with the Owners
determination on the difference between the
contract requirements and the actual requirements - Contract requires notice of unresolved change
(Standard Spec 104.06 A) - Why is timely notice important?
- Why is a timely reply to notice also important?
28Notice of Intent Trends
- 2008 Claims
- 1 claim received. It was resolved by Change
Order before a formal response was required. - 2008 Arbitration
- 1 arbitration hearing for a 2007 claim was held.
29Evaluating Unresolved Change
- Three Basic Steps
- Entitlement
- Determine if a change has occurred
- When a change has occurred, next determine who
has caused the change or is liable for the change - Impacts
- Where the owner has caused a change, the next is
to determine the impacts of the change. These
may include extra work, delays, reduced
efficiency, increased material costs, etc. - Damages
- Once impacts are defined, determine the
associated damages. Damages can be additional
compensation and/or additional time
30Entitlement Provisions
- Significant Changes in Character of Work
- Differing Site Conditions
- Suspension of Work
- Extra Work
- Eliminated Work
Required by FHWA for all Federal Aid work
changes clause
31Significant Changes in Character of Work
- Standard Specification 104.03 A
- The term significant change shall be construed
to apply only to the following circumstances - When the character of the work as altered differs
materially in kind or nature from that involved
or included in the original proposed
construction, or - When a major item of work, as defined in Section
104.03 B, is increased in excess of 125 percent
or decreased below 75 of the original Contract
quantity.
32Differing Site Conditions
- Standard Spec 104.04
- Latent (hidden) physical conditions that differ
materially from - those indicated in the contract, or
- those ordinarily encountered
- Does not reduce the Contractors obligation to
perform a reasonable pre-bid investigation
(102.06) -
33Suspension of Work
- Standard Specification 104.05
- Allows the Owner to stop the work
- Allows for an adjustment for cost and/or time
required to perform the work where the suspension
was - Caused by conditions beyond the control of and
not the fault of the Contractor, and - Not caused by weather.
34Extra Work
- Standard Specification 104.03
- Provides for an adjustment in compensation and
time when extra work is required to complete the
project. - New specifications on preference for compensation
- Unit bid prices
- Price schedule for miscellaneous items (PS-1)
- Either agree to a negotiated unit price or
complete the work under Force Account (109.04) - Specifies the allowable markup for subcontract
work
35Impacts
- Impact Determination
- Extra work
- What is different from what was bid?
- What equipment and labor was added or changed?
- Delays
- Was the work critical?
- Excuseable delay? (Both unforeseen and not the
contractors fault) - Compensable delay? (Time and cost recovery)
- Reduced Efficiency
- How does the productivity compare between
unimpacted work and impacted work (measured mile)
36Damages
- NDDOT Contracts specify how damages are to be
calculated - Compensation
- Unless agreed upon in advance to use Force
Account (109.04), costs are calculated according
to Standard Specification104.06 Claim for Extra
Compensation - Time
- Standard Specification 108.04 Determination and
Extension of Contract Time -
37Claims Avoidance
- Open, frequent, and continued communication
- Partnering
- Careful preparation of design documents
- Careful preparation of contract documents
- Procedure for Pre-bid questions
- Proper project documentation
- Dispute Resolution procedures
38Quiz
- How have federal regulations changed with regards
to weekly payrolls?
- Removed the requirement that weekly payrolls
contain employees social security numbers and
home addresses - Required that certified payrolls include a unique
employee identification number for each employee
and that Contractors maintain records of
employees social security numbers and home
addresses - Required that the Contractor provide any required
employment records upon request of the agency
39Quiz
- True or False?
- All Contractors Requests to Sublet forms shall
be submitted with a Subcontractor Registration
form?
False. If a subcontractor is currently on the
Qualified Contractors list, the Registered
Subcontractors list or the Certified DBE list, a
registration form is not required.
40Quiz
- Prompt Payments Requirements
- How often must the Engineer make partial payments
based on the value of the work performed and
materials delivered by the Contractor?
Answer At least once every 30 days (109.05 A)
- Prompt Payment Requirements
- How often must the Contractor make partial
payments based on the value of the work performed
and materials delivered by a subcontractor?
Answer The Contractor must pay the
subcontractor for work done or services rendered
within 20 calendar days of receipt of payment
from the Agency (109.05 B)
41Quiz
- True or False?
- If the Contractor withholds payments from a
subcontractor, the Contractor must immediately
notify the subcontractor and the Engineer in
writing the reasons for withholding the payment.
True. (109.05 B)
42Quiz
- Extra Work
- What are the specified methods for payment of
extra work in order of preference?
- Answer (104.03)
- Unit Bid Prices
- PS-1 Price Schedule for Miscellaneous Items
- Force Account or Negotiated Unit Price
- Extra Work
- Is extra work completed by a subcontractor at
unit bid prices eligible for additional
Contractor reimbursement for profit and overhead?
Answer No (104.03)
43Quiz
- Significant Change Quantity Underrun
- Can the Contractor payment for a major item, that
underruns the plan quantity by 25 or more,
exceed 75 of the original contract amount?
Answer No (104.03 B. 2. Revised 2008)
44Quiz
- Environmental Protection - Erosion Controls
- On grade widening and selective grading project,
construction operations shall be limited to
________ miles until erosion control measures
have been started in the first mile.
Answer Five (110.06)
45Quiz
- Partial Payment Payment for Materials on Hand
- In order to pay a Contractor for stockpiled
materials, is the Contractor required to furnish
a paid invoice for the material?
Answer No. Contractor has 35 days from the
stockpile payment date to submit an invoice for
stockpiled materials that have not been
incorporated into the work (109.06)
- Fuel Adjustment Clause Payment for Materials on
Hand - Are stockpiled material payments included in the
monthly total of work done to date for the
purposes of calculating the fuel adjustment
clause?
Answer No (SP Fuel Cost Adjustment Clause)
46Questions?