Title: Diapositiva 1
1BORN BY COMBINATION. Key resources and tools for
setting up local public goods in mountain areas
of Emilia Romagna
Antonella Bonaduce, ERVET - Emilia Romagna
Region - Evaluation Unit
Bruxelles - 22th September 2009
2The Evaluation Plan The Integrated Approach
important challenge for the Emilia Romagna Region
- (1) Focusing on evaluations
- NOT ONLY at level of operational programme
- BUT ALSO at level of sub-regional areas or
policy field across operational programmes - (2) Building and fostering the evaluation
capacity - NOT ONLY within administration
- BUT ALSO outside it, challenging professional
networks and partnerships
3The Evaluation plan The overall framework for ex
post and on-going evaluation
- Traditional programme evaluation
- Evaluation in order to understand the specific
contribution of a single operational programme
(ERDF, ESF) towards regional policy objectives - Example
- Ex post impact evaluation of the ERDF
operative programme 2000 2006 - Evaluation across programmes
- Combined effects of actions funded under
different programmes at territorial level and the
value added of the integration of various
policies - Example
- Evaluation of intervention in mountain areas
4Why Mountain areas? The mandate of the Regional
Government
Objective 1 Objective 2
Objective 1 Objective 2
Phasing-out (till 31/12/2006) Objective 2 (partly)
Phasing-out (partly) (till 31/12/2005) Phasing-out (till 31/12/2005)
5Why Mountain areas? The mandate of the Regional
Government
6Why Mountain areas? The mandate of the Regional
Government
- Mountain areas were interested during the
20002006 programming period by different policy
and financial resources, but - not always expected results have been achieved.
In these areas there are persistent and
structural development needs - Mountain areas were confirmed as strategic
territories for regional policy for the 2007-2013
programming period and so financial resources and
tools were identified - It was considered important to understand why
what worked actually worked, in order to learn
how to better design, implement and deliver
public policies for regional marginal areas.
7The Evaluation Goals The Choice of the Unit of
Analysis
- Evaluation activities should capture the
inception of long term changes - Evaluation should analyse the interaction between
different policies / programmes/ interventions - Evaluation should derive general level criteria
as possible reference for future operational
programmes - Focus on successful interventions
- Analyse why, how, and what were the mechanisms
enabling policy interventions (development,
implementation, etc) - The definition of Local Public Good as criterion
to identify successful interventions
8The choice of the unit of analysis
- The successful interventions able to change the
conditions of a specific area - HOW?
- Increasing the Human and Social capital
(training and vocational centres) training
centre) - Improving the access to service for firms and
population of the area (telematic
infrastructure) - Reducing the environmental impact and improve the
competitiveness of the local firms (environmental
certification) - Increasing the value of cultural and
environmental resources of the area.
9The choice of the unit of analysis
- The territorial context of the intervention
became an important aspect to take into
consideration in the evaluation analysis of local
public goods - WHY?
- Territorial Context can influence the mechanisms
enabling the setting up of local public goods and
this means that it can influence the impact of
the policy -
- Coordination is important in order to provide
local public goods, it is important to
understand WHO place this role in the different
contexts.
10The evaluation questions
- The first evaluation question is
- How was the provision and the setting up of
local public good? - Which local needs have been satisfied?
- How have local needs been recognized?
- Who were the institutions and the other actors
involved in project implementation? - Which are the mechanisms enabling the setting up
of local public goods? - The second evaluation question is
- Is it possible to recognize common aspects,
fruitful mechanisms in order to provide inputs to
local needs? - What factors can influence these mechanisms?
- Have Operational Programme characteristics
influenced the process?
11The choice of the method and organisation of the
activity
- Case study analysis
- Direct interviews with different actors involved
in the process
- Project Team
- with different competence and experience
- internal to the regional administration
- The role of the evaluation unit as coordinator of
the project team - The role of operational programmes managing
authorities in the selection of successful
interventions (50 projects) - The establishment of a Steering group.
12Lessons about the provision and setting up of
local public goods
- Provision and implementation process can be
different and different are the resources
involved financial and administrative
resources, know how and competences, agreement
and consensus between different actors - Resources involved are not only local
- Different resources have different importance in
the process
13Lessons about the provision and setting up of
local public goods
FOUR POSSIBLE MECHANISM The first mechanism is
where the consensus is the driving resource a
group of people, sharing the same need or
interest, moves in search of the solution for
change. In the second mechanism knowledge is the
driving resource. An exogenous model of
intervention moves in search of the relevant
stakeholders, as a response to the social need.
The third mechanism is where the
administrativecompetence is the catalyst. The
project design and organization are defined and
managed strategically at administrative level as
a response to a collective need identified before
its emergence.
In the fourth mechanism knowledge and consensus
are activated together and feed each other.
14Lessons we are trying to convince Managing
Authority to learn
- The architecture of the operational programme
can contribute to the production process of
local public goods selection criteria, actors
involved, institutional tools - The story of the implementation of public good
is longer than the programming period - Integration of financial resources and
different policy intervention
15Lessons about about evaluation practice
- It has been difficult but we could manage (not
impossible) - TRUST and a COORDINATION ROLE
- Inside the team project
- In the relationship with the managing authority
- External experts (Steering Group) to help in
understanding where and when something is wrong - Involvement of stakeholders during the evaluation
activities but also discussion/decision/ choice
within the team project
16- THANK YOU FOR ATTENTION
- for more information
- Direzione Generale Programmazione territoriale e
negoziata, intese. Relazioni europee ed
internazionali - Nucleo di Valutazione e Verifica degli
Investimenti Pubblici - Tel. 051/6395820 Fax. 051/6395504
- www.fondieuropei2007-2013.it