Title: Beam Line Status
1Beam Line Status
MEG-Review February 2006
2Measurement Synopsis
- 2005 (post last Review) 2 Beam periods
- mid July end August
- ? BTS arrival Commissioning
- (for technical reasons only dewar
operation possible) - ? Bfield mapping
- ? Phase Space measurements up to end BTS
- misalignment sensitivity observed ?
design steering magnet - beg. November end December
- ? Commissioning BTS with PSI LHe Cryo-plant
- BTS Control systems
- aim to achieve automated BTS
operation - ? Injection Phase Space measurements
inside COBRA - temporary He-Bag system for COBRA
3-D measuring machine - APD new horizontal steering
magnet implemented
3Beam Line Status
-
- All beam elements functioning
- - BTS stable in automatic mode
- - Separator now stable
- - improvised He-Bag for COBRA constructed
tested - - horizontal steering magnet manufactured
installed - Beam Line Commissioning Phase 1 part Phase 2
finished -
(rest Phase 2 2006) - - First beam injected into COBRA measurements
with all Bfields ON - COBRA end-caps/He-Bag System - design close to
completion - - US End-Cap fully designed (apart from Burst
valve system) - - DS End-Cap, same as US apart from central
part for Insertion System, (awaiting
completion of Insertion Tube System design) - Insertion Tube System
- design study underway
- Target System
- Discussions with Bill (UCI) Makisan (KEK) about
3 potential designs also UCI expressed interest
in taking-over the target design/manufacture
agreed on, though in coordination with PSI (beam)
4Measurement Schedule Nov.-Dec. Beam Commissioning
- First Time Operation
- of BTS with LHe-Cryo. Plant
- 4 weeks (2-planned)
- to cool-down
- have stable
- AUTOMATIC
- OPERATION
- (thanks go to Cryo. Group Stefan)
- 5-days lost Separator
- Repair
5Nov.-Dec. Measurement Programme
Measurements with Degrader DC-test Not
possible ? 2006
?
?
?
?
?
?
?
6COBRA Injection Test Setup
LHe From Cryo. Plant
CH2/EVAL/CH2 sandwich
BTS-COBRA Improvised Connection He-Bag US
Improvised He-Bag DS
7Phase Space Measurements
Magnet measuring machine
APD
COBRA DS without He-Bag
- Measurements performed in COBRA
- excitation curves like - unlike --
polarities - beam profiles rates at centre both polarities
SNM, DNM - for ? 0, 180, 30, 45, 60
- axial z-scan over whole COBRA length
- profiles at various z-positions
- Present priority end-cap
design - Detailed Analysis of Nov./Dec. data to be
started shortly
8Provisional Results Centre COBRA
COBRA Axial z-scan (No Degrader)
Very similar to GEANT Predictions
BTS-Excitation Curve to focus beam in COBRA
unlike - Polarity
Measured Rate at Centre COBRA (Dependent on
mode) Rµ (1.15 - 1.19)108 µ s-1 at 1.8mA 4
cm Tg.E
9Provisional Results Centre COBRA cont.
COBRA Horizontal Vertical Beam Profiles In
100He No Degrader
GEANT 90 He 10 Air
? 12.8 mm
Reality
? 13.5 mm
Theory GEANT
Reality
- ?
- Investigating misalignment asymmetry for BTS
/- focusing - !!! Varies with mode ? up to
10 mm off centre !!! - re-measure BTS radial symmetry during COBRA /
BTS field mapping - magnetic axis geometrical axis
???
10Sonic Resonance Gas Concentration Monitor (SRGCM)
- Developed during Nov./Dec. run
- flush COBRA exhaust gas through pipe length L
- use frequency generator, speaker microphone
to create standing wave in pipe - measure resonant frequency overtones ?
determine SPEED OF SOUND in GAS - compare to pre-calibrated curve of SPEED of
SOUND vs. HELIUM CONCENTRATION
- 2L?fij i (j1)
- or
- L ?fii jj ii ( jj2)
1st resonance 2nd resonance 3rd
resonance 4th resonance
With systematics under control
refinements Absolute precision lt lt 0.5 achievable
Frequency
COBRA measurements gave (91.6 0.2) He rest
Air
He-Concentration
11Setup
Gas-Rack
Frequency Generator
Oscilloscope
Pipe (88.6cm)
Air
Microphone
Speaker
Helium
12COBRA End-Cap Flanges Insertion System
- Based on extensive background studies (Kenji)
- Permanent Rohacell insertion tube rejected for
- fixed ?-target (with rotation/translational
possibility) - retractable insertion bellows system for
- accelerator, LH2-target beam monitoring
- future insertion possibilities
e.g. US End-Cap Flange DS-version
Mounted after DCs US-TCs
- Upstream End-Cap Design finished
- apart from rupture valve
system - deadline for completion mid-Feb.
- Downstream End-Cap very similar to US
- apart from central region for Insertion system
- DC cable/gas feedthroughs
- finalization of design depends on completion
- of insertion system design
- deadline for completion mid-March.
13Rupture Valve System
Diminish damage to COBRA environment (mainly DCs)
due to rupture of beam vacuum window (Prob.
2/30 yrs)
- Simplified Calculation based on
- Bernoullis Equation
- Darcy-Weisbach Equation for
- turbulent flow
- Colebrook-White approximation for
- frictional factor Moody diagram
- conservation of mass
- Possible to approximate flow conditions
- after rupture
- ignoring SHOCK WAVE !!!
V3
V3
Vacuum V1
He V2
V3
- No Rupture Valves
- Depressurization time 10 ms
- streaming velocity in vac. 660 m/s
- Reynold number 1.4106 (turbulent gt4000)
- ?PCOBRA 446 mb
- ?TCOBRA 63 K
14Rupture Valve System cont.
- With Rupture Valves max 4 US 4 DS
- re-pressurization time 890 ms/ 1 burst valve
- pressure compensation for 8 valves in 10 ms
- 20 mb/ 10 ms
- Conclusion with 8 Valves dMAX 6 cm
- ONLY 5 compensation !!!
Spring-loaded Hinged Sealing flap
Inside He
Outside air
- Reality must consider
- SHOCK WAVE enhanced by He
- generated into vacuum pipe
- reflection 10 ms also
Contact Surface 979 m/s
COBRA
Shocked air
vacuum
shock front 1175 m/s
Expansion front 1000 m/s
Expansion tail 933 m/s
Conclusion need a faster acting system !!!
Not Solved new idea
15Insertion System
- Insertion System
- telescopic triple-rod system with
- NBR rubber bellows 1mm thick
- outer dia. 270 mm inner dia 170 mm
- attached to DS-end-cap
- retractable into end-cap flange
- allows insertion up to z -150 mm
- allows proton beam-pipe, LH2-target, beam
- monitor as well as possible future devices
- to be inserted with minimal disturbance
- of COBRA He-environment
- motor driven via accelerator bellows motor
- hand driven possibility via friction drive
Rubber Bellows extended
Rubber Bellows retracted
Couples to Accelerator Bellows
accelerator Bellows system motor
16Target system
- Various solutions under study
- UCI/PSI/KEK
- Permanent Muon Target
- Rohacell foam/CH2 combination
- Complete Rohacell
- CH2 or polystyrene Target wire frame
- Support
- from DC frame- rotatable or translational
- Prototypes be investigated at UCI
- Position monitoring
- Idea of using several holes in target? x,y,z
DC support structure
- Monte-Carlo simulations - underway
- check of optimum target inclination wrt.
Energy-loss, - multiple scattering, high/low-energy photon
generation, - momentum resolution, DC/TC-efficiency
- effect of thicker solid Rohacell target as well
as support - structute on vertex angular
- reconstruction resolution timing resolution
and back- - ground generation
- Others Polarization data Rohacell
17Schedule 2006
18Manpower 1st Half 2006
Provisional Numbers