2Accomplishments Since Last Briefing
- QA implementation assessed for EM NE
- Weld quality alert field reviews in progress
- QA-related ORPS data preliminary analysis
complete - QA Order and Guides complete
- Filter Test Facility relocation progressing well
HEPA standards update initiated
3QA Focus Areas
- Leadership
- Flow-down of Requirements
- Integration with ISM
- Implementation of Requirements
- Effective Analyses
- Oversight and Assessment
4Quality Assurance Leadership
- Technical Codes Standards participation
- ORPS manual being updated
- Ongoing Directives updates
- Enforcement Guide Supplement drafted Contractor
Investigation, Causal Analysis and Corrective
Actions - DOE Assessment Guide update to incorporate EH-6
enforcement guide and industry advances - Working with EFCOG to develop interactive ways
for delivering safety and QA guidance and lessons
learned to workers the field
5 Quality Assurance Leadership
- Communicating leadership in a QA newsletter
- First issue June 05
- Bridge between the various DOE organizations,
sites, contractors, EFCOG, SMEs, standards
committees, etc. - Forum for exchange of ideas and success stories,
sharing improvement techniques, approaches, and
tools of the trade
6Flow-down of QA Requirements
Weld Quality Alert Results
7 Flow-down of QA Requirements
- EH-1 memo to PSOs on flow-down of SQA
requirements after DOE O 414.1C issued - EFCOG QA deliverables
- Supplier Quality Improvement Initiative
additional data needed - Attributes of an Effective Quality Improvement
Process - Extent of Conditions Review (PAAA)
- Continuing evaluation of contract language
8Integration with ISM
- EM field assessments address integration of QA
with ISM - Idaho audit report ISM integral part
- 2004-1 Implementation Plan
- Oversight Manual
- Generic QA Assessment plan provided to the team
- QAP and ISM System Descriptions
9Quality Assurance Analysis
- ORPS data was evaluated to develop QA performance
information - 4 existing ORPS cause code categories used
- Design/Engineering
- Equipment/Material
- Communications
- Training
- Developing a baseline of QA performance
information.
10Quality Assurance Analysis
Preliminary Assessment Results
11QA Oversight and Assessment
- HEPA Filter Test Facility Relocation
- Contract for FY05, options to extend for FY06,
07, 08 - Contract requires a QAP
- Old facility shut down
- Construction oversight
- Pre-shipment of filters June 20
- Startup audit to be conducted
- Resume operations in July
- EH assumes responsibility in FY06
- EH published semi-annual FTF Report - May 25,
2005
12QA Implementation Assessments
Calendar Year 2005
13Quality Assurance Leadership
- Technical Codes Standards leadership
- NQA-1 Executive Committee Member
- Applications Subcommittee Chair
- ISO 9001, U.S. Technical Advisory Group
Technical Committee 176 ASQ Z-1 Committee - IAEA Safety Requirements on Management Systems
- IEEE, Software Systems Engineering Standards
Exec. Committee (DOE Liaison) - ANS 10.4 Standards Committee
- ASME AG-1 Nuclear Air and Gas Treatment
Committee - NIST Council of Ionizing Radiation Measurements
Standards - ANSI N13 Accreditation Committee Member