LC Test Beam Activities - PowerPoint PPT Presentation

1 / 7
About This Presentation
Title:

LC Test Beam Activities

Description:

Consists of standalone runs as well as combined runs. Sent a letter to FNAL directorate ... TCMT will complete construction in Spring and will move to CERN for beam ... – PowerPoint PPT presentation

Number of Views:15
Avg rating:3.0/5.0
Slides: 8
Provided by: jae585
Learn more at: http://nicadd.niu.edu
Category:

less

Transcript and Presenter's Notes

Title: LC Test Beam Activities


1
LC Test Beam Activities
  • ALCPG Calorimeter Meeting
  • Feb. 27, 2006
  • Jae Yu
  • Facility updates
  • Current activities
  • ASIAN ECAL and CALICE
  • Upcoming activities in NA
  • Conclusions

2
Facilities Update
  • FNAL
  • MTBF is offered to a few existing programs,
    including three ILC related ones
  • FNAL Shutdown has begun as of Feb. 24 through
    Feb. 26
  • Supposed to last for 14 weeks till end of June
  • An upgrade plan after the shutdown for
  • Improvement of secondary beam rate especially the
    low energy pions
  • Moving the target downstream
  • Improve power supplies for higher stability at
    low currents
  • MIPP not scheduled to run after the shutdown
  • MC Beam line has possibility to become available
    for beam testing
  • EUDET See Andys talk
  • Kicked off on Feb.15 17 at DESY
  • Will utilize DESY and CERN facilities
  • KEK facility has been shutdown end of 2005 as
    planned.
  • No plans for beam test facilities in the
    foreseeable future

3
Current Activities
  • FNAL-MTBF
  • T955 ANLIU RPC Chamber testing
  • Completed initial run ? See Leis talk for
    details
  • Began beam exposure in the week of 2/6/06 and
    lasted till the beginning of the shutdown,
    2/24/06
  • Used 120GeV/c protons in 4 sec spill every 2 min
  • Rates varied from 1000 80k particles/spill
  • Translates to about 250 20k Hz
  • Exposed to beam for 2 4 days
  • Tested total of 3 chambers
  • 1 w/ 32 and 2 with 64 channels each
  • Hits in 2 64 channel chambers can be correlated
  • Need to include Cerenkov and trigger scintillator
    information into the data stream

4
Current Activities
  • FNAL-MTBF
  • T956 FNALIndUWSU, Scintillator muons
  • Was to begin before the shutdown and to last 1
    2 weeks
  • Tests 4 planes of 2.5mx1.25m scintillator based
    detectors
  • Measures number of photo-electron yields
  • T957 NIU TCMT
  • One layer of the cassette has been exposed to
    beam at DESY fall 2005
  • About a week of beam exposure ? See Vishnus talk
    today
  • Will move to CERN
  • LBNL Radiation facility
  • LBNL Vertex group using the facility for initial
    detector testing

5
ASICAN ECAL and CALICE
  • ASIAN Scintillator-Tungsten ECAL
  • Still plans to come end 2006 or early 2007 to
    FNAL
  • CALICE
  • SiW ECAL, AHCAL and TCMT construction in progress
  • Anticipated to complete the construction by
    mid-spring
  • MOU Submitted to CERN for two months of beam time
  • July end of Oct. 2006
  • Will test SiW ECAL, Scintillator-Steel AHCAL and
    the TCMT
  • Consists of standalone runs as well as combined
    runs
  • Sent a letter to FNAL directorate
  • Plan to come to FNAL early 2007 for more detailed
    tests of the prototypes
  • Requests extended low energy hadron beam to 1
    3GeV
  • Requests Increased duty factor from current 5 to
    10 or higher

6
Upcoming Activities - NA
  • CAL
  • GEM DHCAL
  • One plane of 30cmx30cm to be exposed to low
    energy (lt10MeV) electron beams in KAERI, Korea,
    late May, 2006, for chamber characterization and
    rate testing
  • The chamber will then be moved to MTBF for hadron
    beam exposure after the shutdown, July 2006
  • Will need to start working on MOU to FNAL
  • RPC will construct a few layer prototype module
    (slice) and expose to beam at MTBF after the
    current shutdown
  • This will utilize the FE readout using the DCAL
    chip in Nov.
  • TCMT will complete construction in Spring and
    will move to CERN for beam exposure as part of
    CALICE test stack
  • Tracking
  • No activities planned in the foreseeable future
  • Vertex
  • LBNL Vertex group will need pion beams in late
    2007 or early 2008
  • E_pigt5GeV needed for a few days
  • Investigating possibilities of using EUDET
    facility at CERN

7
Conclusions
  • US Calorimeter activities picking up momentum
  • Several groups have already taken runs at MTBF
  • With many coming in later this year
  • CALICE will conduct its initial run at CERN then
    will move to FNAL
  • Tracking and vertex activities lower than cal but
    imagine to pick up speed soon
  • Having EUDET will help alleviate anticipated
    large TB demand
  • Hope to have US funding to significantly improve
  • Funds for ECAL and 1m3 DHCAL prototypes needed
Write a Comment
User Comments (0)
About PowerShow.com