Effective Project Management Part II - PowerPoint PPT Presentation

1 / 72
About This Presentation
Title:

Effective Project Management Part II

Description:

A hierarchical description of the work as defined in the Project Overview statement ... Don't get bogged down in minutia. 18. Determining Resource Requirements ... – PowerPoint PPT presentation

Number of Views:74
Avg rating:3.0/5.0
Slides: 73
Provided by: roger113
Category:

less

Transcript and Presenter's Notes

Title: Effective Project Management Part II


1
Effective Project ManagementPart II
  • CST 332/407
  • Roosevelt University
  • Roger Clery

2
Chapter 4Identifying Project Activities
3
The Work Breakdown Structure
  • A hierarchical description of the work as defined
    in the Project Overview statement

4
Uses for the Work Breakdown Structure WBS
  • As a tool for
  • Thought process
  • Design
  • Planning
  • Reporting

5
Generating the WBS
  • Top-Down Approach
  • Bottom-Up Approach
  • WBS for Small Projects
  • Intermediate WBS for Large Projects

6
Six Criteria to Test for Completeness in the WBS
  • Measurable Status
  • Bounded
  • Deliverable
  • Cost/Time Estimate
  • Acceptable Duration Limits
  • Activity Independence

7
Using a Joint Project Planning Session to Build
the WBS
  • Decide on first level decomposition of goal
    statement
  • Then
  • Use whole planning team to complete the WMS
  • Divide into groups each group do part

8
Approaches to Building the WBS
  • Noun-Type Approaches
  • Verb-Type Approaches
  • Organizational Approaches

9
Representing the WBS
10
Representing the WBS
11
Chapter 5Estimating Duration, Resource
Requirements, and Cost
12
Elapsed time versus work time
13
Estimating Duration
  • Resource Loading versus Activity Duration
  • Variation in Activity Duration
  • Six Methods for Estimating Activity Duration
  • Estimation Precision

14
Estimating Resource Requirements
  • People as Resources
  • Resource Breakdown Structure

15
Estimating Duration as a Function of Resource
Availability
  • Assign as a Total Work and a Constant Percent/Day
  • Assign as a Duration and Total Work Effort
  • Assign as a Duration and Percent/Day
  • Assign as a Profile

16
Estimating Cost
  • Resource Planning
  • Cost Estimating
  • Cost Budgeting
  • Cost Control

17
Using a JPP Session to Estimate Duration,Resource
Requirements, and Cost
  • Get it roughly right
  • Spend more time on front end activities
  • Dont get bogged down in minutia

18
Determining Resource Requirements
  • Create a list do NOT list specific people only
    skills and skill levels
  • Use with the WBS

19
Determining Cost
20
Chapter 6Constructing and Analyzing the Project
Network Diagram
  • This material is covered in CST 331
  • GOTO PowerPoint Presentation

21
The Project Network Diagram
  • Envisioning a Complex Project Network Diagram
  • Benefits to Network-Based Scheduling

22
Building the Network Diagram Usingthe Precedence
Diagramming Method
  • Dependencies
  • Constraints
  • Using the Lag Variable
  • Creating an Initial Project Network Schedule

23
Analyzing the Initial Project Network Diagram
  • Compressing the Schedule
  • Management Reserve

24
Using the JPP Session to Constructand Analyze
the Network
25
Chapter 7Finalizing the Schedule and Cost Based
on Resource Availability
26
Considering Resource Availability
27
Leveling Resources
  • Over committing people
  • Changing priorities
  • No resource management
  • Employee turnover

28
Acceptably Leveled Schedule
  • Only 50 to 65 of time can be used for work
  • Where does the rest of the time go?
  • Donuts!

29
Resource-Leveling Strategies
  • Utilizing Available Slack
  • Shifting the Project Finish Date
  • Smoothing
  • Alternative Methods of Scheduling Activities

30
Cost Impact of Resource Leveling
  • Who pays?
  • How is project billed?
  • Incentive / penalties for completion?

31
Implementing Micro-Level Project Planning
32
Work Packages
  • Purpose of a Work Package
  • Format of a Work Package

33
Chapter 8Organizing and Conducting the Joint
ProjectPlanning Session
34
MEETINGS
35
Joint Project Planning Sessions
  • Planning the JPP Session
  • Attendees
  • Facilities
  • Equipment
  • The Complete Planning Agenda
  • Deliverables

36
Project ProposalContents of the Project Proposal
  • Background
  • Objective
  • Overview
  • Details of work
  • Time and Cost Summery
  • Appendix

37
Chapter 9Recruiting, Organizing, and Managing
the Project Team
38
Project Manager vis-a-vis the Functional Manager
39
Projects as Motivation and Development Tools
  • Motivators
  • Achievement
  • Recognition
  • Advancement and growth
  • Responsibility
  • Work itself
  • Hygiene Factors
  • Company policy
  • Administrative practice
  • Working Conditions
  • Technical Supervision
  • Interpersonal relations
  • Job security
  • Salary

40
Recruiting the Project Team
  • The Project Manager
  • Core Team Members
  • Contracted Team Members

41
Organizing the Project Team
  • Authority
  • Responsibility
  • Balancing a Team
  • Developing a Team Deployment Strategy
  • Developing a Team Development Plan

42
Establishing Team Operating Rules
  • Situations Requiring Team Operating Rules
  • Problem Solving
  • Decision Making
  • Conflict Resolution
  • Consensus Building
  • Brainstorming
  • Team Meetings

43
Managing Team Communications
  • Managing Communications Timing, Content, and
    Channels

44
Managing Communication Beyond the Team
  • To the sponsor
  • Regularly
  • Filtering
  • Withholding
  • Dont stonewall with bad news, but be
    considerate/ empathetic

45
Chapter 10Monitoring and Controlling Progress
46
Control versus Risk
  • Purpose of Controls
  • High ControlLow Risk
  • Low ControlHigh Risk
  • Balancing the Control System

47
Control versus Quality
  • Quality will NOT happen by accident.

48
Progress Reporting System
  • Types of Project Status Reports
  • How and What Information to Update
  • Frequency of Gathering and Reporting
  • Project Progress
  • Variances
  • The planned number
  • The actual number
  • The difference ?

49
Five reasons to measure variance
  • Catch deviations early
  • Dampen oscillations
  • Allow early corrective action
  • Determine weekly schedule variance
  • Determine effort variance

50
Applying Graphical Reporting Tools
  • Gantt Charts
  • Milestone Trend Charts
  • Cost Schedule Control
  • Using the WBS to Report Project Status

51
Deciding on Report Level of Detail
  • Activity Manager
  • Project Manager
  • Senior Management

52
Managing Project Status Meetings
  • Who Should Attend?
  • When Are They Held?
  • What Is Their Purpose?
  • What Is Their Format?

53
Managing Change
  • Every change is significant
  • Document with project change request
  • Project impact statement
  • Six outcomes
  • Yes more time
  • Yes more money
  • Yes more time and money
  • Yes
  • Next version
  • No

54
Managing Problem Escalation
55
The Escalation Strategy Hierarchy
  • Use existing resources
  • Get more resources
  • Last resort, appeal to the customer /sponsor

56
Problem Management Meetings
57
Chapter 11Closing Out the Projects
58
Steps in Closing a Project
  • Getting clients acceptance of deliverables
  • Ensuring that all deliverables are installed
  • Ensuring that the documentation is in place
  • Getting Client sign-off on final report
  • Conducting post-implementation audit
  • Celebrating the success

59
Getting Client Acceptance
  • Ceremonial Acceptance
  • Formal Acceptance

60
Installing Project Deliverables
61
Documenting the Project
62
Post-Implementation Audit
63
The Final Report
64
Celebrating Success
65
Chapter 12Critical Chain Project Management
66
What Is the Critical Chain?
67
Variation in Duration Common Cause versus
Special Cause
68
Statistical Validation of the Critical Chain
Approach
69
The Critical Chain Project Management Approach
  • Step 1 Creating the Early Schedule Project
    Network Diagram
  • Step 2 Converting the Early Schedule to the Late
    Scheduleand Adding Resources
  • Step 3 Resolving Resource Conflicts

70
Buffers
  • Defining Buffers
  • Types of Buffers
  • Using Buffers
  • Managing Buffers

71
Track Record of Critical Chain Project Management

72
END
Write a Comment
User Comments (0)
About PowerShow.com