Underground Lab Design - PowerPoint PPT Presentation

1 / 54
About This Presentation
Title:

Underground Lab Design

Description:

Large rectangular experimental hall and support spaces. ... Cubicle. Farm. Surface Facility: Level 3. Surface Facility: Level 3. Experiment. Control Rooms ... – PowerPoint PPT presentation

Number of Views:89
Avg rating:3.0/5.0
Slides: 55
Provided by: sno7
Category:

less

Transcript and Presenter's Notes

Title: Underground Lab Design


1
  • Underground Lab Design
  • Surface Facility
  • Infrastructure
  • Schedule

2
  • Underground
  • Space for 10-100 tonne class experiment(s)
  • Space for several 1 tonne class experiments
  • Prototyping space
  • Clean machine shop
  • Clean storage
  • Surface
  • Clean lab space
  • Computing facilities
  • Office/meeting room space

3
  • Phase I
  • Large rectangular experimental hall and support
    spaces.
  • Network of connected drifts for smaller scale
    experiments.
  • Expansion of the personnel facilities for larger
    facility.
  • Phase II
  • Addition of a cylindrical cavity and support
    spaces designed specifically for cryogenic
    experiments.
  • Will Require Additional Funding

4
6800 Level
5
(No Transcript)
6
(No Transcript)
7
(No Transcript)
8
(No Transcript)
9
(No Transcript)
10
(No Transcript)
11
(No Transcript)
12
(No Transcript)
13
20 Bar Pressure Bulkhead
Staging Area
Vent Pipe to Return Air Raise
Dirty Access
20 Bar Pressure Bulkhead
14
  • South Drift
  • Recover the existing SNO Personnel Drift and
    Carwash.
  • SNO Detector Cavern
  • Future use of the SNO detector cavern beyond the
    end of the SNO experiment to be determined.

15
  • Large spaces located beyond the 5 zone of
    influence from mining.
  • Cavities designed for a 4.1 seismic event.
  • Peak Particle Velocity 400 mm/s (5 G
    acceleration).
  • Exploratory drilling was done to determine the
    optimal location for the lab.

16
  • Excavation Design and Geotechnical Studies are
    complete.
  • Excavation of Phase I should begin August 2004.
  • Detailed layout design (civil, mechanical,
    electrical, ...) progressing.

17
  • Lessons Learned from Existing SNO Surface
    Facility
  • Require clean lab space.
  • Areas to prepare material for clean transport
    underground.
  • Adequate computing facilities.
  • Sufficient Dry (Change Room) facilities.
  • Office space for on site and visiting staff and
    researchers.

18
(No Transcript)
19
(No Transcript)
20
(No Transcript)
21
(No Transcript)
22
(No Transcript)
23
Change Rooms - 100 Male - 50 Female
24
(No Transcript)
25
(No Transcript)
26
(No Transcript)
27
(No Transcript)
28
(No Transcript)
29
(No Transcript)
30
(No Transcript)
31
  • Construction has begun.
  • Occupancy in May 2005.

32
  • Cleanliness
  • Power
  • Emergency Power
  • Heat Removal
  • Communications
  • Personnel Access
  • Material Transportation

33
  • Existing SNO facility is class 2000
  • Goal for new facility is to be as good or better.
  • Air from labs will be locally recirculated
    through HEPA filters.
  • Problem with H2S identified in existing lab.
  • Will use NaOH impregnated charcoal filters on lab
    air intake.

34
(No Transcript)
35
  • Existing SNO Facility uses 340 kW
  • New facility expected to use approximately 600
    700 kW in Phase I.
  • 150 kW emergency power generator will be located
    near the Chiller.
  • Increase to 1 MW should be possible without
    major effort.
  • Limiting Factor is likely to be available cooling.

36
Hot Waste Air
37
  • 100,000 CFM available from INCO.
  • Air Cooled Chiller
  • Chilled water loop to lab.
  • Up to 300 ton (1 MW) capacity.

38
(No Transcript)
39
  • 300 Ton chiller capacity should be considered an
    upper limit.
  • The existing chiller (120 Ton) is operated at
    80 capacity.
  • Budgeting heat loads for experiments will be a
    key part of experimental design for SNOLAB.

40
(No Transcript)
41
  • Clean transport underground in Blue Boxes.
  • Sealed on surface with pressure equalized by
    HEPA filters during descent to 6800 level.
  • Dimensions 140x68x44.
  • However, the Blue Boxes will be redesigned and
    the dimensions may change.

42
(No Transcript)
43
(No Transcript)
44
(No Transcript)
45
(No Transcript)
46
(No Transcript)
47
  • Personnel travel to and from the lab at fixed
    times.
  • Number of personnel on a cage can be limited.
  • Access may not be possible if there is seismic
    activity or hoist maintenance.

48
  • Maximize performance of Chiller.
  • Removing equipment heat while on emergency power.
  • Radon free air for low background Counting
    facility.
  • LN2 plant UG (radon free nitrogen).
  • Lifting devices in clean spaces (monorail vs
    bridge cranes,...).
  • Quantify seismic activity at lab site.

49
  • Layout of internal lab spaces.
  • Power requirements.
  • Average loads
  • Peak loads
  • Emergency power
  • Heat removal requirements.
  • Material transport
  • Construction, Operations
  • Personnel Access

50
  • Power Outages
  • Summer lightening season.
  • Winter ice season.
  • Accidental interruptions from INCO activities.
  • Annual INCO 12 hour power outage (November 11)
  • Maybe 2-3 12 hour outages per year and many
    blinks and short outages.
  • Loss of communications
  • Damage to fibre optics communications lines
    underground.
  • Failure of network components.
  • No access underground
  • Cage unavailable
  • Annual INCO shut down (several weeks, limited
    access)
  • Seismic activity.

51
  • Redundant communications
  • Minimize single point failures
  • Maximize remote control of experiment
  • Control and monitoring.
  • Shut down, start up
  • Where possible design systems to run without
    intervention from surface.
  • Systems underground must be able to run
    independently of surface
  • I.e. With operators underground.
  • Systems should fail safe.
  • E.g. In the event of communications failure
    systems should go to a safe state.
  • Be aware of the seismic environment.

52
(No Transcript)
53
  • The new SNOLAB facilities will include
  • 30,000 sq ft of new clean room space underground.
  • 34,000 sq ft lab, office and meeting space on
    surface.
  • Surface facility under construction.
  • Excavation of new labs to start in August.
  • First experimental space available early 2006.
  • Main hall and labs available late 2006.

54
(No Transcript)
Write a Comment
User Comments (0)
About PowerShow.com