UNEXPECTED PROJECT COSTS THE COST OF CONSTRUCTION ON CAMPUS - PowerPoint PPT Presentation

1 / 24
About This Presentation
Title:

UNEXPECTED PROJECT COSTS THE COST OF CONSTRUCTION ON CAMPUS

Description:

UNEXPECTED PROJECT COSTS. THE COST OF CONSTRUCTION ON CAMPUS. YOUR HOUSE ON CAMPUS ... have areas to set dumpsters, Construction and Demolition must be hauled away ... – PowerPoint PPT presentation

Number of Views:27
Avg rating:3.0/5.0
Slides: 25
Provided by: lice193
Category:

less

Transcript and Presenter's Notes

Title: UNEXPECTED PROJECT COSTS THE COST OF CONSTRUCTION ON CAMPUS


1
UNEXPECTED PROJECT COSTSTHE COST OF
CONSTRUCTION ON CAMPUS
2
(No Transcript)
3
YOUR HOUSE ON CAMPUSDon Guckert Geri
KingUniversity of Iowa
  • Safe
  • Accessible
  • Elevator
  • Exit Stairs
  • Aesthetics
  • Wider Hallways
  • Widen Stairways
  • Utility Chase
  • Fire Alarm Panel
  • Wired Fire Sensors
  • Sprinkler System
  • Fire Rated Walls
  • Solid Core (Rated) Doors

4
YOUR HOUSE ON CAMPUSDon Guckert Geri
KingUniversity of Iowa
  • Hollow Metal Frames
  • Outside Air Ventilation
  • Redundant Mechanical Systems
  • Dependable Mechanical Systems
  • Cost Effective Mechanical Systems
  • Additional Weight
  • Circulating Hot Water
  • Sound Attenuation Devices (HVAC)
  • Commercial Grade Windows with Energy Efficient
    Glazing

5
Age of our facilities
  • Inadequate infrastructure to support current
    electrical demands
  • Inadequate infrastructure to support current
    cooling loads
  • Inadequate infrastructure to support current data
    requirements
  • Infrastructure failures (piping, valves, )
  • Hidden code violations
  • Higher costs to match existing

6
Regulatory Agencies
  • University inspectors
  • BCCFS (Bureau of Construction Codes and Fire
    Safety)
  • Factory Mutual
  • Michigan Department of Public Health
  • Certified piping systems for Medical Gas
    installations
  • OSEH/MIOSHA

7
Code Regulations
  • Areas being renovated sometime trigger compliance
    with new building codes. For example a customer
    may wish to add in an emergency generator to
    power up certain equipment in a facility. Code
    may require that building components such as
    elevators and alarms be connected to emergency
    power.
  • Contractors may (will) find conduit in a
    renovated area that is not properly supported
  • Contractors may (will) find communication in a
    renovated area that is not run in conduit

8
Environmental Issues
  • Collection and disposal of fluorescent light
    tubes
  • Collection and disposal of lighting ballasts

9
University Standards
  • Floor penetrations require double core, sleeve,
    and fire stopping with UL approved systems
  • Mechanical specifications require materials that
    have higher initial costs, but lower life cycle
    cost
  • Facilities contain rated structures that require
    the fire stopping of all penetrations
  • Many standards for the University are more
    stringent than industry standards resulting in
    more costly materials and longer delivery times

10
University Standards

11
Demolition Surprises
  • Materials may be uncovered that are not in good
    working condition (plumbing pipes)
  • Materials may be found in walls that was not as
    expected
  • Demolition may uncover prior renovation work that
    was not expected
  • Demolition may find concrete slabs and walls that
    are thicker than expected or that are thinner
    than expected (example West Hall Colloquium room)

12
Pests
  • Bugs
  • Termites
  • Bees

13
Complexity of the work(ExampleMoving a
sprinkler head)
  • Turn off fire alarm system notify Factory Mutual
  • Drain system (may be 5-6 floors of piping)
  • Move sprinkler head (Certified contractors
    required for buildings under the jurisdiction of
    the BCCFS)
  • Fill system
  • Energize alarm system

14
Safety
  • Asbestos flooring, insulation, plaster,..
  • Lead based paint
  • Drilling a hole may require removal of carpet and
    VAT to drill one hole
  • Proper safety procedures must be followed at all
    times (Harnesses, Scaffolding requirements)

15
Interim Life Safety Requirements(Patient Care
Facilities)
  • Conversion of space to negative pressure
  • Visqueen enclosures
  • Walk off mats
  • HEPA filtration devices

16
Access
  • Buildings (poor loading docks)
  • Small elevators (carry materials up stairs or
    ride top of elevator)
  • Long distances from Dock to work area for
    delivery of material
  • Long distances from Dock to work area for removal
    of trash

17
Access
  • Few buildings have areas to set dumpsters,
    Construction and Demolition must be hauled away
  • Areas above ceilings are crowded and often times
    difficult to access and work in
  • Access may require specialized lifts that can get
    through the doors and to the work area required
  • Parking

18
Materials
  • Manufacturers materials change over time. For
    Example Wiremold being installed in current
    construction projects has been dropped from the
    standard line and is only available by special
    order

19
Customer Requirements
  • Noisy activities often result in project shut
    down.
  • Utility shut-down may be required on off hours or
    weekends to lessen impact on normal operations
  • Class schedules limit access to rooms
  • Projects are often compressed to lessen impact on
    customers

20
Engineering Costs
  • Complex solutions require mechanical and
    electrical design assistance
  • BCCFS projects over 15,000 require designs
    prepared by AES

21
Balancing Requirements
  • Air Balance
  • Water Balance

22
After the Project.
  • Additional work by occupant
  • Fit Out
  • Laboratory Equipment Hook up
  • Holes in Counter
  • Furniture Hook-up

23
(No Transcript)
24
Questions?
Write a Comment
User Comments (0)
About PowerShow.com