FINANCIAL ASPECTS OF PROJECT ENGINEERING AND CONTRACTING - PowerPoint PPT Presentation

1 / 21
About This Presentation
Title:

FINANCIAL ASPECTS OF PROJECT ENGINEERING AND CONTRACTING

Description:

the ability of the specification writer to define unequivocally what is required ... 'It's unwise to pay too much, but it's even more unwise to pay too little. ... – PowerPoint PPT presentation

Number of Views:43
Avg rating:3.0/5.0
Slides: 22
Provided by: richar487
Category:

less

Transcript and Presenter's Notes

Title: FINANCIAL ASPECTS OF PROJECT ENGINEERING AND CONTRACTING


1
FINANCIAL ASPECTS OF PROJECT ENGINEERING AND
CONTRACTING
PRICING CONTRACTS AND PROPOSALS
  • Richard Hill

2
Competitve Tendering
  • Purchasers invitation
  • tender document
  • specification
  • Contractors offer
  • proposal
  • how the requirements of the specification will be
    met
  • Purchasers acceptance

3
Competitve Tendering
  • Shortcomings
  • the ability of the specification writer to define
    unequivocally what is required
  • the ability of the tenderer to design and cost
    the work accurately in the time available
  • the ability of the proposal writer to define is
    being offered

4
Deciding to Bid
  • Is there an order to be placed?
  • Do we know the Purchaser?
  • Can we do the job?
  • Have we done it before?
  • Can we meet the programme?
  • Who is the competition?
  • What is the Specification?
  • Do we have a USP?
  • Are conditions of contract acceptable?
  • Are there penalties?
  • Can we make any money?

5
Proposal Team
  • Proposal Manager
  • process
  • control instrumentation
  • mechanical
  • electrical
  • civil
  • CAD draughtsmen
  • estimators
  • planners
  • secretarial

6
Proposal Team
  • conceptual
  • creative
  • innovative
  • estimate
  • inspirational
  • intense
  • detailed
  • pedantic
  • specific
  • precise
  • methodical
  • perseverance

PROPOSAL MANAGER
CONTRACT MANAGER
7
TENDER DESIGN
  • Compliant bid
  • design data
  • process design/optimisation
  • equipment schedules
  • equipment data sheets
  • Alternative bid
  • Quality Assurance

8
TENDER PRICE
  • Cost Estimate
  • price make-up
  • Market intelligence
  • competition
  • purchasers budget
  • Business plan
  • work in progress
  • resource requirements
  • financing implications

9
The Price of the Contract
  • A blind guess carried out to seven significant
    figures ?
  • Cost, price and value all mean different things
    but are expressed in the same contract price
  • Contracting is a competitive business and, all
    other things being equal, purchasers generally
    place contracts with the lowest bidder
  • So, just as in the supermarket or the petrol
    station, the lowest price gets the order
  • Too high a price means that the company doesnt
    win any contracts cannot cover its overheads
  • Too low a price means that the contribution is
    too low to cover the overheads
  • Either way, the company will fail.

10
The Price of the Contract
"It's unwise to pay too much, but it's even more
unwise to pay too little. When you pay too much,
you lose a little money. That is all. When you
pay too little, you sometimes lose everything,
because the item you bought was incapable of
doing the thing that you bought it to do.The
common law of business prohibits paying a little
and getting a lot. It can't be done. If you deal
with the lowest bidder, it's as well to add
something for the risk you run. And if you do
that, you will probably have enough to pay for
something better"John Ruskin 1819 - 1900
11
Competition
  • Contracting is highly competitive because it
    takes relatively little capital to start trading.
  • Profitability (ie profit as a percentage of
    turnover) is low
  • Potential return on capital is high
  • Low profitability means that the margin for error
    is small
  • Contracts can easily swing into loss - it only
    takes one or two bad contracts to break a company
  • No two contracts are the same site conditions,
    labour conditions, weather etc all have an effect
  • By comparison manufacturing takes place in a more
    controlled environment which makes costing simpler

12
Competition
  • In a competitive tendering situation the contract
    which is let to the lowest tenderer is let to the
    contractor who made the biggest error in his
    estimate
  • Every major project is being built by a
    contractor who hasnt got enough money to do it
    properly.

13
Making up the Price
  • When a contractor receives an enquiry from a
    purchaser there is a limited, and usually short,
    period in which he has to submit his price.
  • During that time (typically six to twelve weeks)
    the contractors Proposal Manager has to get a
    preliminary design prepared, estimate the
    materials and subcontract costs (usually called
    the bought out costs), the direct costs from
    his own cost centres and finally the contribution
    calculated in the years business plan
  • This will all be set out in a Price Make-Up
    Sheet
  • This is a very important document because it not
    only shows how the tender price was arrived at
    but, if the company wins the contract, it will be
    the basis of the Contract Managers budget and
    cash flow forecasts

14
Making up the Price
15
Making up the Price
  • All the equipment and materials that will be
    purchased for the contracts concrete,
    shuttering, steelwork, pumps, pipes, specialist
    machinery etc.
  • Packages of work that will be carried out by
    other companies on site as opposed to direct
    labour employed by the contractor. Typically this
    might include piling, scaffolding, equipment
    installation, electrical cabling, painting and
    similar activities.
  • Engineering is estimated on the basis of company
    experience with cost per man-hour arrived at by
    considering the engineering department as a cost
    centre.
  • Contract management and other direct costs are
    estimated in much the same way.

16
Making up the Price
  • Site costs vary from contract to contract
    design can save money for example prefabrication
    off site might mean the difference between having
    an expensive tower crane on site for months and
    having a mobile crane on site for days.
  • At the tender stage, the Proposal Manager will
    prepare a cash flow forecast and an S curve for
    the contract so as to be able to estimate how
    much money will have to be borrowed and how much
    interest is attributable to the contract.
  • In overseas contracting it is quite usual to have
    an agent (an individual or a company) who knows
    the local situation and has good contacts within
    the purchasers company so his help may be
    invaluable in winning the contract
  • In some specialist sectors, contractors might be
    using technology that they have obtained under a
    licence agreement, and they have to pay a licence
    fee or royalty to the owner of the technology.

17
Making up the Price
  • Contractors normally carry a Contractors All
    Risk insurance that covers them for damage or
    injury to staff, subcontractors and third parties
    as well as for mistakes in the design and
    consequential losses. Sometimes they need to take
    up additionalspecial insurances
  • The total direct costs of the contract.
  • The contribution may be the straightforward
    number calculated in the years business plan or
    it may be higher if the contractor is confident
    of winning the contract or lower if he wants to
    be sure of getting it.
  • The price may include a contingency to reflect a
    particular type of risk or liquidated damages in
    the contract or to provide a negotiating margin
    for the salesman to give as a discount
  • And there it is the Contract Price well
    almost.
  • Note that profit isn't mentioned anywhere - a
    single contract makes no profit

18
Finalising the price
  • Other factors influence the price but are not
    quantifiable are discussed at the Price
    Settlement Meeting
  • Competition
  • Does the purchaser have a budget limitation?
  • Does the purchaser have a particular preference?
  • Which other contractors are tendering?
  • Reasons for wanting to win a particular contract
    which justify a low price
  • Particularly onerous conditions of contract may
    require special contingencies to be added.
  • Weighing up all these factors will usually lead
    to an adjustment to the calculated price
  • A blind guess carried out to seven significant
    figures

19
Tender costs
  • Preparing tenders is a costly process
  • Although the tender stage design is not fully
    detailed, it will take a full team of discipline
    engineers process, mechanical, electrical and
    civil as well as planners, estimators,
    architects and draughtsmen.
  • A typical 2.2m tender might cost 20,000 to
    prepare thats 1 of the contract price, and
    that cost is part of the contractors overheads.
  • Most ontractors expect to win one tender in four
    and get no payment for the work which goes into
    the other three

20
Proposal Submission
  • Submission date/time
  • Format
  • Presentation
  • The written word
  • Spin

21
Summary
  • Many items go into working out a contract price.
  • We try to minimise uncertainty with cost centres
    and so on, but much remains a best guess.
  • With thin profit margins, small errors make a big
    difference to profitability.
  • The proposal document has to sell the
    contractors capabilities and design
Write a Comment
User Comments (0)
About PowerShow.com