Title: FINANCIAL ASPECTS OF PROJECT ENGINEERING AND CONTRACTING
1FINANCIAL ASPECTS OF PROJECT ENGINEERING AND
CONTRACTING
PRICING CONTRACTS AND PROPOSALS
2Competitve Tendering
- Purchasers invitation
- tender document
- specification
- Contractors offer
- proposal
- how the requirements of the specification will be
met - Purchasers acceptance
3Competitve Tendering
- Shortcomings
- the ability of the specification writer to define
unequivocally what is required - the ability of the tenderer to design and cost
the work accurately in the time available - the ability of the proposal writer to define is
being offered
4Deciding to Bid
- Is there an order to be placed?
- Do we know the Purchaser?
- Can we do the job?
- Have we done it before?
- Can we meet the programme?
- Who is the competition?
- What is the Specification?
- Do we have a USP?
- Are conditions of contract acceptable?
- Are there penalties?
- Can we make any money?
5Proposal Team
- Proposal Manager
- process
- control instrumentation
- mechanical
- electrical
- civil
- CAD draughtsmen
- estimators
- planners
- secretarial
6Proposal Team
- conceptual
- creative
- innovative
- estimate
- inspirational
- intense
- detailed
- pedantic
- specific
- precise
- methodical
- perseverance
PROPOSAL MANAGER
CONTRACT MANAGER
7TENDER DESIGN
- Compliant bid
- design data
- process design/optimisation
- equipment schedules
- equipment data sheets
- Alternative bid
- Quality Assurance
8TENDER PRICE
- Cost Estimate
- price make-up
- Market intelligence
- competition
- purchasers budget
- Business plan
- work in progress
- resource requirements
- financing implications
9The Price of the Contract
- A blind guess carried out to seven significant
figures ? - Cost, price and value all mean different things
but are expressed in the same contract price - Contracting is a competitive business and, all
other things being equal, purchasers generally
place contracts with the lowest bidder - So, just as in the supermarket or the petrol
station, the lowest price gets the order - Too high a price means that the company doesnt
win any contracts cannot cover its overheads - Too low a price means that the contribution is
too low to cover the overheads - Either way, the company will fail.
10The Price of the Contract
"It's unwise to pay too much, but it's even more
unwise to pay too little. When you pay too much,
you lose a little money. That is all. When you
pay too little, you sometimes lose everything,
because the item you bought was incapable of
doing the thing that you bought it to do.The
common law of business prohibits paying a little
and getting a lot. It can't be done. If you deal
with the lowest bidder, it's as well to add
something for the risk you run. And if you do
that, you will probably have enough to pay for
something better"John Ruskin 1819 - 1900
11Competition
- Contracting is highly competitive because it
takes relatively little capital to start trading.
- Profitability (ie profit as a percentage of
turnover) is low - Potential return on capital is high
- Low profitability means that the margin for error
is small - Contracts can easily swing into loss - it only
takes one or two bad contracts to break a company
- No two contracts are the same site conditions,
labour conditions, weather etc all have an effect - By comparison manufacturing takes place in a more
controlled environment which makes costing simpler
12Competition
- In a competitive tendering situation the contract
which is let to the lowest tenderer is let to the
contractor who made the biggest error in his
estimate - Every major project is being built by a
contractor who hasnt got enough money to do it
properly.
13Making up the Price
- When a contractor receives an enquiry from a
purchaser there is a limited, and usually short,
period in which he has to submit his price. - During that time (typically six to twelve weeks)
the contractors Proposal Manager has to get a
preliminary design prepared, estimate the
materials and subcontract costs (usually called
the bought out costs), the direct costs from
his own cost centres and finally the contribution
calculated in the years business plan - This will all be set out in a Price Make-Up
Sheet - This is a very important document because it not
only shows how the tender price was arrived at
but, if the company wins the contract, it will be
the basis of the Contract Managers budget and
cash flow forecasts
14Making up the Price
15Making up the Price
- All the equipment and materials that will be
purchased for the contracts concrete,
shuttering, steelwork, pumps, pipes, specialist
machinery etc. - Packages of work that will be carried out by
other companies on site as opposed to direct
labour employed by the contractor. Typically this
might include piling, scaffolding, equipment
installation, electrical cabling, painting and
similar activities. - Engineering is estimated on the basis of company
experience with cost per man-hour arrived at by
considering the engineering department as a cost
centre. - Contract management and other direct costs are
estimated in much the same way.
16Making up the Price
- Site costs vary from contract to contract
design can save money for example prefabrication
off site might mean the difference between having
an expensive tower crane on site for months and
having a mobile crane on site for days. - At the tender stage, the Proposal Manager will
prepare a cash flow forecast and an S curve for
the contract so as to be able to estimate how
much money will have to be borrowed and how much
interest is attributable to the contract. - In overseas contracting it is quite usual to have
an agent (an individual or a company) who knows
the local situation and has good contacts within
the purchasers company so his help may be
invaluable in winning the contract - In some specialist sectors, contractors might be
using technology that they have obtained under a
licence agreement, and they have to pay a licence
fee or royalty to the owner of the technology.
17Making up the Price
- Contractors normally carry a Contractors All
Risk insurance that covers them for damage or
injury to staff, subcontractors and third parties
as well as for mistakes in the design and
consequential losses. Sometimes they need to take
up additionalspecial insurances - The total direct costs of the contract.
- The contribution may be the straightforward
number calculated in the years business plan or
it may be higher if the contractor is confident
of winning the contract or lower if he wants to
be sure of getting it. - The price may include a contingency to reflect a
particular type of risk or liquidated damages in
the contract or to provide a negotiating margin
for the salesman to give as a discount - And there it is the Contract Price well
almost. - Note that profit isn't mentioned anywhere - a
single contract makes no profit
18Finalising the price
- Other factors influence the price but are not
quantifiable are discussed at the Price
Settlement Meeting - Competition
- Does the purchaser have a budget limitation?
- Does the purchaser have a particular preference?
- Which other contractors are tendering?
- Reasons for wanting to win a particular contract
which justify a low price - Particularly onerous conditions of contract may
require special contingencies to be added. - Weighing up all these factors will usually lead
to an adjustment to the calculated price - A blind guess carried out to seven significant
figures
19Tender costs
- Preparing tenders is a costly process
- Although the tender stage design is not fully
detailed, it will take a full team of discipline
engineers process, mechanical, electrical and
civil as well as planners, estimators,
architects and draughtsmen. - A typical 2.2m tender might cost 20,000 to
prepare thats 1 of the contract price, and
that cost is part of the contractors overheads. - Most ontractors expect to win one tender in four
and get no payment for the work which goes into
the other three
20Proposal Submission
- Submission date/time
- Format
- Presentation
- The written word
- Spin
21Summary
- Many items go into working out a contract price.
- We try to minimise uncertainty with cost centres
and so on, but much remains a best guess. - With thin profit margins, small errors make a big
difference to profitability. - The proposal document has to sell the
contractors capabilities and design