Title: Morupule Coalfired Power Generation Expansion Project
1Morupule Coal-fired Power Generation Expansion
Project
- By
- Chandapiwa Macheke
- Martha S. Kelesitse
2Introduction
- Country background information
- The project
3Country information
4Economic overview
5Economic growth of the country
6Political stability
- The Constitution of Botswana established a
nonracial democracy which maintains basic
freedoms.
- One party (BDP) has been in power since
independence.
- Elections occur regularly (every 5 years) with
many political parties (15) competing for
leadership.
7Botswana and the UNFCCC
- Party status UNFCCC January 1994
- Kyoto Protocol July 2004
- Reporting INC at COP-7 (2001 October)
- Projects
- US Country Study Programme
- Enabling Activity (350 000)
- Top Up (100 000)
- Preparation of TNA report
- Capacity building of relevant government
institutions, NCCC and DMS
8Brief overview of the TNA report cont
- Major findings
- Potential for EST in coal application and biogas
- Abundance of solar
- Wastewater from water treatment plants.
- Wind technologies
- Energy efficiency
- Treatment of brackish water
- Agricultural technologies
9Morupule Power Project
10Botswana Power Corporation
- Botswana Power Corporation (BPC) is wholly owned
by the Government of the Republic of Botswana.
- Utility was established by an Act of Parliament.
- BPC responsible for the generation, transmission
and distribution of electricity in Botswana.
11Project Background
- BPC currently owns and operates 132 MW
mine-mouth, dry cooled power plant at Morupule.
- Morupule Power Station is situated near Palapye,
in the Central District of Botswana.
12Morupule Power Station
13Project Background (cont..)
- Current system peak demand is 434 MW.
- Demand satisfied through internal generation at
Morupule ( net 120 MW) and imports.
- BPC has Power Purchase Agreement (PPA) with Eskom
which expires in Dec. 2007, for firm imports of
up to 410MW.
- The Southern African region faces diminishing
surplus generation capacity, which is expected to
be exhausted by 2007/10.
- BPC is an active member of Southern African Power
Pool (SAPP).
14Botswana National Grid
15Power Statistics
16Unit electricity sales by sector
17Current Tariff Structure
18Project Description
- BPC commissioned a generation expansion
feasibility study.
- Study recommended implementation of 400 MW by
2009/10, and a further 100 MW in 2018, and final
100 MW in 2023.
- The project will be accommodated within the
existing property at Morupule Power Stn.
19Project Description (cont..)
- As part of the feasibility, a coal resource
assessment was done.
- A 25 year mine plan developed indicated a
resource in the order of 150 million tones of
coal available. (national reserves 32 billion
tonnes total)
20Project Description (cont..)
- Nature of the coal is sub-bituminous with sulphur
content averaging 1.5 , ash content of 21,
moisture 4, and ave. CV of 23 MJ/kg.
- The base case for this project is conventional
pulverised coal-fired boilers with ESPs.
21Technical Aspects of the Project
- The project is intended to immediately generate
additional 400 MW from 4 x 100 MW units with a
design life of 25 years.
- The EIA scoping study for the project has been
completed.
- As a mitigation measure, the environmental
performance of the project could be improved
through use of cleaner coal technologies.
22Technical Aspects of the Project (cont.)
- We need technologies that reduce the quantities
of emissions (NOx, SO2, particulates) including
high efficiency technologies for coal to
electricity conversion process (reduction of CO2,
NOx). - Coal cleaning, low-NOx burners, scrubbers,
Electrostatic Precipitators.
- subcritical pulverised fuel, atmospheric
fluidised bed combustion.
23Finance/Economic Aspects of the Project
- The current legislative framework does not allow
direct private equity participation into BPC.
- BPC intends to finance the project partly through
equity, and balance through debt/grants.
- The project (400 MW) is planned as follows
- 2009 1st Phase 2 x 100 MW
- 2010 2nd Phase 2 x 100 MW
- Estimated cost of 4 x 100 MW units US600
million and unit cost of US1,500/kW.
- Expected year of project commencement 2006
24Finance/Economic Aspects (Cont)
- The cost estimate include capital and all soft
costs (project management costs, financial costs,
interest during construction.
- Employing high efficiency boilers or other
cleaner coal technologies, costs could range
US800-1000 million for 600 MW new capacity.
- The cost and access to these technologies is a
barrier.
25Finance/Economic Aspects
- The capital cost estimates, indicate that an
electricity price of US 2.75 c/kWh (BWP 13.75
thebe/kWh) at the power station busbar is
sufficient to cover the total cost of the
expanded power station over a 25-year design life
period. - Currently, the cost of generation stands at BWP
9.50 thebe/kWh (US 1.90 c/kWh) as compared to the
price of imports at BWP 11.50 thebe/kWh (US 2.30
c/kWh). - Indications are, expanding Morupule will have
smaller impact on tariffs than continued imports
from Eskom.
- Therefore, from an economic, financial and tariff
impact perspective, the project is feasible.
26Morupule Power Project
- Engineering, Procurement and Construction
Contracts
- Once contracts for owners engineer and financial
advisor in place, the procurement process for
civil, electromechanical contracts, etc will be
initiated - Big Question
- How can BPC Project benefit from UNFCCC
mechanisms?
- How the UNFCCC process can assist BPC in the
selection of the technological options?
27Thank you Cmacheke_at_gov.bw Kelesitses_at_bpc.bw h
ttp//www.bpc.bw
http//www.gov.bw