WP1 Experimentation and Validation - PowerPoint PPT Presentation

1 / 19
About This Presentation
Title:

WP1 Experimentation and Validation

Description:

... scale for the best identification and modelling of the ... Defining a protocol for the calibration of the TELEMAC system on a new plant. Normal functioning ... – PowerPoint PPT presentation

Number of Views:28
Avg rating:3.0/5.0
Slides: 20
Provided by: enriqu9
Category:

less

Transcript and Presenter's Notes

Title: WP1 Experimentation and Validation


1
WP1Experimentation and Validation
Review Meeting Brussels - 3 September 2002
  • Enrique RocaUSC
  • Enrique.Roca.Bordello_at_Xunta.es

2
General Objectives of WP1 (I)
  • Providing data at lab, pilot and industrial scale
    for the best identification and modelling of the
    process
  • Defining a protocol for the calibration of the
    TELEMAC system on a new plant

? Normal functioning
? Abnormal functioning
3
General Objectives of WP1 (II)
  • Validating the control and supervision system at
    lab, pilot and industrial scale
  • Evaluating the performances of the TELEMAC system

4
WP1 tasks and deliverables
T0
T06
T012
T018
T024
T030
T036
WP1.1 Optimal experiment design for modelling and
supervision set up
D1.1 Experimental protocol specifications to
reproduce normal and abnormal working conditions
WP1.2 Experiment running
WP1.3 System validation and result evaluation
5
WP1.1 Optimal experiment design for modelling
and supervision set up
6
WP1.1 Optimal experiment design for modelling
and supervision set up
  • Deliverable 1.1 completed in due time
  • (report written by USC, ENEA, AGRALCO,
  • SAUZA, DOMECQ UK, PSPc, INRA and INRIA)
  • Types of digesters to be used at lab and pilot
    scale with respect to what is done in the
    industry
  • Type of wastewater for lab and pilot scales,
  • Protocol for working conditions normal and
    abnormal operation,
  • Type of measurements (variables/sampling
    rates/precision),
  • Format of data base needed for the experiments.

7
WP1.1 Optimal experiment design for modelling
and supervision set up
? Type of digester
  • Lab scale UASB and CSTR (USC)
  • Pilot scale UASB (ENEA)
  • Preindustrial and industrial scale CSTR (Agralco
    and Domecq Sauza )

8
WP1.1 Optimal experiment design for modelling
and supervision set up
? Type of wastewater Industrial wastewater are
being used in all cases
  • Lab scale (USC)
  • Preindustrial and industrial scale (Agralco)

9
WP1.1 Optimal experiment design for modelling
and supervision set up
? Lab and pilot UASB protocol
Start-up and low load period
10
WP1.1 Optimal experiment design for modelling
and supervision set up
? Lab and pilot UASB protocol
Proposed reference load period
11
WP1.1 Optimal experiment design for modelling
and supervision set up
? Lab and pilot UASB protocol
High load period and final acidification
12
WP1.1 Optimal experiment design for modelling
and supervision set up
? Lab CSTR protocol
Proposed lab CSTR protocol
13
WP1.1 Optimal experiment design for modelling
and supervision set up
? Industrial CSTR protocol (Sauza and Agralco)
Proposed preindustrial and industrial CSTR
protocol
14
WP1.1 Optimal experiment design for modelling
and supervision set up
? Format of data base
  • Adequate and homogeneous format
  • Set of files
  • Measurements performed (length not fixed).
  • File type and content

agralco2-020121_12h45-vfa_dig-CODs_dig
  • Figures files quantitative records.
  • Text files.

15
WP1.2 Experiment running
16
WP1.2 Experiment running
  • A first version of Deliverable 1.3a completed in
    due time (report written by USC)
  • Data base of experimental data sets of lab scale
    (USC) experiments were supplied
  • Start-up and two organic overloads in CSTR.
  • Start-up of UASB
  • Previous data sets of lab, pilot and industrial
    scale processes were collected and supplied in an
    adequate format for modelling (Data from Agralco,
    INRA, Domecq Sauza, USC).
  • Pilot, preindustrial and industrial scale plants
    are starting up or ready (fully equipped and
    instrumented) (Agralco, ENEA and Domecq Sauza).

17
WP1.2 Experiment running
? Lab scale experiments
UASB
CSTR
18
WP1.2 Experiment running
? UASB lab scale
19
WP1.2 Experiment running
? UASB lab scale
20
WP1.2 Experiment running
? CSTR lab scale
21
WP1.2 Experiment running
? CSTR lab scale
22
WP1.2 Experiment running
? CSTR lab scale
23
WP1.2 Experiment running
? Pilot and pre-industrial plants
  • Pilot plant (ENEA) Start up phase.
  • The prototype version of the software for remote
    control and data acquisition of the pilot plant
    is ready (WP5).
  • Preindustrial plant
  • Agralco Ready
  • Sauza data since 2 years

Preindustrial PlantAgralco
24
WP1.2 Experiment running
? Full scale plants
  • - Agralco
  • It was under operation on summer
  • inhibition problem.
  • last 3 years data.
  • - Sauza
  • start-up 10/2002

Industrial PlantSauza
25
WP1 Efforts for the 1st project year
26
Plan for the next year
  • Further experimentation at lab scale (CSTR and
    UASB) according to the established protocols,
  • Development of pilot (UASB) and preindustrial
    (CSTR) scale experiments, D1.3b should be ready
    at t20,
  • Beginning of the experiments at industrial scale,
  • Developing a protocol for setting up TELEMAC
    system on a new plant, D1.2 must be ready at t24.