QUARTERLY IN POWER POINT - PowerPoint PPT Presentation

1 / 19
About This Presentation
Title:

QUARTERLY IN POWER POINT

Description:

Schedule to be presented to HQ / Code Y in mid-March. ... GLAS CPT only partially completed. Some problems under investigation. ... – PowerPoint PPT presentation

Number of Views:26
Avg rating:3.0/5.0
Slides: 20
Provided by: MTPE
Category:
Tags: point | power | quarterly | code | cpt

less

Transcript and Presenter's Notes

Title: QUARTERLY IN POWER POINT


1
MONTHLY STATUS REVIEW EOS ICE, CLOUD LAND
ELEVATION SATELLITE (ICESat) PROJECT Code
425 UPN 227-6 Project Scientist
Dr. J. Zwally / 971 Project
Manager James Watzin /
425 DPM / Resources
Linda Greenslade / 425 Instrument
Development Ron Follas / 556
Instrument Scientist Dr. J. Abshire /
924 Ground System Development ESDIS /
423 Spacecraft Contractor
Ball
April 9, 2002
2
ICESat PROJECT SUMMARY STATUS AS OF 3/31/ 02
Major Interfaces
Resources
Prime
JAN FEB MAR
JAN FEB MAR
Spacecraft Bus
JAN FEB MAR
R G G G
G G G G
G G G G
G G G G
G G G G
R G G G
G G G G G G
G G G G G G
G G G G G G
Launch Vehicle
Program Management
Launch Site (VAFB)
Subcontracts
Ground SYS / OPS (EOS)
Systems Engineering
JPL GPS Receivers
Subsystems
Spacecraft IT
Observatory IT
Science / Operations
Instruments
Business
JAN FEB MAR
JAN FEB MAR
JAN FEB MAR
Y G G G
Y
Y
GLAS
Y
R G G G
R G G G
RD Budget
G
G
G
GLAS
Procurement
Workforce
Travel
Summary Assessment
LEGEND
Technical Cost Schedule
Management Overall
Good Shape
G
G
Y
Y
G
Y
Minor Problem
Y
R
Major Problem
3
SCHEDULE ICESat Project STATUS AS OF 3/31/02
DATE ESTAB COMPL 10 / 15 11
/ 1 Closed 10 / 15 11 / 30 Test
removed issue closed 11 / 15 1 / 30
Closed 11/15 2/15 Complete
PROBLEM / ISSUES PROGRAMMATIC
IMPACT ACTION
G
  • Codes 400 and 500 are discussing ways to contain
    this problem
  • Expedite thermal performance evaluation of
    optical system
  • Conduct overall ICESat development and personnel
    assessment.
  • Develop revised mission schedule
  • Latest GLAS completion schedule causes impact to
    LRD.
  • GLAS component rework cycles continue to erode
    GLAS integration and test schedule longer GLAS
    integration effort needed
  • GLAS CPT only partially completed. Some problems
    under investigation. Instrument scientists
    struggling to interpret the data.
  • CURRENT STATUS
  • GLAS on proposed re-plan schedule for June 17
    delivery and subsequent 12/16 LRD. Schedule to
    be presented to HQ / Code Y in mid-March.
  • Launch manifest indicates NET 12/19/02 LRD
  • GLAS remains on schedule for June 17 delivery.
    Code Y PMC rescheduled for May 3. CLOSED

4
GLAS IT PROBLEMS IN WORK OPTICAL PATH ICESat
Project STATUS AS OF 3/31/02
DATE ESTAB COMPL 11/30
6/15
PROBLEM/ISSUES PROGRAMMATIC
IMPACT ACTION
Y
GLAS boresite stability does not meet mission
performance requirements
Fundamental measurements may be compromised if
behavior persists on orbit.
  • Hold mini-peer review on calibration results
  • Get AETD and systems involvement in development
    of troubleshooting plan.
  • CURRENT STATUS
  • Peer Review held
  • Retest conducted preliminary results look
    favorable with major errors traceable to set-up
    issues. Detailed data analysis results look
    promising.
  • Additional analysis initiated on the telescope
    assembly.
  • Test plan defined.
  • Plan in place to validate requires completion of
    environmental test program.

5
GLAS IT PROBLEMS IN WORK LIDAR OPERATION ICESat
Project STATUS AS OF 3/31/02
DATE ESTAB COMPL 12/17 6/15

PROBLEM/ISSUES PROGRAMMATIC
IMPACT ACTION
Y
Intermittent energy monitor on green laser
Potential compromise on Etalon operation and data
reduction
  • Investigate root cause
  • Investigate alternate means for Etalon operation
    and data reduction
  • CURRENT STATUS
  • Several troubleshooting tests conducted,
    inconclusive results.
  • Alternate Etalon operation algorithms in
    development.
  • Problem understood and board modification
    solution verified on the engineering model board.
    Alternative (baseline) software approaches being
    investigated and validated.
  • Software fix to be validated in T / V testing

6
COST ICESat Project STATUS AS OF 3/31/02
DATE ESTAB COMPL 7/ 01
11/15 Complete 11 / 01 2/28
Complete 4/02 6/02
PROBLEM / ISSUES PROGRAMMATIC
IMPACT ACTION
Y
  • Present overguide requirements to Code Y.
  • Generate cost / schedule impacts
  • Pursue budget approval through POP-02 process.
  • Cannot meet late 2002 LRD without additional
    funding.
  • Potential additional cost and schedule impact to
    late 2002 LRD
  • ICESat is unfunded beyond 5 / 31 / 02
  • Cost / schedule impact of SN001 Laser and other
    anomalies
  • CURRENT STATUS
  • Schedule and cost requirements ready to be
    presented to HQ / Code Y in mid-March.
  • Code Y PMC rescheduled for May 3.
  • Working with Code Y to determine plan for
    providing additional mission funding. Plan may
    require substantial FY02 carryover and FY03
    emergency operating plan submittal.

7
PMC ACTION STATUS
ICESat Project STATUS AS OF 3/31/02
Action(s) NONE
Data / Source
Status
8
IT SECURITY
ICESat Project STATUS AS OF 3/31/02
Risk National Management IT
Security Contingency Agency Number Authorization E
lement Plan Plan Plan Check People To
Proceed Ball / LASP Complete Complete Complete To
Center 22 Pending Security ISIPS /
ISF Final Pending Final Pending Final Pending To
be 18 N / A (GSFC Bldg 22)
Re-assessed Number increased significantly due
to changes in IT security requirement to include
data handling personnel. Forms have been
submitted and fingerprinting is in progress.
9
ICESat SIGNIFICANT PROGRESS
ICESat Project STATUS AS OF 3/31/02
  • THE GLAS INSTRUMENT IS FULLY INTEGRATED.
  • GLAS HAS SUCCESSFULLY COMPLETED ACOUSTICS
  • GLAS VIBRATION TESTING IS UNDERWAY TWO AXES
    SUCCESSFULLY COMPLETED
  • INITIATED A RISK MITIGATION EFFORT TO DEVELOP
    CORRECTIVE OPTICS DEVICE FOR USE IF THE GLAS
    BORESITE PERFORMANCE PROVES TO BE UNACCEPTABLE
  • INSTALLATION OF HEATERS ON UPPER DECK OF THE
    SPACECRAFT IS COMPLETE. LIMITED FUNCTIONAL
    TESTING IS UNDERWAY FULL FUNCTIONAL TESTING WILL
    TAKE PLACE IMMEDIATELY BEFORE GLAS DELIVERS.
  • CONDUCTED A EEE PARTS AUDIT ON THE SPACECRAFT
    BALL HAS HANDLED RESIDUAL PARTS PROBLEMS VERY
    WELL.

10
GLAS ENROUTE TO ACOUSTICS (4/2/02)
11
VIBRATION TESTING (4/5-9/02)
12
(No Transcript)
13
ICESat SCHEDULE SLACK
ICESat Project STATUS AS OF 4/9/02
84 56 28 0
D A Y S
Replan to 12/02 LRD
Mar Apr May Jun Jul Aug
Sept Oct Nov Dec 02
LRD
14
BACKUP
15
END OF MISSION PLAN DEVELOPMENT COMPLETED
ICESat Project STATUS AS OF 2/28/02
Final Estimate Final Orbital Debris
Generation report was approved by Headquarters on
4 / 9 / 01. The total mission package included
ICESat, CATSAT, DPAF, and launch vehicle. Both
ICESat and CATSAT meet the 8m2 guideline by
significant margins. ICESat is 3.9m2 and CATSAT
0.9m2. ICESat will reenter in 15 years, which is
well under the 25 year guideline. Disposal
Option Assessment Controlled Reentry Not
practical -- 240kg additional fuel and 6 months
delay Safe Orbit Not feasible -- same as
re-entry Shuttle Recovery ICESat polar orbit
not accessible to the shuttle also spacecraft
design not manned-flight rated Expect no changes
when CHIPSAT data becomes available
16
ICESat PROJECT OUTSTANDING PROPOSALS STATUS
ICESat Project STATUS AS OF 3/31/02
Contract Number NONE Contractor Technical
Officer Contract Officer / Specialist Type
Action In-house Estimate Proposed Value
Proposal Date Technical Completion Plan
Actual Award Date Plan Actual
17
ACRONYMS
ICESat Project STATUS AS OF 3/31/02
AFT - (GLAS aft optics) AGS - Alaska Ground
Station ANT - Antenna ARO - After Receipt of
Order ATP - Authority to Proceed CCAS Cape
Canaveral Air Station CM Center of Mass CPT-
Comprehensive Performance Test CTU - Command and
Telemetry Unit DBC - Data Bus Coupler DO
Delivery Order DSU - Data Storage Unit EAC
Estimate at Completion E-BOX - Electronics Box (
MEU) EDAC - Error Detection and Correction EIC -
Electrical Integration Complete ENV - Environment
or Environmental EPS - Electrical Power
Subsystem FOR - Flight Operations Review FOT -
Flight Operations Team
FRR - Flight Readiness Review FSW - Flight
Software FSWTB - Flight Software Test Bench HRG -
Hemispherical Resonating Gyro HVPS High Voltage
Power Supply IGS - ICESat Ground System IIRR
Instrument Integration Readiness Review IRU -
Inertial Reference Units ISF - Instrument Science
Facility I-SIPS - ICESat Science Investigator-Led
Processing IST - Instrument Star Tracker ITOC -
Instrument Test Operations Center LASP -
Laboratory for Atmospheric Space Physics LED
Light-Emitting Diode LHP - Loop Heat Pipe LPA
Laser Profiling Array LRA - Laser Retro-Reflector
Assembly LRD - Launch Readiness Date LRR - Launch
Readiness Review LRS - Laser Reference System
18
ACRONYMS
ICESat Project STATUS AS OF 3/31/02
LSM - Laser Steering Mechanism MEU - Main
Electronics Unit MIC - Mechanical Integration
Complete MIWG - Mission Integration Working
Group MOC - Mission Operations Center MOR -
Mission Operations Review MORD - Mission
Operations Requirements Doc. MOWG - Mission
Operations Working Group MPS - Multi-program
Support MRR - Mission Readiness Review NADIR
Earth-facing side of spacecraft NGS - Norway
Ground Station NISN - NASA Integrated Services
Network NSIDC - National Snow and Ice Data
Center NTGSE - (Windows) NT Ground Support
Equip ORR - Operational Readiness Review OTS -
Optical Test Source PDA - Power Distribution
Assembly PDU Power Distribution Unit PEC -
Precise External Clock
PRA Probabilistic Risk Assessment RWA
Reaction Wheel Assembly S / A - Solar Array SADA
Solar Array Drive Assembly SADE Solar Array
Drive Electronics SCC - Spacecraft Control
Computer SEP - Spacecraft Electronics
Package SIPS Science Investigator-Led
Processing System SIRU - Space Inertial Reference
Unit SLTC Space Lidar Technical Center SM -
Safe Mode SORD - Systems Operations Requirements
Document SPCM - Single Photon Counting Module SRS
Stellar Reference System
19
PROJECT OVERVIEW
ICESat Project STATUS AS OF 3/31/02
  • ICESat
  • SIGNIFICANT PROGRESS
  • THE GLAS INSTRUMENT IS FULLY INTEGRATED
  • GLAS HAS SUCCESSFULLY COMPLETED ACOUSTICS
  • GLAS VIBRATION TESTING IS UNDERWAY TWO AXES
    SUCCESSFULLY COMPLETED
  • INITIATED A RISK MITIGATION EFFORT TO DEVELOP
    CORRECTIVE OPTICS DEVICE FOR USE IF THE GLAS
    BORESITE PERFORMANCE PROVES TO BE UNACCEPTABLE
  • INSTALLATION OF HEATERS ON UPPER DECK OF THE
    SPACECRAFT IS COMPLETE. LIMITED FUNCTIONAL
    TESTING IS UNDERWAY FULL FUNCTIONAL TESTING WILL
    TAKE PLACE IMMEDIATELY BEFORE GLAS DELIVERS
  • CONDUCTED A EEE PARTS AUDIT ON THE SPACECRAFT
    BALL HAS HANDLED RESIDUAL PARTS PROBLEMS VERY
    WELL
  • ISSUES / CONCERNS
  • NO NEW ISSUES

Y
Write a Comment
User Comments (0)
About PowerShow.com