State of the Nation Address (SONA) Projects
Republic of the PhilippinesDepartment of Public
Works and Highways
  • STATUS REPORT
  • June 30, 2008

2
Republic of the Philippines Department of Public
Works and Highways
NORTH LUZON AGRI-BUSINESS QUADRANGLE
3
Republic of the Philippines Department of Public
Works and Highways
NORTH LUZON AGRI-BUSINESS QUADRANGLE
2. BONTOC-TABUK-TUGUEGARAO ROAD
LENGTH 108.03 Kms.
COST P 3.289 Billion
SCHEDULE January 2007-April 2010
STATUS 10.30
1. HALSEMA HIGHWAY
LENGTH 95.29 Kms.
COST P 1.959 Billion
SCHEDULE September 2006 April 2010
STATUS 23.97
a. Tinglayan Bdry.-Lubuagan-Tabuk Section II
LENGTH 78.52 Kms.
COST P 2.341 Billion
SCHEDULE January 2007-April
2010 STATUS 9.78
a. Bontoc-Banaue Section, Phase III
LENGTH 44.80 Kms.
COST P 0.864 Billion
SCHEDULE January 2007 December 2009
STATUS 19.95
b. Bontoc-Tinglayan Bdry. Section I
LENGTH 29.51 Kms.
COST P 0.948 Billion
SCHEDULE March 2007-April 2010
STATUS 11.56
b. Mt. Data-Bontoc Section, Phase II
LENGTH 50.49 Kms.
COST P 1.095 Billion
SCHEDULE September 2006 April 2010
STATUS 27.14
c. La Trinidad-Mt. Data Section, Phase I
LENGTH 84.84 Kms.
COST P1.038 Billion
STATUS Completed
IBRD-NRIMP I
3. BALER, AURORA-CASIGURAN ROAD
LENGTH 120 Kms.
COST P 2.337 Billion
SCHEDULE March 2007 March 2011
STATUS 4.45
4
Republic of the Philippines Department of Public
Works and Highways
LUZON URBAN BELTWAY
5
Republic of the Philippines Department of Public
Works and Highways
LUZON URBAN BELTWAY
1. TARLAC-NUEVA ECIJA-AURORA-DINGALAN PORT
LENGTH 120.65 Kms.
COST P 1.575 Billion
SCHEDULE March 2007 March 2010
STATUS 14.98
4. TARLAC-LA UNION TOLL EXPRESSWAY (TLUTE)
LENGTH 83.5 Kms. COST P 11.594 Billion
SCHEDULE 2009-2012 STATUS Not Yet Started
2. MARIKINA-INFANTA ROAD
LENGTH 109.125 Kms. COST
P 2.323 Billion SCHEDULE
May 2004 April 2010
STATUS 23.11
5. NORTH LUZON EXPRESSWAY, Phase 2 (C5)
LENGTH 29.20 Kms. COST 2.104 Billion
SCHEDULE STATUS Not Yet Started

3. SOUTHERN TAGALOG ARTERIAL ROAD PROJ. (Lipa
City-Batangas City Section)
LENGTH 20 Kms. COST 2.511
Billion SCHEDULE Jan.
2006July 2008 STATUS
93.52
6. MANILA-CAVITE EXPRESSWAY PROJECT (R-1
Expressway Extension)
LENGTH 11.24 Kms. COST P
4.300 Billion SCHEDULE
Jan. 2007- Jan. 2009
STATUS 39.491
7. SOUTH LUZON EXPRESSWAYEXTENSION PROJECT
LENGTH 92.732 Kms.
COST 16.736 Billion
SCHEDULE 2006-2010
STATUS TR1 (71.49) TR2 (41.50) TR3 (2.520)
TOLL ROAD PROJECTS
6
Republic of the Philippines Department of Public
Works and Highways
CENTRAL PHLIPPINES
7
Republic of the Philippines Department of Public
Works and Highways
CENTRAL PHILIPPINES
7. Aroroy-Esperanza Road
LENGTH 161.971 Kms. COST
P 0.614 Billion SCHEDULE
Jan. 2007-Dec. 2009
STATUS 27.79
3. PANDAN-LIBERTAD-ANTIQUE/AKLAN BDRY. RD.
LENGTH 27.7 Kms.
COST P 0.453 Billion
SCHEDULE 2008-2009
STATUS Under Pre-Construction Activities
2. ILOILO CITY STA. BARBARA ROAD
LENGTH 13.096 Kms.
COST P 0.568 Billion
SCHEDULE March 2007-December 2009
STATUS 12.32
6. NEW BACOLOD (SILAY) AIRPORT ACCESS ROAD
LENGTH 10.12 Kms.
COST P 0.972 Billion
SCHEDULE Sept. 2008- March 2010
STATUS Under Pre-Construction
Activities
5. CEBU NORTH COASTAL ROAD
LENGTH 9.45 Kms.
COST P 2.309 Billion
SCHEDULE 2007-2010
STATUS 1.66
8. BOHOL CIRCUMFERENTIAL ROAD
LENGTH 260.60 Kms.
COST P 2.200 Billion
STATUS Completed
1. EL NIDO-BATARAZA ROAD
LENGTH 280.65 Kms.
COST P 8.167 Billion
SCHEDULE April 2004-April 2010
STATUS 21.55
4. METRO ILOILO RADIAL ROAD
LENGTH 11.863 Kms.
COST P 0.696 Billion
SCHEDULE March 2007-March 2010
STATUS 0.76
8
Republic of the Philippines Department of Public
Works and Highways
EL NIDO-BATARAZA-RIO TUBA ROAD
EL NIDO-BATARAZA ROAD (El
Nido-Taytay-Roxas Section)
LENGTH 100.28 Kms. COST
P 3.315 Billion SCHEDULE
April 2004-April 2010
STATUS 40.51
EL NIDO-BATARAZA ROAD (Roxas-Puerto
Princesa Section) LENGTH
109.74 Kms. COST P 0.930
Billion STATUS Completed
EL NIDO-BATARAZA ROAD (Puerto
Princesa-Narra-Aboabo Section)
LENGTH 94.0 Kms.
COST P 2.208 Billion
SCHEDULE January 2007-April 2010
STATUS 11.78
EL NIDO-BATARAZA ROAD
(Aboabo-Espanola-Bataraza-Rio Tuba Section)
LENGTH 86.37 Kms.
COST P 2.644 Billion
SCHEDULE August 2006-April 2010
STATUS 5.94
9
Republic of the Philippines Department of Public
Works and Highways
AGRI-BUSINESS MINDANAO
10
Republic of the Philippines Department of Public
Works and Highways
AGRI-BUSINESS MINDANAO
1. DINAGAT ISLAND ROAD NETWORK
LENGTH 89.80 Kms.
COST P 0.30 Billion
SCHEDULE April 2007-Dec. 2009
STATUS 30.28
2. ILIGAN CITY CIRCUMFERENTIAL ROAD 3
LENGTH 10.518 Kms.
COST P 0.363 Billion
SCHEDULE August 2008-March 2010
STATUS Bid-out
3. DAPITAN-DAKAK ROAD.
LENGTH 10.766 Kms. COST
P 0.303 Billion SCHEDULE
March 2007-March 2010
STATUS 23.40
9. DIOSDADO MACAPAGAL BRIDGE (2ND MAGSAYSAY
BRIDGE AND BUTUAN CITY BY-PASS ROAD)
COST P 2.159 Billion
STATUS Completed
4. ZAMBOANGA WEST COAST ROAD.
LENGTH 169 Kms.
COST P 3.428 Billion
SCHEDULE April 2007-March 2010
STATUS 8.20
5. PANGUIL BAY BRIDGE
LENGTH 2.36 Km. (Bridge)
COST P 2.671 Billion
SCHEDULE 2009-2012
STATUS Not Yet Started
6. JCT. AWANG-UPI-LEBAK-KALAMANSIG, SULTAN
KUDARAT, MAGUINDANAO
LENGTH 87.62 Kms. COST P
2.630 Billion SCHEDULE
2008-2010 STATUS Under
Pre-Construction Activities
7. KAPALONG-TALAINGOD-VALENCIA, BUKIDNON RD.
LENGTH 151.88 Kms.
COST P 3.615 Billion
SCHEDULE April 2007-March 2010
STATUS 1.52
TOLL ROAD PROJECTS
11
Republic of the Philippines Department of Public
Works and Highways
AGRI-BUSINESS MINDANAO
8. SURIGAO DAVAO COASTAL ROAD (BACUAG-CLAVER)
LENGTH 40 Kms.
COST P 0.858 Billion
SCHEDULE November 2007-April 2009
STATUS 20.54
SDCR, CORTES-TANDAG-MARIHATAG SECTION
LENGTH 75.0 Kms.
COST P 0.758 Billion
SCHEDULE May 2007-March 2010
STATUS 9.21
SDCR, MARIHATAG-HINATUAN-BISLIG SECTION
LENGTH 89.06 Kms.
COST P 1.175 Billion
SCHEDULE February 2007-March 2010
STATUS 20.62
SDCR, BISLIG-BOSTON SECTION
LENGTH 72.39 Kms.
COST P 1.092 Billion
SCHEDULE April 2007-March 2010
STATUS 18.58
SDCR, BOSTON-MANAY SECTION
LENGTH 83.89 Kms.
COST P 1.703 Billion
SCHEDULE June 2007-March 2010
STATUS 6.47
SDCR, MANAY-MATI SECTION
LENGTH 66.650 Kms. COST
P 0.984 Billion SCHEDULE
October 2004-April 2008
STATUS 92.05
12
Republic of the Philippines Department of Public
Works and Highways
COMPLETED PROJECTS
13
Republic of the Philippines Department of Public
Works and Highways
BOHOL CIRCUMFERENTIAL ROAD
2004
2006
Shore Protection and Concreting in the town of
Garcia-Hernandez
14
Republic of the Philippines Department of Public
Works and Highways
BOHOL CIRCUMFERENTIAL ROAD
2004
2007
Shore Protection and Concreting in the town of
Lila
15
Republic of the Philippines Department of Public
Works and Highways
DIOSDADO MACAPAGAL BRIDGE (2nd MAGSAYSAY BRIDGE
AND BUTUAN CITY BYPASS ROAD)
  • DESCRIPTION
  • The project covers the construction of the Second
    Magsaysay Bridge and Butuan City Bypass Road and
    its linkages to the Surigao Butuan and the
    Iligan Cagayan-Butuan City Roads.
  • The Second Magsaysay Bridge consists of a 300 m
    steel cable stayed main bridge with concrete
    tower and steel deck plate girder on steel pipe
    pile foundation. A 372 and 150 m approach
    viaducts composed of steel I-girders with
    pre-cast prestressed concrete deck slab on steel
    pipe piles foundation will be constructed at the
    east and west banks, respectively.
  • The Bypass Road Starts at Km 1236 394 and ends
    at Km 1247 260. To be constructed will be a
    6.70 m wide PCCP with 2.5 m shoulders for the
    8.10 km road length. The road links include 1.33
    km of the Maguinda Nieves Road and 2.9 km of
    the Bonbon Libertad Road. To be included are
    major channelized road junctions at Surigao
    Tiniwisan intersection, junction with
    Butuan-Malaybalay road and intersection of Bonbon
    Road with Iligan-Cagayan-Butuan Road. The Bonbon
    and Bonbon Proper intersections will also become
    major road intersections. Minor road junctions
    will also be improved and crossdrains and animal
    crossings will be provided.
  • IMPLEMENTATION SCHEDULE

16
Republic of the Philippines Department of Public
Works and Highways
DIOSDADO MACAPAGAL BRIDGE (2nd MAGSAYSAY BRIDGE
AND BUTUAN CITY BYPASS ROAD)
CONTRACTUAL DATA
17
Republic of the Philippines Department of Public
Works and Highways
DIOSDADO MACAPAGAL BRIDGE (2nd MAGSAYSAY BRIDGE
AND BUTUAN CITY BYPASS ROAD)
18
Republic of the Philippines Department of Public
Works and Highways
DIOSDADO MACAPAGAL BRIDGE (2nd MAGSAYSAY BRIDGE
AND BUTUAN CITY BYPASS ROAD)
19