1
Transmission Upgrades and Additions in West
Texas
Johnnie Davis LCRA Transmission Services October
21, 2002
2
Rio Pecos Wind Generation Project
Noelke Hill Project
3
  • AEP Rio Pecos Project
  • Project Manager Natalie Vaughn
  • Project Agreement Signed June 2002
  • Project Budget 90.5 million

4
PROJECT SCOPE (AEP Rio Pecos Project)
  • Rebuild 13.46 miles of 69 kV from North McCamey
    to Tippet to 138 kV
  • Construction underway complete Nov 2003
  • Convert 9.98 miles of 69 kV from Tippet to West
    Yates Switch Station to 138 kV
  • Scheduled for completion Apr 2003
  • Rebuild 25 miles of 69 kV and double circuit from
    McElroy to WTU Crane
  • Scheduled for completion Apr 2003

5
PROJECT SCOPE (AEP Rio Pecos Project)
  • Construct new 1.5 mile 69/138 kV double circuit
    on a portion of McElroy to WTU Crane
  • CCN application filed Sept 2003
  • Scheduled for completion May 2003
  • Crane Substation Addition
  • Construction Underway Complete May 2003
  • Convert 4.23 miles of 69 kV from West Yates
    Switch Station to Yates Pump to 138 kV
  • Scheduled for completion Jul 2003

6
PROJECT SCOPE (AEP Rio Pecos Project)
  • Construct new 5.85 mile 138 kV line from North
    McCamey to SW Mesa
  • CCN application filed Oct 2003
  • Scheduled for completion Jul 2003
  • Add West Yates 138 kV Switching Station
  • Scheduled for completion Sept 2003
  • Add 1.0 mile 138 kV line between Yates Pump to
    Mesa View
  • Scheduled for completion Sept 2003
  • Add Mesa View 138 kV Switch Station
  • Scheduled for completion Sept 2003

7
PROJECT SCOPE (AEP Rio Pecos Project)
  • Rebuild 5.57 miles of 138 kV from Mesa View to
    Mesa View Switch Station to 138 kV
  • Scheduled for completion Jan 2004
  • Convert 23 miles of 69 kV to 138 kV from Rio
    Pecos to Crane
  • Scheduled for completion May 2004
  • Rebuild 27.13 miles of 138 kV from Rio Pecos to
    Mesa View Switch Station
  • Scheduled for completion Aug 2004

8
PROJECT SCOPE (AEP Rio Pecos Project)
  • Rebuild 9.67 miles of 138 kV from Rio Pecos to
    North McCamey
  • Scheduled for completion Oct 2004
  • Rebuild 19.8 miles of 138 kV from Mesa View
    Switching Station to Fort Lancaster
  • Scheduled for completion Jan 2005

9
  • Morgan Creek to Comanche Project

Project Manager Manny Garcia Project Agreement
Signed September 2000 Project Budget 89 million
10
(No Transcript)
11
PROJECT SCOPE (Morgan Creek to Comanche)
  • New 345 kV line (145 total miles)
  • Complete by June 2003
  • New 345/138 kV Switching Station
  • Named Twin Buttes - located NW of San Angelo
  • Engineering Underway

12
  • Twin Buttes 138kV Loop Circuit Project

Project Manager Johnnie Davis Project Agreement
Signed September 14, 2001 Project Budget 4.5
million
13
(No Transcript)
14
PROJECT SCOPE(Twin Buttes 138kV Loop Circuit)
  • One new 138kV line (approx. 7 miles)
  • Line will connect Twin Buttes switching station
    to existing Big Lake to San Angelo Power Station
    line

15
MILESTONES (Twin Buttes 138kV Loop Circuit)
  • Regulatory (CCN) On-going
  • Open house held on November 13, 2001
  • CCN application filing is planned for Dec 2002
  • Construction
  • Scheduled completion - Dec 2003

16
  • Ft Lancaster-Friend Ranch-Twin Buttes Project
  • Project Manager Natalie Vaughn
  • Project Agreement Signed December, 2001
  • Project Budget 43 million

17
PROJECT SCOPE (Ft Lancaster-Friend Ranch-Twin
Buttes )
18
PROJECT SCOPE (Ft Lancaster-Friend Ranch-Twin
Buttes )
  • Construct a 40-mile 138-kV transmission line
    between the Fort Lancaster and Friend Ranch
    substations
  • CCN application filing is planned for Nov 2002
  • Recommended in-service date Sept 2005
  • Construct a 70-mile 138 kV transmission line
    between Friend Ranch to Twin Buttes
  • CCN application filing is planned for Dec 2002
  • Recommended in-service date Mar 2006
  • Held five open houses in West Texas

19
  • ONCOR Rio Pecos Project

Project Manager Rob Seiler Project Agreement
Signed Scheduled for Fall 2002 Project Budget
28 million
20
PROJECT SCOPE (Oncor Rio Pecos)
21
PROJECT SCOPE (Oncor Rio Pecos)
  • Upgrade 31.8 mile Crane to Odessa
  • Scheduled for completion Dec 2003
  • Upgrade/Rebuild 67.4 mile Crane to Spraberry
  • Scheduled for completion Jul 2003

22
  • South Abilene to Eskota Project

Project Manager Rob Seiler Project Agreement
Signed May 2002 Project Budget 7 million
23
PROJECT SCOPE (South Abilene to Eskota )
  • Project will upgrade 24.7 miles of an existing
    69kV transmission line between the South Abilene
    substation (WTU) and an interconnect structure
    near the Eskota substation (ONCOR)
  • Scheduled for completion Dec 2003

24
  • Noelke Hill Project
  • Project Manager Natalie Vaughn
  • Interconnect Agreement Signed June 20, 2002
  • Project Budget To be determined

25
PROJECT SCOPE (Noelke Hill Project )
  • Interconnect Noelke Hill to West Yates Switchyard
  • Recommended in-service date Oct 2003
  • Add a double circuit to the 25-mile 138 kV West
    Yates to North McCamey
  • CCN is required for this project
  • Recommended in-service date Sept 2004
  • Construct a 110-mile transmission line between
    North McCamey and Twin Buttes substations
  • CCN is required for this project
  • Recommended in-service date Dec 2007

26