Eastern Interconnection Phasor Project Modernizing
North Americas Electric Grid
  • Enhanced Wide-Area Visibility
  • In the Eastern Interconnection for Reliability
    Management
  • Floyd Galvan, PE
  • Entergy Transmission

Distributed Sensors Control in Power
Systems Clemson University, March 2005
2
Overview
  • Overview of EIPP
  • Discussion of Entergy Phasor System
  • Real-Time Demonstration of Entergy Phasor System
  • http//phasors.pnl.gov

3
Strategic Importance
August 14th Blackout By-The-Numbers 1 Canadian
Province 3 deaths 8 U.S. states 12 airports
closed 23 cases of looting in Ottawa 250 power
plants 9,266 square miles 61,800 MW of power
lost 1.5 mill Cleveland residents without
water 50 million people 4.5-10 billion in
economic activity lost
it's clear that the power grid needs an
overhaul. It needs to be modernized. As we go
into an exciting new period of American history,
we want the most modern electricity grid for our
people we need more investment we need research
and development President Bush September 2003
When the lights go out, modern life as we know
it grinds to a sudden halt.  Transportation is
interrupted, communications fail, water systems
shut down, factory work is disrupted, food
spoils, businesses lose money, and people are
inconvenienced and even endangered.  Secretary
Abraham April 2004
4
EIPP Working Group
  • Vision improve power system reliability through
    wide-area measurement, monitoring and control
  • EIPP Working Group Organizations (as of 12/2004)

US DOE Entergy National Grid AEP FERC NER
C Ameren First Energy NYISO CERTS Hydro
One NYPA Com Ed IMO PJM Con Ed ISO
NE Southern Co. Dominion MAPP SPP Duke MISO
TVA at least ten additional Work Group
members are vendors of hardware or software
These organizations have expressed interest but
have not yet committed resources.
5
EIPP Task Teams
EIPP Work Group
Leadership Committee
WECC/ERCOT Coordination
Navin Bhatt AEP
Floyd Galvan Entergy
Off Line Applications Task Team
Business Management Task Team
Terry Bilke MISO
Mike Ingram TVA
Real Time Applications Task Team
Equipment Placement Task Team
Bruce Fardanesh NYPA
TBD
Performance Requirements Task Team
Networking Task Team
Coordinate with WECC, ERCOT
Eastern Interconnection specific
6
Phasor Measurement Systems Structure
Critical Grid Locations
Reliability Coordinators
Control Area Operators
Software Applications
7
Phase I Concentrator Locations
NYISO
AEP
Ameren
TVA
Entergy
8
Eastern Interconnection Phasor Project Plan
  • Phase I (Completed 12/04)
  • 20 Instruments installed
  • Resolve major communications issues
  • Transfer software tools to users
  • Establish relationships

EIPP
  • Phase II (2007- )
  • More than 350 Instruments
  • Situational awareness and state estimator apps
    realized, automatic control apps beginning
  • Vendors participating at all levels
  • Inexpensive instruments and communications
    available
  • Phase II (2006)
  • 50 Instruments
  • Situational awareness and state estimator apps
    demonstrated
  • All major corridors covered
  • Data available to research community to begin
    work on projected benefits

9
Expected Benefits from EIPP Project
  • Improved wide area visibility
  • Improved real time monitoring tools for
    reliability coordinators
  • and system operators
  • Improved ability to monitor grid dynamics and
    stability for
  • reliability management
  • Time-synchronized data for system assessments and
    post
  • disturbance analysis
  • Improvements in state estimation
  • Dynamic system ratings for improved reliability
    and market
  • performance
  • Public-private industry collaboration to develop
    new
  • technologies and systems for modernizing the
    electric grid

10
NEW ORLEANS, LA
11
  • Entergy owns and operates 30,000 MW of capacity
  • 2nd largest nuclear generator in the US
  • Entergy has 2.6 million customers
  • Entergy has annual revenues of over 10 Billion
    and approximately 14,000 employees

12
  • Entergy
  • PMU Locations
  • 10 Sites are operational
  • 4 sites coming on-line May 2005

13
Current System Configuration
14
Planned System Configuration
15
(No Transcript)
16
Analysis Tool Development
  • Currently Exploring Options for Use of Phasor
    Data Including
  • Dynamic Line Loading
  • Real-Time Visualization of System Stability
  • Optimal PMU Placement
  • State Estimator Integration
  • Designing with Eye to Integration of Industry
    Recommendations
  • Open Architecture is Key

17