Title: Project Economics of Landfill Gas Energy
1Project Economics of Landfill Gas Energy
- Brian Guzzone
- US EPA Landfill Methane Outreach Program
- June 8, 2006
- LaGrange, Georgia
2Why Use Landfill Gas?
- Local, available fuel source easy to capture and
use - Source of renewable energy
- Constant supply - 24 hours a day, 7 days a week
- Reliable technologies exist for using landfill
gas - gt90 up time - Uses a source of energy that otherwise would have
been wasted - Helps the environment by reducing uncontrolled
emissions of landfill gas
3Why Use Landfill Gas? Heres Why!
4Cost Categories
- Gas collection and control system (GCCS)
- Gas treatment
- Blower/flare station
- Electricity generator sets
- Direct Use pipeline and retrofit costs
- Operation and Maintenance
5Gas collection and control system wellfield
schematic
6Gas collection and control system wellheads and
header piping
7Gas collection and control system blower/flare
station and treatment
8Typical GCCS and Treatment System Costs 900 cfm,
50 acre site
If more extensive treatment system needed
(siloxane removal, coalescing filters, carbon
filters, refrigeration, etc.), costs will be
higher.
9What are my options?
- Direct Use
- Electricity Production
- Combined Heat and Power
- Alternate Fuels
10Direct Gas Utilization
- Boilers
- Direct thermal applications
- Innovative applications
- Greenhouses
- Infrared heaters
- Pottery kilns
- Leachate evaporation
11Direct Gas Utilization
- Gas piped to a nearby customer to offset other
fuel (natural gas, oil, coal) use - 100 projects in the US
- Pipeline lengths range from ½ mile to 20 miles
- Gas used at end users site
12Direct Use Boilers and Direct Thermal
- Sizing
- Applicable to wide variety of landfill sizes
- Costs
- 1.50 to 3.50 per MMBtu, depending on
- GCCS in place or not
- Cost of boiler retrofits
- Pipeline length
- 100K - 250K per mile depending upon rights of
way, terrain, geology, permitting, geography
13Direct Use Innovative Applications- Leachate
Evaporation
- Sizing
- Typically 10,000 to 20,000 gallons per day
- Costs
- Capital Cost - 295,000 (10,000 gpd) to 485,000
(20,000 gpd) - Annual OM Cost - 70,000 to 95,000
14Direct Use Innovative Applications- Greenhouses
- Applicable to smaller landfills
- Produce high purity carbon dioxide that is used
to grow greenhouse plants - 5 operational greenhouse projects in the U.S.
15Direct Use Innovative Applications - Greenhouses
- Sizing
- Depends on greenhouse size - generally require
relatively low LFG volume - Costs
- Limited cost information available one project
in the U.S. estimated costs to be around 4.80
per MMBtu
16Electricity Generation
- Most prevalent type of project in the US
- In US, 1000 MW of capacity from over 200
operational projects - Electricity sold to utility, cooperative or
nearby customer - Average project size 4 MW (500 kW - 50 MW)
50 MW Steam Turbine, Puente Hills LF, CA
17Internal Combustion Engine
- Sizing
- 1-3 MWs
- Costs
- 1,100-1,300 (/kW)
- Major suppliers
- Cat, GE-Jenbacher, Waukesha, Deutz
18Turbines Gas, Steam, and Combined Cycle
- Sizing
- 1-10MWs
- Costs
- 1,200-1,700 (/kW)
- Major suppliers Cat-Solar, Fairbanks-Morse
19Microturbines
- Sizing
- 30-200 kW
- Costs
- 1,200-2,000 (/kW)
20Emerging Technologies
- Stirling External Combustion Engine (Continued)
- Sizing
- 25 - 55 kW
- Costs
- OM approximately 0.8cents/kW
- Capital Cost - limited information, demonstration
project in Michigan should provide more detailed
costs
21Combined Heat and Power Industrial
- Industrial
- Generally applicable to mid to larger size
landfills - Costs
- Available information indicate overall costs in
the 1200-2000 per kWh range. - Microturbines
- Generally applicable to small to mid size
landfills - Costs
- Available information indicate overall installed
costs in the 1800-3000 per kWh range.
22Alternate Fuels High-Btu Upgrades
- Technology
- Gas is purified from 50 to 99 methane
- Removal of carbon dioxide is primary step
- Advantages
- Inject treated product into pipeline
- Reduction in use of fossil fuels
- Reduce local ozone pollution
- Disadvantages
- Must meet strict standards of pipeline
- Costly technology
- Limited track record of performance
23Alternate Fuels High-Btu Upgrades
- Sizing
- Economical for large scale only
- Costs
- Capital Costs for 57 cubic meters/min. system
range from 3 million to 4 million - OM costs range from 0.82 to 1.12 per MMBtu
24Alternate Fuels - Vehicle Fuel
- Compressed landfill gas (CNG)
- Liquefied landfill gas (LNG) - Prometheus
- Early stages of commercial development
25Alternate Fuels- Vehicle Fuel
- Advantages
- LNG/CNG price lower than diesel fuel cost
- Reduction in use of fossil fuels
- Reduce local ozone pollution
- Disadvantages
- Very small percentage of alternative-fuel
vehicles - Vehicle conversion costs
- Limited track record of performance
- Costs
- Retrofit vehicles 3,500 to 4,000 per vehicle
- Fueling station 1,000,000
- Fuel price 0.48 to 1.26 per gallon
26Summary
- Key Selection considerations include
- Environmental performance
- Reliability
- Accuracy of assumptions
- Permitting issues emissions
- Cost
27Summary, continued
- Many ways to beneficially utilize LFG
- Available niche technologies range from research
and development stage units to commercially
available systems - Technologies exist for low and high volumes of
LFG production - Selection of technology is project specific