Project Economics of Landfill Gas Energy - PowerPoint PPT Presentation

1 / 27
About This Presentation
Title:

Project Economics of Landfill Gas Energy

Description:

Direct Use: Innovative Applications- Greenhouses. Applicable to smaller landfills. Produce high purity carbon dioxide that is used to grow greenhouse plants ... – PowerPoint PPT presentation

Number of Views:209
Avg rating:3.0/5.0
Slides: 28
Provided by: steve402
Category:

less

Transcript and Presenter's Notes

Title: Project Economics of Landfill Gas Energy


1
Project Economics of Landfill Gas Energy
  • Brian Guzzone
  • US EPA Landfill Methane Outreach Program
  • June 8, 2006
  • LaGrange, Georgia

2
Why Use Landfill Gas?
  • Local, available fuel source easy to capture and
    use
  • Source of renewable energy
  • Constant supply - 24 hours a day, 7 days a week
  • Reliable technologies exist for using landfill
    gas - gt90 up time
  • Uses a source of energy that otherwise would have
    been wasted
  • Helps the environment by reducing uncontrolled
    emissions of landfill gas

3
Why Use Landfill Gas? Heres Why!
4
Cost Categories
  • Gas collection and control system (GCCS)
  • Gas treatment
  • Blower/flare station
  • Electricity generator sets
  • Direct Use pipeline and retrofit costs
  • Operation and Maintenance

5
Gas collection and control system wellfield
schematic
6
Gas collection and control system wellheads and
header piping
7
Gas collection and control system blower/flare
station and treatment
8
Typical GCCS and Treatment System Costs 900 cfm,
50 acre site
If more extensive treatment system needed
(siloxane removal, coalescing filters, carbon
filters, refrigeration, etc.), costs will be
higher.
9
What are my options?
  • Direct Use
  • Electricity Production
  • Combined Heat and Power
  • Alternate Fuels

10
Direct Gas Utilization
  • Boilers
  • Direct thermal applications
  • Innovative applications
  • Greenhouses
  • Infrared heaters
  • Pottery kilns
  • Leachate evaporation

11
Direct Gas Utilization
  • Gas piped to a nearby customer to offset other
    fuel (natural gas, oil, coal) use
  • 100 projects in the US
  • Pipeline lengths range from ½ mile to 20 miles
  • Gas used at end users site

12
Direct Use Boilers and Direct Thermal
  • Sizing
  • Applicable to wide variety of landfill sizes
  • Costs
  • 1.50 to 3.50 per MMBtu, depending on
  • GCCS in place or not
  • Cost of boiler retrofits
  • Pipeline length
  • 100K - 250K per mile depending upon rights of
    way, terrain, geology, permitting, geography

13
Direct Use Innovative Applications- Leachate
Evaporation
  • Sizing
  • Typically 10,000 to 20,000 gallons per day
  • Costs
  • Capital Cost - 295,000 (10,000 gpd) to 485,000
    (20,000 gpd)
  • Annual OM Cost - 70,000 to 95,000

14
Direct Use Innovative Applications- Greenhouses
  • Applicable to smaller landfills
  • Produce high purity carbon dioxide that is used
    to grow greenhouse plants
  • 5 operational greenhouse projects in the U.S.

15
Direct Use Innovative Applications - Greenhouses
  • Sizing
  • Depends on greenhouse size - generally require
    relatively low LFG volume
  • Costs
  • Limited cost information available one project
    in the U.S. estimated costs to be around 4.80
    per MMBtu

16
Electricity Generation
  • Most prevalent type of project in the US
  • In US, 1000 MW of capacity from over 200
    operational projects
  • Electricity sold to utility, cooperative or
    nearby customer
  • Average project size 4 MW (500 kW - 50 MW)

50 MW Steam Turbine, Puente Hills LF, CA
17
Internal Combustion Engine
  • Sizing
  • 1-3 MWs
  • Costs
  • 1,100-1,300 (/kW)
  • Major suppliers
  • Cat, GE-Jenbacher, Waukesha, Deutz

18
Turbines Gas, Steam, and Combined Cycle
  • Sizing
  • 1-10MWs
  • Costs
  • 1,200-1,700 (/kW)
  • Major suppliers Cat-Solar, Fairbanks-Morse

19
Microturbines
  • Sizing
  • 30-200 kW
  • Costs
  • 1,200-2,000 (/kW)

20
Emerging Technologies
  • Stirling External Combustion Engine (Continued)
  • Sizing
  • 25 - 55 kW
  • Costs
  • OM approximately 0.8cents/kW
  • Capital Cost - limited information, demonstration
    project in Michigan should provide more detailed
    costs

21
Combined Heat and Power Industrial
  • Industrial
  • Generally applicable to mid to larger size
    landfills
  • Costs
  • Available information indicate overall costs in
    the 1200-2000 per kWh range.
  • Microturbines
  • Generally applicable to small to mid size
    landfills
  • Costs
  • Available information indicate overall installed
    costs in the 1800-3000 per kWh range.

22
Alternate Fuels High-Btu Upgrades
  • Technology
  • Gas is purified from 50 to 99 methane
  • Removal of carbon dioxide is primary step
  • Advantages
  • Inject treated product into pipeline
  • Reduction in use of fossil fuels
  • Reduce local ozone pollution
  • Disadvantages
  • Must meet strict standards of pipeline
  • Costly technology
  • Limited track record of performance

23
Alternate Fuels High-Btu Upgrades
  • Sizing
  • Economical for large scale only
  • Costs
  • Capital Costs for 57 cubic meters/min. system
    range from 3 million to 4 million
  • OM costs range from 0.82 to 1.12 per MMBtu

24
Alternate Fuels - Vehicle Fuel
  • Compressed landfill gas (CNG)
  • Liquefied landfill gas (LNG) - Prometheus
  • Early stages of commercial development

25
Alternate Fuels- Vehicle Fuel
  • Advantages
  • LNG/CNG price lower than diesel fuel cost
  • Reduction in use of fossil fuels
  • Reduce local ozone pollution
  • Disadvantages
  • Very small percentage of alternative-fuel
    vehicles
  • Vehicle conversion costs
  • Limited track record of performance
  • Costs
  • Retrofit vehicles 3,500 to 4,000 per vehicle
  • Fueling station 1,000,000
  • Fuel price 0.48 to 1.26 per gallon

26
Summary
  • Key Selection considerations include
  • Environmental performance
  • Reliability
  • Accuracy of assumptions
  • Permitting issues emissions
  • Cost

27
Summary, continued
  • Many ways to beneficially utilize LFG
  • Available niche technologies range from research
    and development stage units to commercially
    available systems
  • Technologies exist for low and high volumes of
    LFG production
  • Selection of technology is project specific
Write a Comment
User Comments (0)
About PowerShow.com