Title: Value Stream Mapping the Delaware Air Quality Permitting Process
1Value Stream Mapping the Delaware Air Quality
Permitting Process
- Bob Zimmerman
- Innovation Action Council
- April 26, 2006
2Overview of Administrative Efficiency Processes
- Techniques are variations of Japanese
manufacturing systems which look for waste and
inefficient approaches to administrative (permit)
timelines. - These lean processes include Value Stream
Mapping, Kaizen, and Six Sigma different names
and slightly different approaches to reach the
same bottom line.
3Delaware Value Stream Mapping Project Partners
- Delaware Economic Development Office
- Delaware Manufacturing Extension Partnership
- DNREC Office of the Secretary
- DAWM Air Quality Management
- General Motors
- Daimler Chrysler
- CIBA Specialty Chemicals
- ILC Dover, Inc.
- PPG Industries
- DuPont
4Delaware Value Stream Mapping Process Objectives
- Improve the permitting process without weakening
regulatory requirements. - Capture the experience of those who have to meet
the regulatory requirements. - Process redesign activity would be transparent to
the public and the regulated community.
5Why Did DE Engage in a Value Stream Mapping
Process?
- Listening to voice of customer
- DEDO report on industry clusters to Governor -
early 2005 - DNREC asked to identify specific process - AQ
construction permitting selected - Stakeholders (Public/ Industry/ DNREC)
- Improve permitting process
- Reduce processing time/effort
- Create greater business certainty
- Optimize DNRECs resources for other functions
- Improve environmental quality
6Perspectives from Delawares Business Community
- Cost issues due to
- Cumbersome and slow permitting process
- No allowance for green companies that are
proactive and stay in compliance
7Using the Value Stream Mapping Tool
Value Stream Scope
Determine the Value Stream to be Improved
Understand How Things Currently Operate. This
is the Foundation for the Future State
Current State Drawing
Future State Drawing
Design a Lean Flow
Standardize for Later Improvement
Develop a Detailed Plan of Implementation to
Support Objectives (What, Who, When)
Implementation Plan
Implementation of Improved Plan
The Goal of Mapping!
8Focus of Value Stream Mapping
- Process Versus People
- Customer Requirements Versus Weve Always Done
it that Way - Value-Added Activities Versus Waste
- We Can Versus We Cant
9Points to Remember About Waste
- Consider Waste in the Context of the Value that
the Process Provides to the Customer - Waste is Really a Symptom Rather than a Root
Cause of the Problem - Waste Points to Problems within the System
- Find and Address Causes of Waste to Improve Flow
- Waste is Most Prevalent in the Information Flow
of Non-manufacturing Processes - Experts Suggests up to 40 of What We do Adds no
Value
10What is a Value Stream?
- A Value Stream involves all the steps, both Value
Added and Non Value Added, required to complete a
product or service from beginning to end.
11What is a Value Stream Map?
- Visual Representation of a Value Stream
- Pencil Paper Tool
- Helps Reveal Waste Problems with Flow
- Establishes a Common Language to Document
Processes - Provides a Blueprint for Improvement
12History of DNREC / DEDO Value Stream Mapping
Process
- June 05 Initial Scoping Meeting
- July 05 Planning Session
- Aug 05 3 Day Training / Action Plan
- Sept 05 30 Day Progress Review
- Oct 05 60 Day Progress Review
- Nov 05 90 Day Progress Review
- Jan 06 120 Day Progress Review
- March 06 180 Day Progress Review
- May 06 240 Day Progress Review
13Delaware Value Stream Mapping
- For public transparency we created a web page for
the DNREC/ DEDO Value Stream Mapping project - http//www.dnrec.state.de.us/DNREC2000/VSM/Index.h
tm - All materials are available on the web page
14Mapping the Current State
- Created the goal for the session
- Defined what was in scope and out of scope
- Mapped the current state of the Air Quality
Construction Permitting Process.
15Goal for VSM Project
- Develop and implement an air permitting process
that results in expeditious issuance of
environmentally sound, operationally flexible and
achievable permits in a timeframe not to exceed
90 days and ensure requirements are identified
clearly prior to submittal reducing re-work in
the process to 50
16 17(No Transcript)
18Mapping the Current State
- Lessons learned
- Majority of process problems stem from the permit
applications! - First pass quality yield was lt 1
- Assuming perfect customer input, first pass
quality yield was 18 - Re-work was nearly 100!
- Construction permits issued within 180 days
19Mapping the Current State
- Identified opportunities for improvement called
Kaizen Bursts. - Kaizen are rapid improvement processes
focused on eliminating waste, improving
productivity, and achieving continual
improvement. - Kaizen Bursts were used to help create the
Future State.
20(No Transcript)
21Creating the Future State
- Defined our future state where we wanted to be
in one year - Internal first pass quality yield - 80
- Customer information quality - 80
- Administrative completeness - 100
- Technical completeness - 80
- Re-work less than 50
- Construction permit issued within 90 days
22(No Transcript)
23Achieving Our Future State
- Identified and scheduled specific tasks to
accomplish. These tasks included - create visual tracking boards
- implement a First-In-First-Out system
- create permitting checklists
- seek applicant feedback
- modify our applications to make them more user
friendly - modify application review process and
- collecting new performance metrics.
24Visual Tracking Board
25Project Highlights
- Surveyed applicants to discuss why they submitted
incomplete applications and learned important
information - Reduced our permitting backlog from 199 AQ
construction permits on 8/24/2005 to 48 on
1/11/2006 - Implemented a First-In-First-Out system
- Now issuing AQ construction permits within 61
days of receiving a complete application
26What We Learned from Applicants
- Difficult to know which form to complete
- Difficult to know where and how to obtain
information that is requested - Difficult to know which questions to answer and
which ones are not applicable - Applicants would like help with engineering
calculations - Applicants would like to know why specific
information is requested
27Important Process Improvements
- Future State includes three important changes to
the permitting process - Pre-Submittal Meeting
- Administratively Complete Gate
- Technically Complete Gate
28DNREC Value Stream Mapping Air Permitting Process
Future State
- PLUS
- Top Down Commitment
- Cross Functional Communications
- Employee Involvement
- First Time Quality
- Partnership Support
- Customer Focus and Communications
SEPTEMBER, OCTOBER NOVEMBER 05
- MINUS
- Reduced Waste in
- Motion
- Waiting
- Processing
- Rework
- Lead time
Current State
Created a permitting process that is
environmentally sound, operationally flexible and
achievable.
29Next Steps
- We are still working on some of the action items
required to implement the process. - Weve enlisted volunteers (especially our
permittees) to participate in the permit
application redesign. - We are reviewing/revising the metrics for permit
processing, e.g. return rates
30Schedule
- Feb 06 - Complete drafts of all VSM action items
- Mar-April 06 - Train regulated community on new
processes and documentation - May-June 06 Debug new processes
- July 06 complete full implementation of new
processes
31For more information
- Robert J. Zimmerman
- Office of the Secretary, Director of External
Affairs - Robert.Zimmerman_at_state.de.us
- 302-739-9000
- Ali Mirzakhalili
- Program Administrator, Air Quality Management
- Ali.Mirzakhalili_at_state.de.us
- 302-739-9400
- Amy Mann
- Environmental Engineer III, AQM
- Amy.Mann_at_state.de.us
- 302-323-4542
32State use of lean principles in administrative
process
- Michigan
- Delaware
- Iowa
- Nebraska
- Minnesota
33Common Lessons Learned by Delaware, Nebraska,
Michigan, Minnesota and Iowa
- Worth the effort
- Carefully select the situation or process
- There is a lot more waste than you realize
- Eliminating waste doesnt mean eliminating people
- Goal-setting is critical
- Communications (before, during and after)
- Active and visible management support
- Be prepared for resource issues
- Follow- thru essential to keep on track