1UCSB Module Assembly
2UCSB Parts Inventory 5/9/05
Hybrids Hybrids Hybrids Sensors Sensors Sensors  Frames
ST HPK IT ST HPK IT
L12pu 85 128 0 67 223 0 247
L12pd 0 0 0 67 223 0 247
L12su 0 0 0 67 223 0 249
L12sd 0 0 0 67 223 0 249
L34pu 85 128 1 67 223 208 1002
L56p 0 152 61 139 317 18/49 1002
R5N 16 3 0 31pr 248 pr 0 6
R5S 9 5 0 31pr 248 pr 0 3
R6 6 2 0 0 109pr 0 258
R7 0 0 0 0 72pr 101pr 198
3UCSB Module Assembly Mech. Specs.
Weekly Weekly Weekly Cumulative Cumulative Cumulative Â
A B F A B F A or B
L12pu 0 0 0 0 0 0 0.00
L12pd 0 0 0 0 0 0 0.00
L12su 0 0 0 0 0 0 0.00
L12sd 0 0 0 0 0 0 0.00
L34p 47 1 0 155 3 0 100.00
L56p 0 0 0 338 5 1 99.7
R5N 27 0 0 67 2 0 100.00
R5S 12 0 0 69 1 2 97.2
R6 6 0 0 87 9 0 100.00
R7 0 0 0 0 0 0 0.00
Total 92 1 0 716 20 3 99.6
4UCSB Module Assembly Problems
- Past Week
- U-motor E-stopped twice while picking up the
hybrid from the supply position during one day.
Has been fine since. - High point on TEC R5N module because much extra
work and limited production on Friday the 13th. - 400 storage plates are in production. Should be
done by the end of the week.
5Wirebonding
- This Week
- Bonding kept up with production on a daily basis.
- No significant problems encountered.