Title: UCSB Module Assembly


1
UCSB Module Assembly
  • Week of 5/9-5/13

2
UCSB Parts Inventory 5/9/05
Hybrids Hybrids Hybrids Sensors Sensors Sensors  Frames
ST HPK IT ST HPK IT
L12pu 85 128 0 67 223 0 247
L12pd 0 0 0 67 223 0 247
L12su 0 0 0 67 223 0 249
L12sd 0 0 0 67 223 0 249
L34pu 85 128 1 67 223 208 1002
L56p 0 152 61 139 317 18/49 1002
R5N 16 3 0 31pr 248 pr 0 6
R5S 9 5 0 31pr 248 pr 0 3
R6 6 2 0 0 109pr 0 258
R7 0 0 0 0 72pr 101pr 198
3
UCSB Module Assembly Mech. Specs.
Weekly Weekly Weekly Cumulative Cumulative Cumulative  
A B F A B F A or B
L12pu 0 0 0 0 0 0 0.00
L12pd 0 0 0 0 0 0 0.00
L12su 0 0 0 0 0 0 0.00
L12sd 0 0 0 0 0 0 0.00
L34p 47 1 0 155 3 0 100.00
L56p 0 0 0 338 5 1 99.7
R5N 27 0 0 67 2 0 100.00
R5S 12 0 0 69 1 2 97.2
R6 6 0 0 87 9 0 100.00
R7 0 0 0 0 0 0 0.00
Total 92 1 0 716 20 3 99.6
4
UCSB Module Assembly Problems
  • Past Week
  • U-motor E-stopped twice while picking up the
    hybrid from the supply position during one day.
    Has been fine since.
  • High point on TEC R5N module because much extra
    work and limited production on Friday the 13th.
  • 400 storage plates are in production. Should be
    done by the end of the week.

5
Wirebonding
  • This Week
  • Bonding kept up with production on a daily basis.
  • No significant problems encountered.