Agency Readiness Program - PowerPoint PPT Presentation

1 / 7
About This Presentation
Title:

Agency Readiness Program

Description:

Agencies will need dedicated personnel to assist them to prepare for new ... In good shape. Some concerns. Critical - Urgent. attention needed. Process: Meetings ... – PowerPoint PPT presentation

Number of Views:32
Avg rating:3.0/5.0
Slides: 8
Provided by: corectS
Category:

less

Transcript and Presenter's Notes

Title: Agency Readiness Program


1
Agency Readiness Program
2
Agency Readiness Program
Agencies have specific tasks and responsibilities
to prepare their agencies for Core-CT.
  • People readiness
  • Process readiness
  • Data and cutover readiness
  • Infrastructure readiness
  • Implement network and desk top upgrades / changes
  • Support Readiness

3
Agency Readiness Program
Agencies will need dedicated personnel to assist
them to prepare for new processes and new tools
ARCs are the go-between Core-CT and the agencies.
75 Sponsors for 62 Agencies
As of 11/12/01
4
Agency Readiness Program
Sponsors work closely with their ARCs and need to
delegate and monitor agency readiness tasks.
  • Address requests for information from Core-CT
    Team
  • Monitor / complete monthly action items See
    sample action plan
  • Updated list of action items keep their agency on
    track
  • Delegate and follow-up to ensure that they are
    completed
  • Update their action item list as items are
    completed
  • Track questions and/or issues
  • Assess agency progress towards readiness see
    sample progress report card
  • Complete progress report card (ARC to assist)
  • Attend their designated readiness meeting
    typically 4th Wednesday each month

5
Agency Readiness Program
Readiness progress is measured and reported
monthly until 2 months prior to go-live then,
assessments are truly Readiness Assessments.
6
Agency Readiness Program
At each monthly checkpoint, agency readiness will
be measured against a pre-defined set of factors,
using the following approach
Input Assessments
Output Reports Actions
In good shape
(1) Agency Assessment -
Sponsors (2) Project Management
Assessment - Project Directors
(4) Publish Report - Project Directors
- Change Management (5) Implement
corrective actions / adjustments -
Sponsors - Project Team
Some concerns
Critical - Urgent attention needed
Process Meetings
(3) Agree on consolidated assessment and
corrective actions / adjustments
- Sponsors - Project Directors
7
Agency Readiness Program
  • Several meetings in the upcoming weeks will
    involve active participation of the Sponsors,
    ARCs and other agency personnel.
  • Sponsor kickoff - March 27
  • Communications Workshops - Financials on April 3,
    4 and 8 HRMS to be scheduled for week of May 13
  • Meet with sponsors - ASAP after kickoff Audience
    Analysis interviewees confirmation begin
    relationship
  • Attend Audience Analysis Interviews - April and
    May
  • First Readiness Assessment - May (lag a month to
    give time for meetings, etc.)
  • Process workshops - HRMS to be held June and
    Financials to be held July / August
Write a Comment
User Comments (0)
About PowerShow.com