Title: BNL Diagnostics Meeting
1BNL Diagnostics Meeting
BNL Diagnostics Meeting Feb. 5-6, 2004 Held at
BNL Mike Plum
2The HEBT, Ring, and RTBT
Ring Service Building
Ring
HEBT
RTBT
HEBT Service Building
RTBT Service Building
3HEBT/Ring/RTBT Commissioning Schedule
CD-4 deadline 1/Jun/06
HEBT/Ring/RTBT, to extr. dump 6/Jul 18/Nov/05
Jan/07
Jan/06
Jan/05
Linac, to linac dump 11/Mar 31/May/05
RTBT, to target 1/Feb 28/Feb/06
4High level commissioning plan
- HEBT beam line up to arc, then on to linac dump,
commissioned as part of linac commissioning
(start 11/Mar/05 31/May/05). - Beam current limited (by linac dump) to 7.5 kW
avg. One full pulse (24 kJ) at very low rep rates
is also OK. - Start with low current beam (1 - 4 Hz, 1 - 100
us) (note 1 ea. 38 mA, 690 ns minipulse 26 J,
and1Hz, 100 us, 26 mA avg (38 mA chopped) 2.4
kW) - Should be able to use single mini pulse beam to
steer beam to dump. - Steer beam through collimators using BPMs and
loss monitors. - Check that BPMs, BLMs, BCMs, WSs all
functioning. - Check beam emittance and match to HEBT using the
four wire scanners at the beginning of the HEBT
(WS01-04).
5High level commissioning plan (cont.)
- Commission up to ring extraction dump (6/Jul/05
18/Nov/05). - First commission HEBT up to injection dump.
- Current limit to injection dump is about 150 uA.
- Start with low current beam (1 - 4 Hz, 1 - 100
us). - Should be able to use single mini pulse beam to
steer beam to dump. - Check that BPMs, BLMs, BCMs, WSs all
functioning. - Check HEBT optics Beam parameters at foil
(position, emittance, Twiss parameters,
achromat) beam stability at foil. - Measure beam emittance and Twiss parameters using
WS20-23, WS32). Extrapolate to ring and verify
correct. Adjust if not. - Check beam position and position stability at
foil, using HEBT/IDump BPMs upstream and
downstream of foil, and phosphor screen / video. - Measure dispersion in HEBT arc, using BPMs and
varying beam energy. At same time check for
achromat at end of arc and at stripper foil,
using BPMs and foil video. - May want to check halo scrapers. Insert until see
beam loss increase.
6High level commissioning plan (cont.)
- Next commission ring.
- Current limit to extraction dump is 7.5 uA avg.
Not necessary to extract beam if power is less
than a few kW (2 kW/collimator). - Verify correct beam parameters at stripper foil
using WS20-23, WS32, foil video, and BPMs. - Verify stripper foils are in place and in good
shape using foil video cameras. - Single shot injection into ring, 1 4 Hz. Bump
magnets off rf off trim, sextupole, octupole
magnets off, scrapers at out limits. - Correct closed orbit using BPM system.
- Measure betatron tune and position/angle of
injected beam at foil using BPM system in ring. - Very important Need BPM system that works well
with single shot injection (20 mA pk, 500 ns,
1 mm resolution). Note Model calculations
predict that 402.5 MHz structure will dissolve
after about 10 turns. Need good baseband system.
7High level commissioning plan (cont.)
- Ring commissioning (cont.)
- Measure ring revolution frequency and check MEBT
chopper period. Necessary for multi-turn
injection. Use BPM and/or WCM. - Next commission up to extraction dump.
- Keep beam current low 1 to 10 turn
accumulation, 1 4 Hz. - Extract beam at about 50 us from start of
injection, before beam has time to debunch. - May need to flat-top injection bump magnets to
get small beam size. - Steer beam using BLMs and BPMs.
- Check for good beam transport to extraction dump.
- Check RTBT BLMs, BCMs, BPMs, WSs.
8High level commissioning plan (cont.)
- Commission up to ring extraction dump (cont.)
- Ramp beam current to 1013 ppp (CD-4 requirement).
- To get 1013 ppp, need 75 turns at 38 mA peak, but
OK to inject for longer at lower peak currents
(15 - 20 mA) - 1013 ppp at 1 Hz 1.6 kW. Limit is 7.5 kW avg to
ext. dump. - Check injection bump magnet system using BPMs
and IPM. - Check ring rf system using BCM and wall current
monitor. - Check that beam losses remain below operational
limits. - This is the minimum needed for CD-4.
9High level commissioning plan (cont.)
- Commission RTBT to target (1/Feb 28/Feb/06).
- Verify 1013 ppp to extraction dump.
- Reduce beam current to 1 10 turns accumulation,
1 Hz. - Steer beam to target.
- Verify beam size and position on target, using
harp and halo monitor (thermocouples downstream
of proton beam window). - We are working on a temporary phosphor screen
that can be used to qualify and tune up the beam
at the target. - Check RTBT BLMs, BCMs, BPMs, WSs.
- Ramp beam current up to 1 Hz, 1013 ppp, and
declare success in meeting CD-4!
10Ramp up to high power operations
- After CD-4 need to ramp up to high power
operations. - 3 kW in 06, 50 150 kW in 07, 300 800 kW in
08, 1200 1400 kW in 09. - Primary goals run ring with acceptable beam loss
(1 W/m of uncontrolled loss) and deliver beam to
target with correct size and position. - Tools needed to achieve these goals
- Diagnostics to measure beam loss, beam lifetime.
- Fast and slow BLM system.
11Ramp up to high power operations (cont.)
- Diagnostics to measure lattice functions
(betatron functions, dispersion functions,
chromaticity). Needed to fine-tune ring lattice. - BPM system, single shot and multi-turn
accumulation. - Kicker system would allow more accurate
measurements and lattice function measurements at
higher beam powers. - Measure orbit response matrix (closed orbit,
phase, tune, betatron amplitude vs. steering
magnet and quad magnet variation). - With 200 turns can get good measurement of phase
advance, used to verify/optimize quad settings.
12Ramp up to high power operations (cont.)
- Diagnostics to measure chromaticity ( magnets to
control it). Needed to adjust chromaticity toward
zero. - BPM system.
- Kicker system would allow more accurate
measurements at higher beam powers. - Measure tune vs. injection energy.
- Diagnostics to measure beam energy.
- Fast BCM and/or wall current monitor.
- Measure revolution period for a few hundred turns
after end of injection, with rf off. - Diagnostics to measure beam halo.
- Halo scrapers.
- Beam losses caused by halo will likely be the
ground on which we spend most of our time
fighting.
13Ramp up to high power operations (cont.)
- Diagnostics to measure structure resonances (
magnets to control them). - Loss monitor system.
- BPM system (and kicker system preferred).
- Measure beam loss (and tune) as move
low-intensity tune across resonance line. - Diagnostics to measure longitudinal profile.
- Needed to verify MEBT chopper frequency.
- Needed to set up 1st harmonic rf system and 2nd
harmonic rf. - Fast BCM and/or wall current monitor.
- Tune phase to get symmetric bunch shape.
- Tune amplitude to keep gap clear of beam.
14Ramp up to high power operations (cont.)
- Diagnostics to measure evolution of beam profile.
- WS in extraction line, or non-intercepting beam
profile monitor, e.g. IPM (preferred). - Verify that injection painting is working as
planned. - Diagnostics to measure coherent space charge tune
shift. - Coherent tune kicker.
- Measure tune as a function of beam intensity.
- Diagnostics to measure beam in gap.
- Halo scrapers BIG kicker.
- Diagnostics needed to address electron cloud
issues. - Electron probes.
- Wide bandwidth BPM.
15Ramp up to high power operations (cont.)
- Diagnostics to estimate incoherent tune, tune
spread. - 50 MHz dipole kicker/pickup.
- Quadrupole kicker/pickup.
- Diagnostics to measure beam transfer function
- 50 MHz dipole kicer/pickup.
16HEBT/Ring/RTBT diagnostics risk table
17HEBT/Ring/RTBT diagnostics risk table (cont.)
18HEBT/Ring/RTBT diagnostics risk table (cont.)
19Conclusion
- Minimal set of diagnostics needed to reach CD-4
- BPM, BCM, BLM, WS, foil video.
- Diagnostics that would reduce the risk associated
with meeting CD-4 - Coherent tune, IPM, WCM.
- Diagnostics that would reduce the risk associated
with achieving high power operations - 50 MHz dipole kicker pickup, quadrupole kicker
pickup, electron probe, halo scraper/detector,
beam-in-gap kicker, wideband BPM.
20(No Transcript)
21HEBT
22Ring
23RTBT
24(No Transcript)