1
PeopleSoft Stabilization Project StatusIssues
  • Prioritization of Issues Calendar Year End
  • Payroll Task Force
  • Testing for W2 processing in January
  • General Ledger posting
  • Accounts Payable patches installed to clear
    backlog
  • Benefits Administration open enrollment,
    deductions issues
  • Impact Not everything we know is being worked on
    right now
  • First Quarter 2007
  • Target Majority of payroll items cleared up
  • Process W2s (January 2007)
  • Commence Budget, Purchase Order rollover
  • Prepare for Fiscal year end close
  • Longer Term
  • Knowledge Transfer / Staffing / Training
  • Clean up backlog of known issues
  • Support / Communications

2
PeopleSoft Stabilization Project Issues
  • Payroll Task Force
  • Roy Childers heading up Payroll Task Force
  • Approx 2,850 issues reported, 400 500 resolved
  • Improved communication to schools
  • Dozens of sources for errors (Contract Pay,
    Benefits / Deductions, multiple others)
  • Target Majority of 2,850 items cleared up by
    March 31, 2007
  • SACC workers retro-pay to July targeted for 12/15
    payroll
  • Approx 4 of checks produced still have some
    error
  • W2, 1099 processing
  • W2s will be as accurate as PeopleSoft Pay
  • Tax updates tested,will be moved to production
    this weekend
  • Test of W2 printing and import of legacy YTD
    numbers nearly complete
  • Need to correct as many Payroll problems as
    possible to make W2s accurate
  • Impact Employee tax return processing

3
PeopleSoft Stabilization ProjectIssues
  • General Ledger posting
  • Progress being made on Nov 14 - July payroll
    posted, now into October 13
  • Month end close for July nearly complete
  • Impact Payroll corrections and Budget accuracy
  • Accounts Payable
  • Backlog of Accounts Payable being worked
  • Financial patches in place matching, budget
    checking now working
  • Impact Aging of vendor payables
  • Benefits Administration
  • Open enrollment data being posted to PeopleSoft
  • Still need to correct data sent to service
    providers
  • Improve processing of HR, Payroll, Benefits
  • Impact Inaccurate reporting of some employee
    benefits, vendor payments and posting

4
PeopleSoft Stabilization ProjectSupport People,
Process, Technology
  • ERP Support Organization
  • Draft organization chart completed
  • New functional, technical hires in process, but
    still open
  • Departments managing issues backlog with
    consultants
  • Focused on prioritizing and working issues
  • Consultants to support functional areas
  • Functional areas do not have expertise, and are
    short staff
  • Staffing
  • 3 Technical, 5 Functional positions (targeted to
    be in place 11/9)
  • Only 2 in place (6 still open) 2 offers pending
  • Focusing on pursuing resources
  • Lost over 1000 hours in resources to clear up
    backlog
  • Impact Inhibits issue resolution, knowledge
    transfer, user support

5
PeopleSoft Stabilization Project Status Support
People, Process, Technology
  • Correct process problems
  • HR / Payroll / Benefits need to be tightly
    integrated
  • Commenced weekly meetings
  • Impact Improved processing of all areas, fewer
    errors moving forward
  • User Community
  • Elementary, Middle, High School Principals
  • Department Heads, Employees
  • Will be commencing road shows during December
  • Impact Better communications and setting of
    priorities
  • Technology
  • PeopleSoft patches installed, tested
  • Impact Alleviate backlog of some issues, free
    resources for other items

6
PeopleSoft Stabilization ProjectSummary
  • 2006 Calendar Year End
  • Clear up major Payroll Items
  • General Ledger posting Payrolls, month end
  • Reduce AP backlog
  • Open Enrollment posting (Benefits)
  • First Quarter - 2007
  • Majority of payroll items cleared up
  • Process W2s (January 2007)
  • Commence Budget, Purchase Order rollover
  • Prepare for Fiscal year end close
  • Longer Term
  • Support / knowledge transfer
  • User Community, Communications
  • Training