Presentation to the 40th - PowerPoint PPT Presentation

1 / 27
About This Presentation
Title:

Presentation to the 40th

Description:

Trailers had been periodically sited in and around process areas handling highly ... Trailer Siting ... Trailers are not generally designed to protect the ... – PowerPoint PPT presentation

Number of Views:40
Avg rating:3.0/5.0
Slides: 28
Provided by: ryanw8
Category:

less

Transcript and Presenter's Notes

Title: Presentation to the 40th


1
Presentation to the 40th Loss Prevention
Symposium
CSB Investigation of the Explosionsand Fire at
the BP Texas City Refinery on March 23, 2005
CSB Lead Investigator Don Holmstrom
April 26, 2006 Orlando, Florida
2
Disclaimer
  • The PowerPoint presentation is given for general
    informational purposes only. The presentation
    represents the individual views of the Board
    member and all references, conclusions or other
    statements regarding current on going CSB
    investigations are preliminary in nature and do
    not represent a formal adopted product of the
    entire Board. Users of this presentation should
    also note that the contents were compiled solely
    for this presentation. For specific and accurate
    information on completed investigations, please
    refer to the final printed version by going to
    the CSB website at www.csb.gov. and clicking on
    the specific report desired under completed
    investigations

3
Incident Summary
  • March 23, 2005
  • Flammable vapor cloud, explosions, fire, and
    toxic release
  • 15 deaths
  • 170 injuries
  • Offsite property damage

4
Incident Summary
  • Occurred during startup
  • Tower overfilled and overpressured
  • Blowdown drum filled
  • Vapor cloud formed
  • Trailers too close to blowdown drum

5
(No Transcript)
6
Preliminary Findings
7
Trailer Siting
  • All of the fatalities and many of the serious
    injuries occurred in or around the nine
    contractor trailers that were sited near process
    areas and as close as 121 feet from the isom
    blowdown drum
  • Trailers had been periodically sited in and
    around process areas handling highly hazardous
    materials for reasons of convenience such as
    ready access to work areas

8
Trailer Siting
  • Trailers were placed in an unsafe location, too
    close to a process unit handling highly hazardous
    materials

9
Trailer Siting
  • Under BPs siting policy, trailers used for short
    periods of time such as turnaround trailers were
    considered as posing little or no danger to
    occupants
  • This approach conforms with the safety guidance
    published in Recommended Practice 752 by the
    American Petroleum Institute (API)

10
Trailer Siting
  • API 752 provides no minimum safe distances from
    process hazards for the location of trailers used
    in refineries and other chemical facilities
  • Trailers are not generally designed to protect
    the occupants from fire and explosion hazards

11
The CSB issued urgent recommendations to API and
NPRA on ensuring the safe location of occupied
trailers away from hazardous process areas
12
Unit Start-up Mechanical Integrity Issues
  • The raffinate splitter tower was started up
    despite malfunctioning key process
    instrumentation and equipment on the day of the
    incident
  • Tower level indicator and sight glass
  • Tower high level alarm
  • Blowdown drum high level alarm
  • Tower 3 lb. pressure valve

13
Unit Start-up Mechanical Integrity Issues
  • Proper working order of key process
    instrumentation was not checked as required by
    the start-up procedure
  • Unit operations management turned away instrument
    technicians and signed off on the checks as if
    they had been completed
  • The unit should not have been started up with
    existing malfunctions of the level indicator,
    level alarm, and a control valve

14
Unit Start-ups
  • Operations personnel did not open the tower level
    control valve at the time specified in the
    start-up procedures the operator did not balance
    the flow of hydrocarbons in and out of the tower
  • The tower level was actually rising rapidly for
    three hours
  • A false level indication showing the tower level
    declining was a factor in the delay in removing
    liquid from the tower

15
Unit Start-ups
  • Start-up procedures did not address the
    importance of maintaining a balance of
    hydrocarbon flow in and out of the tower
  • The tower was not equipped with additional
    instrumentation indicating tower level

16
A History of Abnormal Unit Start-ups
  • In 16 startups of the ISOM unit from April 2000
    to March 23, 2005
  • Eight experienced at least two times the normal
    pressure (gt 40 psi vs. 20 psi)
  • Thirteen had liquid levels above the range of the
    level indicator (gt 10 ft, some lasting as long as
    four hours)

17
A History of Abnormal Unit Start-ups
  • BP did not investigate previous raffinate
    splitter tower start-ups with high pressures and
    high levels, despite being required by BP policy
  • Investigations of these incidents could have
    resulted in improvements to tower design,
    instrumentation, procedures, and controls

18
Management Oversight and Accountability
  • BP management did not assure that an experienced
    supervisor was in the unit during startup to
    provide oversight, as specified in BP policies
  • At 10 am the supervisor in charge left the unit
    for a family emergency, but no substitute with
    ISOM operating experience was assigned

19
Process Design
  • The blowdown drum and stack were outdated and
    unsafe because they released flammable
    hydrocarbons to the atmosphere that ignited
    rather than to a safe location, such as a flare
    system

20
Process Design
  • Amoco safety standards last revised in 1994 state
    that blowdown drums should be connected to a
    flare when major modifications are made
  • In 1997, Amoco replaced the blowdown drum and
    stack with identical equipment rather than
    connecting the drum to a safer location such as a
    flare system
  • After the merger in 1999, BP adopted the Amoco
    safety standard for blowdown drums

21
Process Design
  • In 2002, BP evaluated connecting the blowdown
    drum to a flare system as part of an
    environmental initiative but did not pursue this
    option

22
Previous Blowdown Drum and Stack Incidents
  • In 1992, OSHA cited and fined Amoco on the
    hazardous design of a similar blowdown drum and
    stack at the Texas City refinery
  • In a settlement agreement, OSHA withdrew the
    citation and the fine, and the refinery continued
    to use blowdown drums without flares

23
Previous Blowdown Drum and Stack Incidents
  • Since 1995, four releases from the blowdown drum
    sent hydrocarbons to the stack and sewer,
    generating flammable vapor clouds at ground level

24
Vehicles
  • BPs traffic policy allowed vehicles unrestricted
    access near process units
  • Approximately 55 vehicles were located in the
    vicinity of the blowdown drum and stack
  • Two running vehicles may have provided sources of
    ignition for the incident one was within 25 feet
    of the blowdown drum

25
The CSB issued an urgent recommendation that BP
form an independent panel to study their safety
culture.
26
Future Investigative Activities
  • Analyze root causes and develop additional safety
    recommendations
  • Issue final report at public meeting in Texas
    City in Fall 2006

27
  • Questions
Write a Comment
User Comments (0)
About PowerShow.com