Title: Presentation to the 40th
1Presentation to the 40th Loss Prevention
Symposium
CSB Investigation of the Explosionsand Fire at
the BP Texas City Refinery on March 23, 2005
CSB Lead Investigator Don Holmstrom
April 26, 2006 Orlando, Florida
2Disclaimer
- The PowerPoint presentation is given for general
informational purposes only. The presentation
represents the individual views of the Board
member and all references, conclusions or other
statements regarding current on going CSB
investigations are preliminary in nature and do
not represent a formal adopted product of the
entire Board. Users of this presentation should
also note that the contents were compiled solely
for this presentation. For specific and accurate
information on completed investigations, please
refer to the final printed version by going to
the CSB website at www.csb.gov. and clicking on
the specific report desired under completed
investigations
3Incident Summary
- March 23, 2005
- Flammable vapor cloud, explosions, fire, and
toxic release - 15 deaths
- 170 injuries
- Offsite property damage
4Incident Summary
- Occurred during startup
- Tower overfilled and overpressured
- Blowdown drum filled
- Vapor cloud formed
- Trailers too close to blowdown drum
5(No Transcript)
6Preliminary Findings
7Trailer Siting
-
- All of the fatalities and many of the serious
injuries occurred in or around the nine
contractor trailers that were sited near process
areas and as close as 121 feet from the isom
blowdown drum - Trailers had been periodically sited in and
around process areas handling highly hazardous
materials for reasons of convenience such as
ready access to work areas
8Trailer Siting
- Trailers were placed in an unsafe location, too
close to a process unit handling highly hazardous
materials
9Trailer Siting
- Under BPs siting policy, trailers used for short
periods of time such as turnaround trailers were
considered as posing little or no danger to
occupants - This approach conforms with the safety guidance
published in Recommended Practice 752 by the
American Petroleum Institute (API)
10Trailer Siting
- API 752 provides no minimum safe distances from
process hazards for the location of trailers used
in refineries and other chemical facilities - Trailers are not generally designed to protect
the occupants from fire and explosion hazards
11The CSB issued urgent recommendations to API and
NPRA on ensuring the safe location of occupied
trailers away from hazardous process areas
12Unit Start-up Mechanical Integrity Issues
- The raffinate splitter tower was started up
despite malfunctioning key process
instrumentation and equipment on the day of the
incident - Tower level indicator and sight glass
- Tower high level alarm
- Blowdown drum high level alarm
- Tower 3 lb. pressure valve
13Unit Start-up Mechanical Integrity Issues
- Proper working order of key process
instrumentation was not checked as required by
the start-up procedure - Unit operations management turned away instrument
technicians and signed off on the checks as if
they had been completed - The unit should not have been started up with
existing malfunctions of the level indicator,
level alarm, and a control valve
14Unit Start-ups
- Operations personnel did not open the tower level
control valve at the time specified in the
start-up procedures the operator did not balance
the flow of hydrocarbons in and out of the tower - The tower level was actually rising rapidly for
three hours - A false level indication showing the tower level
declining was a factor in the delay in removing
liquid from the tower
15Unit Start-ups
- Start-up procedures did not address the
importance of maintaining a balance of
hydrocarbon flow in and out of the tower - The tower was not equipped with additional
instrumentation indicating tower level
16A History of Abnormal Unit Start-ups
- In 16 startups of the ISOM unit from April 2000
to March 23, 2005 - Eight experienced at least two times the normal
pressure (gt 40 psi vs. 20 psi) - Thirteen had liquid levels above the range of the
level indicator (gt 10 ft, some lasting as long as
four hours)
17A History of Abnormal Unit Start-ups
- BP did not investigate previous raffinate
splitter tower start-ups with high pressures and
high levels, despite being required by BP policy - Investigations of these incidents could have
resulted in improvements to tower design,
instrumentation, procedures, and controls
18Management Oversight and Accountability
- BP management did not assure that an experienced
supervisor was in the unit during startup to
provide oversight, as specified in BP policies - At 10 am the supervisor in charge left the unit
for a family emergency, but no substitute with
ISOM operating experience was assigned
19Process Design
- The blowdown drum and stack were outdated and
unsafe because they released flammable
hydrocarbons to the atmosphere that ignited
rather than to a safe location, such as a flare
system
20Process Design
- Amoco safety standards last revised in 1994 state
that blowdown drums should be connected to a
flare when major modifications are made - In 1997, Amoco replaced the blowdown drum and
stack with identical equipment rather than
connecting the drum to a safer location such as a
flare system - After the merger in 1999, BP adopted the Amoco
safety standard for blowdown drums
21Process Design
- In 2002, BP evaluated connecting the blowdown
drum to a flare system as part of an
environmental initiative but did not pursue this
option
22Previous Blowdown Drum and Stack Incidents
- In 1992, OSHA cited and fined Amoco on the
hazardous design of a similar blowdown drum and
stack at the Texas City refinery - In a settlement agreement, OSHA withdrew the
citation and the fine, and the refinery continued
to use blowdown drums without flares
23Previous Blowdown Drum and Stack Incidents
- Since 1995, four releases from the blowdown drum
sent hydrocarbons to the stack and sewer,
generating flammable vapor clouds at ground level
24Vehicles
- BPs traffic policy allowed vehicles unrestricted
access near process units - Approximately 55 vehicles were located in the
vicinity of the blowdown drum and stack - Two running vehicles may have provided sources of
ignition for the incident one was within 25 feet
of the blowdown drum
25The CSB issued an urgent recommendation that BP
form an independent panel to study their safety
culture.
26Future Investigative Activities
- Analyze root causes and develop additional safety
recommendations - Issue final report at public meeting in Texas
City in Fall 2006
27