Title: Aucun titre de diapositive
1May 11, 2006
Subtitle (Arial 22)
Hydropower Refurbishment Alstoms Methodology
and Case Studies
Presented By Naresh Patel ( Electrical) Sreenivas.
V ( Mechanical)
- Add text to be highlighted here -
2Introduction
- Alstom Power Hydro Products
- Descended from Neyrpic, ASEA, BBC, Alsthom
- Over 100 years experience in hydro industry
- Engg Mfgg in Americas, Europe Asia
- Presence in Asia Includes
- Turbine, Generator, Hydro Mech, PS, BoP
- Design Mfgg in Tianjin, China
- Design Mfgg in Vadodara, India
3The Need for Refurbishment
- Repair, Modernize Uprate
- Repair Equipment failure results in units out
of service / operating at derated output - Most compelling of refurbishment drivers
- Issue Return to full service quickly
- Solution Often a temporary band-aid
- If quick fix not possible, modernize and uprate
options should be considered
4We should have done this last year as a planned
outage!
5The Need for Refurbishment
- Repair, Modernize Uprate
- Modernize Apply new technology, materials and
calculation techniques - Normally done in conjunction with other
refurbishment work - Example Uprate field-coil insulation during a
stator rewind - Example - Install self-lubricating bushings
during runner replacement
6The Need for Refurbishment
- Repair, Modernize Uprate
- Uprate Increase the output capability of the
generating unit - Most economically feasible of drivers
- Typically 15 to 40 uprate without civil-works
modification - Minimum scope usually involves runner replacement
and new stator core winding - BoP modifications have to be considered
7GENERATOR LIFE CYCLE
8Refurbishment Methodology
- General Philosophy
- Refurbishment presents more challenging design
requirements than that of new units - Interfaces between old new equipment have to be
considered - Existing unit must be synthesized
- Collection of reliable data for existing units is
absolutely necessary for a successful project
9Refurbishment Methodology
- Data Collection
- Review of specification and data from spec
- Site visit absolutely necessary for
- Measurements and visual inspection of unit
- Assess the installation environment limitations
- Collection of additional data, eg maintenance
records, test operational data, OEM drawings,
etc. - Discussion of refurbishment requirements and Q
A with customer engineers - Duration of site visit is scope dependent and can
last from a few hours to a few days
10Generator Specific Methodology
- Proposal Design
- Refurbishment of the generator and turbine parts
will be presented here separately, but the shaft
coupling is an important interface for matching
of capability and maximum speed. Generator and
turbine design are performed together - Relatively short time for design
- Synthesis of existing design required with
accurate model of components to be kept - Model of existing design is modified for
refurbished parts - Modeling is only rigorous enough to ensure the
solution will work and to guarantee performance
11Generator Specific Methodology
- Basic and Detailed Design
- Continuation of the proposal design
- A second site visit is essential
- Additional generator testing may be required to
validate the model of existing unit - Analysis is much more rigorous and can include
electromagnetic mechanical FEM studies - Interface issues are resolved during detailed
design
12Generator Specific Methodology
- Synthesis of Existing Generator
- Required data are rarely all available
- Physical model is created from dimensions given
in spec and from site visit - Electromagnetic model, including excitation
requirements and reactances are correlated to
test operational data - Thermal model, including ventilation
configuration and airflow are correlated to
measured temperatures losses - Throughout the synthesis, measured data are used
to deduce unknown dimensions and material
properties - Additional tests may be required after award of
contract
13Modeling of the Refurbishment
- New Winding
- Small scope with very little design space
- Optimize temperature (output) and efficiency
- Slot dimensions are fixed so the only variables
are - Insulation thickness (design for hipot or VET)
- Strand dimensions
- Typically a 15 uprate is possible if replacing
asphalt bars or coils - Upgrade field insulation during outage
14Modeling of the Refurbishment
- New Core Winding
- This scope allows a change in winding
configuration - Important to identify core-replacement need at
time of tendering through inspection or El Cid
test or by the age of the core
15Allatoona Stator Core 45 Years Old
16Modeling of the Refurbishment
- New Core Winding
- This scope allows a change in winding
configuration - Important to identify core-replacement need at
time of tendering through inspection or El Cid
test - Possible to achieve large increase in efficiency
17STATOR-STEEL QUALITY
18Modeling of the Refurbishment
- New Core Winding
- This scope allows a change in winding
configuration - Important to identify core-replacement need at
time of tendering through inspection or El Cid
test - Possible to achieve large increase in efficiency
- Possible to eliminate noise problems
- Keying and clamping system should be replaced
- Effective soleplate modifications not usually
possible unless frame also replaced, i.e. new
stator
19Modeling of the Refurbishment
- New Poles and Field Coils
- In conjunction with a new stator ventilation
modifications, can allow up to a 40 uprate - Torque transmission of other components plus BoP
has to be checked explicitly for gt15 uprate
20Modeling of the Refurbishment
- Refurbishment with Larger Scope
- Begins to look like design for a new machine with
fewer interfaces, fewer dimensional and
performance limits - In these cases, the limits are given by the civil
works and balance-of-plant components - Optimization of performance and output has much
higher opportunity
21Generator Case Studies
- Rocky Reach, Units 1-7
- Customer Chelan County PUD, Washington State
- Existing unit - 120 MVA, 15 kV, 90 rpm, 0.95 pf
- Airgap instability
- Stator-core buckling
- Increase of efficiency
- Some units noisy, gt 95 dB
- Life extension / increased availability
- Scope new stators rotors - everything except
shaft, brackets bearings
22Rocky Reach, Units 1-7
- Design Requirements
- High efficiency main design driver
- US55k / kW evaluation, US70k / kW penalty
- Airgap shape tolerances one half of IEC/CEA
standard - Low audible noise, lt80 dB 1 m from housing
- High evaluation for short outage
23Rocky Reach, Units 1-7
- Design Solutions High Efficiency
- 30 more active material than benchmark,
- Increase frame OD to accommodate larger core
frame radial clearance in housing reduced to
limit - Losses temperatures very low, so ventilation
system can be optimized for efficiency not
cooling - Airgap reduced to allowable SCR limit of 0.8
- Relative to existing machine, the efficiency was
increased by 0.5 to almost 99
24Rocky Reach, Units 1-7
- Design Solutions Airgap Stability Shape
- Rim shrunk for full, off-cam runaway speed
- Oblique elements used on spider and frame
- Double dovetail design used for precise setting
of stator keybars - Rotor poles individually shimmed to high
circularity tolerance
25Rocky Reach, Units 1-7
- Design Solutions Noise Outage Time
- Frame stator core stiffened with radial depth
and higher core clamping pressure - Outage reduced by constructing both rotor and
stator in erection bay - Last (fourth) unit had only 45 days between
commercial service of existing and refurbished
units - All guaranteed performance requirements were met
26Generator Case Studies
- Crystal Power Plant, Unit 1
- Customer US Bureau of Reclamation, Colorado
- Existing unit - 28 MVA, 11.0 kV, 257 rpm, 1.0 pf
- Realize uprate potential
- Increase reactive capability for black-start,
line charging - Generator and turbine refurbishment for reduced
maintenance costs - New rating 35 MVA, 0.9 pf
27Crystal Power Plant, Unit 1
- Design Requirement
- Contract requirement for 80 K field-temperature
rise - Existing unit had 75 K limit, which it could not
meet - 25 increase in MVA
- Power factor change from unity to 0.9 over
excited - 12.5 increase in MW
28Crystal Power Plant, Unit 1
- Interface Requirements / Design Space
Restrictions - Existing soleplates
- Housing diameter
- Rotor outer diameter and axial length
- Upper bracket and deck plates
29Crystal Power Plant, Unit 1
- Design Solutions Field Temperature-Rise Limit
- Do all possible to reduce excitation requirements
- Re-insulate field with Class F material
- Increase series turns by 20 - tooth x-section
reduction more than compensated - Increase radial depth of stator core
- Reduce airgap length
- Performance testing last year measured a field-
temperature rise of 78 K
30 Turbine
31Turbine methodology
- Tender stage
- Simplified analysis of main components (Spiral
case, stay vanes, distributor, runner and draft
tube) - Geometrical comparison between existing design
and manufacturing references - Hydraulic transient calculation
- Cavitation studies
- Search solutions for specifics problems (frequent
mechanical failures, silt abrasion, operational
instability and others) - Define the future turbine performance
(guarantees)
Short term analysis (Basic studies with simple
tools)
32Turbine methodology
- Design stage
- Measurement of existing performance
- Deeply inspection of all components of machine
- Fluid Dynamic analysis of the static components
(Spiral Case, Stay Vane, Distributor and Draft
tube) - Design of some new profiles to improve the flow
behavior (stay vane, wicket gates and draft tube) - Comparison of existing and new design (CFD)
- Development of new runner (genetic algorithm)
- Model test to validate the results
Deeply analysis and experience of specialist to
reach targets
33Turbine methodology
- Stay vane and Wicket Gate Optimization
CFD remain the main tool for analysis
34Turbine methodology
Draft tube study
Stream Line analysis
Existing
Modified
Flow velocity in a sectional elevation view of
the existing draft tube elbow.
When technically available modification in Draft
tube provide good results
35Turbine methodology
Runner development
Classical runner
Final runner
Blade profile is developed using an evolutionary
algoritm and the experience of a hydraulic
engineer
Good Accuracy between CFD calculation and model
test
36St-Lawrence Rehab Project
- St-Lawrence Power Project
- 32 propeller units (16 NYPA and 16 OPG)
Two turbine designs BLH 8 runners Ø5.8m (229
in.) 77.5 ? 85 kHp (63.4MW) AC
8 runners Ø6.1m (240 in.) 79 kHp
Targets - Increase overall efficiency -
Translation of the peak efficiency to higher
load - Reduction of erosion by cavitation -
Increase of the stability of the turbine
Ambitious targets
37St-Lawrence Rehab Project
- Main modification ? New Runner
- Development using the Alstom methodology
- Twisted blade shape
Runner developed to reach targets and solve the
old design problems
38St-Lawrence Rehab Project
Sigma break curve at full load up to the maximal
flow allowed by contract near the rated net head
for the refurbishment of ST. LAWRENCE Power Plant.
39St-Lawrence Rehab Project
- Acceptance model test cavitation
New runner
Old runner
New Existing runner for St. LAWRENCE power
plant at the rated net head, full load and plant
sigma value (model runner manufactured by ASTRÖ).
40St-Lawrence Rehab Project
Accurate manufacturing the reach the results
41St-Lawrence Rehab Project
New rated output 63.4 MW Cavitation behavior
improved Better stability Best efficiency in the
higher load
After commissioning confirmation of targets
42Conclusion
- Refurbishment is required to extend life of
aging equipments and increase the value of
equipment to the owner in terms of performance
(higher output and efficiency, greater
availability) - Presented Alstom case studies demonstrate the
methodology success - Integration between Generator and Turbine is
essential for good results in refurbishment
projects - Alstom methodology has been efficient for
projects in all the corners of the world
43(No Transcript)