Title: Progress Report


1
  • Progress Report
  • 900 MHz NMR Probe Cryogenic Gas Supply System
  • Team 2
  • Rebecca Altman
  • Jason Kitchen
  • Zachary Stevenson
  • Jessica Vanterpool
  • January 29th, 2009

2
Presentation Outline
  • Project overview
  • Changes in project scope
  • Baseline testing of system performed last week
  • Assembly and fabrication progress
  • Purchase summary
  • Upcoming tests of system

Team with Dr. Brey in front of 900 MHz magnet
3
Project Overview
  • Improve efficiency of existing cold gas delivery
    system to cool NMR samples to 103 K, with 0.2 K
    temperature regulation
  • Design an automatic refill controller so liquid
    nitrogen heat exchanger cryostat will remain full
    during long duration NMR experiments

Cold gas delivery system schematic
4
System Hardware
5
Project Scope Update
  • Contacted Cryofab Inc. with the details of our
    design for the NMR probe dewar
  • Lead time on the manufacture of the new dewar is
    8 weeks
  • Not enough time to assemble and test as a part of
    this project
  • Based on sample temperature measurements of 106 K
    achieved last week, redesign of probe dewar no
    longer a priority
  • Sponsors and team both agree to shift this focus
    to maintaining sample temperature stability
    during cryogen refill

Rigid stainless steel probe dewar
6
January 21, 2009 NMR Test on 900 MHz magnet
  • Purpose of test was to compare probes T-type
    thermocouple measurement to sample temperature
    and calculate ?T
  • Test used lead nitrate spinning at 5.0 0.1 kHz
    to detect 207Pb spectrum
  • NMR signal peak shift is temperature dependent,
    approximately 0.753 ppm / C

Bielecki, 1995
7
January 21, 2009 Experimental Results
  • Lowest achievable sample temperature was 105.9
    0.1 K
  • Unexpected results showed average ?T of -8.8
    2.7 C from thermocouple to sample, could be from
    N2 gas rapid expansion in stator

8
January 23, 2009 NMR Test on 900 MHz magnet
  • Purpose of test was to confirm probe could
    achieve a stable temperature target by detecting
    NMR spectra of a sample with a well-known phase
    transition at a particular temperature
  • Test used single crystal ammonium dihydrogen
    phosphate (ADP) spinning at 5 kHz to detect 31P
  • ADP undergoes a solid phase transition at its
    Curie point, becoming antiferroeletric at
    approximately 148 K

Sen, 2007
Sen, 2007
Sen, 2007
9
January 23, 2009 Experimental Results
  • NMR spectrum showed the phase transition at a
    probe thermocouple temperature of approximately
    156 K
  • 156 K average ?T 147.2 K confirming lead
    nitrate test ?T

Temperature regulation interface
10
Assembly Progress
  • HX (Heat Exchanger) fabrication
  • Design modification
  • Single set of coils easier to fabricate than
    concentric dual coils, so 13 coils were made
    instead of 8 inner and 8 outer coils
  • Coils were then attached to bottom of the HX
    using brass compression fittings (leak tight in
    LN2)

13 loop HX
11
Assembly Progress
  • Refill Controller
  • Rear plate and component mounting board machining
    is complete
  • Nut rivet inserts installed in component board
  • Single switch relay and the barrier terminal
    block were screwed onto the board
  • Board screwed onto box

12
Assembly Progress
  • Solenoid Valve
  • 110 V AC cryogenic rated solenoid valve
  • Wires were soldered to electrical connection,
    shell of connector is threaded so valve cannot
    become accidentally unplugged
  • Strain-relief grommet was added to valve so wires
    will not break free

13
Purchase Summary
  • Total dollars spent to date for refill
    controller 340
  • All components have been received for refill
    controller
  • Need to price pneumatically-actuated cryogenic
    valves
  • Need to price a standard vacuum insulated
    transfer line for connection between supply dewar
    and HX cryostat

14
Planned Testing
  • February 2nd Run system to determine rate at
    which LN2 is consumed by the HX
  • February 10th Run system venting N2 vapor inside
    cryostat past the HX precooling coils
  • Compare to rate of normal LN2 consumption
  • Determine what effect precooling has on the
    sample temperature
  • February 10th Test new 13 loop HX coils
  • Confirm temperature output for given flow rate
  • February 17th Run system and vary time between
    refills
  • Compare sample temperature stability during a
    long refill period with a short refill period

15
Summary
  • Experimental results show system can achieve 106
    K, temperature difference between thermocouple
    and sample verified by ADP test
  • Based on experimental temperature results and
    vendor lead-time, redesigned probe dewar removed
    from project scope
  • Temperature fluctuations over 2 K during start
    of refills adds a new task to improve system
    performance
  • Assembly of refill controller on schedule, should
    be completed by middle of February for later
    testing of automatic refills
  • Pneumatic actuated valves need to be researched
    and purchased due to concerns of solenoid valve
    in 900 MHz magnetic field